Guernsey Power Station

Source 📝

229:
Regulatory filings were originally submitted in 2016 to take advantage of decreasing natural gas costs, but construction was delayed until 3rd quarter 2019. The power plant sits atop a former coal mine, and was selected in part due to its proximity to the Rockies Express East natural gas pipeline
220:
The facility uses three of General Electric’s advanced gas turbines, each with a heat recovery steam generator and steam turbine generator and will produce electricity equivalent to the power needs of approximately 1.4 million homes within the PJM region.
390: 449: 237:. In June 2020, local union construction workers protested the use of out-of-state non-union workers on the project instead of the completely local workforce promised. A company spokesperson denied the allegations. 216:
The electric generating facility will sell energy and capacity into the PJM market. PJM is the regional transmission organization that coordinates the movement of wholesale electricity in 13 states, including Ohio.
382: 537: 441: 326: 419: 612: 470: 533: 210: 492: 108: 617: 593: 360: 53: 240:
After construction is complete, the plant is expected to provide about 30 full-time jobs, according to a local newspaper's interview with a
632: 513: 247:
While the first unit was scheduled to go online in September 2022, initial start up activity was still underway as of December 2022.
234: 209:
in the heart of the Utica and Marcellus shale region. It generates 1.875 GW of power, enough to power 1.5 million homes. It's the
318: 194: 41: 411: 627: 586: 233:
Construction is expected to create up to 1,000 jobs. Taxes paid during construction will also pay for new buildings at
383:"An Ohio couple eyed retirement and their racehorses. Then a natural gas power plant moved in, and it all changed" 622: 579: 260: 267: 352: 567: 484: 293: 198: 442:"'We got plenty of local help': Local laborers protest out-of-state workers at power plant" 8: 514:"December 13, 2022 – Notice of Upcoming Start Up Activity – Guernsey Power Station" 270: 241: 104: 534:"Caithness Energy Orders GE's HA Gas Turbines for Guernsey Power Station in Ohio" 274: 206: 563: 123: 606: 68: 55: 31: 180: 256: 471:"Guernsey Power Station slated to be fully operational in December 2022" 485:"Electric Power Monthly - U.S. Energy Information Administration (EIA)" 171: 319:"Massive Natural Gas-Fired Power Plant Moving Forward in Ohio" 273:
7HA.02 gas turbines. Water for operation will be provided by
213:
in the United States. The plant cost $ 1.7 billion to build.
202: 562:
This article about a United States power station is a
412:"$ 1.6B financing obtained for Guernsey Power Station" 353:"Guernsey Power Station, Guernsey County, Ohio, USA" 613:Buildings and structures in Guernsey County, Ohio 604: 587: 594: 580: 439: 266:Power will be generated by three advanced 255:GPS will receive its natural gas from the 618:Natural gas-fired power stations in Ohio 277:which will then process the wastewater. 316: 605: 380: 557: 440:GARABRANDT, KRISTI R. (2020-05-01). 347: 345: 343: 13: 14: 644: 633:United States power station stubs 340: 172:https://guernseypowerstation.com/ 540:from the original on 2021-01-27 526: 495:from the original on 2021-01-27 452:from the original on 2021-01-27 422:from the original on 2021-01-27 393:from the original on 2021-01-27 363:from the original on 2021-01-27 329:from the original on 2020-10-28 230:running from Ohio to Missouri. 506: 477: 463: 433: 404: 374: 310: 286: 1: 317:Cocklin, James (2019-09-04). 294:"ECONOMIC BENEFITS/COMMUNITY" 280: 566:. You can help Knowledge by 263:formations in eastern Ohio. 250: 7: 628:2019 establishments in Ohio 381:Grant, Julie (2020-12-28). 10: 649: 556: 224: 211:69th largest power station 177: 167: 162: 142: 138: 133: 122: 114: 100: 92: 84: 47: 37: 27: 23: 18: 387:StateImpact Pennsylvania 323:Natural Gas Intelligence 298:guernseypowerstation.org 147:Make and model 235:Meadowbrook High School 93:Construction began 446:The Daily Jeffersonian 416:The Daily Jeffersonian 191:Guernsey Power Station 69:39.93750°N 81.535028°W 19:Guernsey Power Station 623:Guernsey County, Ohio 195:gas-fired power plant 150:GE 7HA.02 Gas Turbine 134:Power generation 42:Valley Township, Ohio 357:nsenergybuisness.com 74:39.93750; -81.535028 163:External links 124:Combined cycle 65: /  155:Units planned 575: 574: 188: 187: 640: 596: 589: 582: 558: 549: 548: 546: 545: 530: 524: 523: 521: 520: 510: 504: 503: 501: 500: 481: 475: 474: 467: 461: 460: 458: 457: 437: 431: 430: 428: 427: 408: 402: 401: 399: 398: 378: 372: 371: 369: 368: 349: 338: 337: 335: 334: 314: 308: 307: 305: 304: 290: 242:Caithness Energy 181:edit on Wikidata 109:Apex Power Group 105:Caithness Energy 80: 79: 77: 76: 75: 70: 66: 63: 62: 61: 58: 16: 15: 648: 647: 643: 642: 641: 639: 638: 637: 603: 602: 601: 600: 554: 552: 543: 541: 532: 531: 527: 518: 516: 512: 511: 507: 498: 496: 483: 482: 478: 469: 468: 464: 455: 453: 438: 434: 425: 423: 410: 409: 405: 396: 394: 379: 375: 366: 364: 351: 350: 341: 332: 330: 315: 311: 302: 300: 292: 291: 287: 283: 261:Marcellus shale 253: 227: 199:Guernsey County 184: 107: 73: 71: 67: 64: 59: 56: 54: 52: 51: 12: 11: 5: 646: 636: 635: 630: 625: 620: 615: 599: 598: 591: 584: 576: 573: 572: 551: 550: 536:. 2019-09-09. 525: 505: 476: 462: 432: 418:. 2019-08-30. 403: 373: 339: 309: 284: 282: 279: 268:combined-cycle 252: 249: 226: 223: 186: 185: 178: 175: 174: 169: 165: 164: 160: 159: 156: 152: 151: 148: 144: 143: 140: 139: 136: 135: 131: 130: 127: 120: 119: 116: 112: 111: 102: 98: 97: 94: 90: 89: 86: 82: 81: 49: 45: 44: 39: 35: 34: 29: 25: 24: 21: 20: 9: 6: 4: 3: 2: 645: 634: 631: 629: 626: 624: 621: 619: 616: 614: 611: 610: 608: 597: 592: 590: 585: 583: 578: 577: 571: 569: 565: 560: 559: 555: 539: 535: 529: 515: 509: 494: 490: 486: 480: 472: 466: 451: 447: 443: 436: 421: 417: 413: 407: 392: 388: 384: 377: 362: 358: 354: 348: 346: 344: 328: 324: 320: 313: 299: 295: 289: 285: 278: 276: 272: 269: 264: 262: 258: 248: 245: 243: 238: 236: 231: 222: 218: 214: 212: 208: 204: 200: 196: 192: 182: 176: 173: 170: 166: 161: 157: 154: 153: 149: 146: 145: 141: 137: 132: 128: 125: 121: 117: 113: 110: 106: 103: 99: 95: 91: 87: 83: 78: 50: 46: 43: 40: 36: 33: 32:United States 30: 26: 22: 17: 568:expanding it 561: 553: 542:. Retrieved 528: 517:. Retrieved 508: 497:. Retrieved 488: 479: 465: 454:. Retrieved 445: 435: 424:. Retrieved 415: 406: 395:. Retrieved 386: 376: 365:. Retrieved 356: 331:. Retrieved 322: 312: 301:. Retrieved 297: 288: 265: 254: 246: 239: 232: 228: 219: 215: 190: 189: 118:30 - planned 60:81°32′06.1″W 489:www.eia.gov 197:located in 72: / 48:Coordinates 607:Categories 544:2021-01-26 519:2022-12-22 499:2021-01-26 456:2021-01-27 426:2021-01-27 397:2021-01-27 367:2021-01-27 333:2021-01-26 303:2021-01-26 281:References 244:official. 158:3 x 600 MW 57:39°56′15″N 275:Byesville 251:Operation 207:Byesville 205:south of 115:Employees 538:Archived 493:Archived 450:Archived 420:Archived 391:Archived 361:Archived 327:Archived 101:Owner(s) 38:Location 225:History 168:Website 28:Country 193:is a 85:Status 257:Utica 179:[ 564:stub 259:and 203:Ohio 96:2019 88:Open 129:Yes 609:: 491:. 487:. 448:. 444:. 414:. 389:. 385:. 359:. 355:. 342:^ 325:. 321:. 296:. 271:GE 201:, 595:e 588:t 581:v 570:. 547:. 522:. 502:. 473:. 459:. 429:. 400:. 370:. 336:. 306:. 183:] 126:?

Index

United States
Valley Township, Ohio
39°56′15″N 81°32′06.1″W / 39.93750°N 81.535028°W / 39.93750; -81.535028
Caithness Energy
Apex Power Group
Combined cycle
https://guernseypowerstation.com/
edit on Wikidata
gas-fired power plant
Guernsey County
Ohio
Byesville
69th largest power station
Meadowbrook High School
Caithness Energy
Utica
Marcellus shale
combined-cycle
GE
Byesville
"ECONOMIC BENEFITS/COMMUNITY"
"Massive Natural Gas-Fired Power Plant Moving Forward in Ohio"
Archived



"Guernsey Power Station, Guernsey County, Ohio, USA"
Archived
"An Ohio couple eyed retirement and their racehorses. Then a natural gas power plant moved in, and it all changed"
Archived

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.