Knowledge

Britannia Bridge

Source 📝

915: 628: 870:. The superstructure of the new bridge was to include two decks: a lower rail deck supported by steel arches and an upper deck constructed out of reinforced concrete, to carry a new road crossing over the strait. Concrete supports were built under the approach spans and steel archways constructed under the long spans on either side of the central Britannia Tower. The two long spans are supported by arches, which had not been an option for the original structure as a result of the clearance needed for tall-masted vessels; modern navigational requirements require much less headroom. 846:
the lack of an adequate water supply meant they were unable to control the fire, which spread all the way across from the mainland to the Anglesey side. After the fire had burned itself out, the bridge was still standing. However, the structural integrity of the iron tubes had been critically compromised by the intense heat; they had visibly split open at the three towers and had begun to sag. It was recognised that there was still danger of the structure collapsing. As a consequence, the bridge was rendered unusable without the enactment of major restorative work.
606:" It became apparent from Fairbairn's experiments that- without special precautions - the failure mode for the tube under load would be buckling of the top plate in compression, the theoretical analysis of which gave Hodgkinson some difficulty. When Stephenson reported to the directors of the railway in February 1846, he attached reports by both Hodgkinson and Fairbairn. From his analysis of the resistance to buckling of tubes with single top plates, Hodgkinson believed that it would require an impracticably thick (and therefore heavy) top plate to make the tubes 702:; they were only raised by a few inches at a time, after which supports would be built underneath the section to keep it in place. This aspect of the bridge's construction was novel at the time. Reportedly, the innovative process had been responsible for costing Stephenson several nights of sleep at one stage of the project. The work did not go smoothly; at one point, one of the tubes allegedly came close to being swept out to sea before being recaptured and finally pushed back into place. The tubes were manoeuvred into place between June 1849 and February 1850. 659: 510: 37: 587:. Stephenson therefore intended to cross the strait at a high level, over 100 ft (30 m), by a bridge with two main spans of 460-foot-long (140 m), rectangular iron tubes, each weighing 1,500 long tons (1,500 tonnes; 1,700 short tons), supported by masonry piers, the centre one of which was to be built on the Britannia Rock. Two additional spans of 230 ft (70 m) length would complete the bridge, making a 1,511-foot-long (461 m) continuous girder. The trains were to run inside the tubes (inside the 706:
deflection. The tubes had a width of 15 feet (4.5 m) and differed between 23 feet (7 m) and 30 feet (9.1 m) in overall depth, while also having a 10 foot (3 m) gap between them; they were supported on a series of 15-foot-long (4.6 m) cast iron beams that were embedded in the stonework of the towers. To better protect the iron from the weather, an arched timber roof was constructed to cover both tubes; it was roughly 39 feet (12 m) wide, continuous over their whole length, and covered with
518: 532: 618:
determined what the optimum form of the tubular girder should be "I would venture to state that a Tubular Bridge can be constructed of such powers and dimensions as will meet, with perfect security, the requirements of railway traffic across the Straits" although it might require more materials than originally envisaged and the utmost care would be needed in its construction. He believed it would be 'highly improper' to rely upon chains as the principal support of the bridge.
497:, carrying only rail traffic. Over the next eight years more of the structure was replaced, allowing for more trains to run and a second tier to be completed. The second tier was opened to accommodate road traffic in 1980. The bridge was subject to a £4 million four-month in-depth maintenance programme during 2011. Since the 1990s, there has been talk of increasing road capacity over the Menai Strait, either by extending the road deck of the existing bridge or via the 774: 641:, and used as a basis for the final design. Stephenson, who had not previously attended any of Fairbairn's experiments, was present at one involving this 'model tube', and consequently was persuaded that auxiliary chains were unnecessary. No chains were fitted. As the only purpose of the piers (above the level of the present road deck) was to support the chains, these piers have never had any practical use. Although Stephenson had pressed for the tubes to be 591:). Up until then, the longest wrought iron span had been 31 feet 6 inches (9.60 m), barely one fifteenth of the bridge's spans of 460 ft (140 m). As originally envisaged by Stephenson, the tubular construction would give a structure sufficiently stiff to support the heavy loading associated with trains, but the tubes would not be fully self-supporting, some of their weight having to be taken by suspension chains. 95: 906:
The programme included a detailed inspection of the internal chambers of the three towers and the construction of a special walkway to enable easier and safer access to the structure for future inspections of the masonry piers; special protective efforts adopted for the work included the use of special pollution-minimising paint and the decontamination of all equipment before being brought onsite.
673:, who had previously aided Stephenson in performing the complex structural stress calculations involved in its design process. The first major elements of the structure to be built were the side tubes, this work was performed in situ, using wooden platforms to support it. The construction method used for the iron tubes was derived from contemporary shipbuilding practices, being composed of 623:
fact, it should be a huge sheet-iron hollow girder, of sufficient strength and stiffness to sustain those weights; and, provided that the parts are well-proportioned and the plates properly riveted, you may strip off the chains and have it as a useful monument of the enterprise and energy of the age in which it was constructed.
865:
Further analysis showed that the wrought iron tubes had been too badly damaged to be retained. In light of this discovery, it was decided to dismantle the tubes in favour of replacing them with a new deck at the same level as the original tracks. With the exception of the original stone substructure,
563:
was invited to comment on this proposal but stated his concern about re-using a single carriageway of the suspension bridge, as bridges of this type were unsuited to locomotive use. By 1840, a Treasury committee decided broadly in favour of Stephenson's proposals, however, final consent to the route,
492:
A fire in May 1970 caused extensive damage to the Britannia Bridge. Subsequent investigation determined that the damage to the tubes was so extensive that they were not realistically repairable. The bridge was rebuilt in a quite different configuration, reusing the piers while employing new arches to
905:
undertook a £4 million joint programme to strengthen the 160-year-old structure and improve its reliability. The work involved the replacement of eroded steelwork, repairs to the drainage system, restoration of the parapets and stonework, and the painting of the steel approach portals of the bridge.
877:
was restored to the railway on 30 January 1972 by reusing one of the tubes. The next stage was to dismantle and remove the other tube and replace it with a concrete deck for the other rail track. Then the single-line working was transferred to the new track (on the west side); this allowed the other
845:
During the evening of 23 May 1970, the bridge was heavily damaged when boys playing inside the structure dropped a burning torch, setting alight the tar-coated wooden roof of the tubes. Despite the best efforts of the Caernarfonshire and Anglesey fire brigades, the bridge's height, construction, and
705:
Once in place, the separate lengths of tube were joined to form parallel prestressed continuous structures, each one possessing a length of 1,511 feet (460.6 m) and weighing 5,270 long tons (5,350 tonnes). The pre-stressing process had increased the structure's loadbearing capacity and reduced
716:
On 5 March 1850, Stephenson himself fitted the last rivet of the structure, marking the bridge's official completion. Altogether, the bridge had taken over three years to complete. On 18 March 1850, a single tube was opened to rail traffic. By 21 October of that year, both tubes had been opened to
622:
Under every circumstance, I am of opinion that the tubes should be made sufficiently strong to sustain not only their own weight, but in addition to that load 2000 tons equally distributed over the surface of the platform, a load ten times greater than they will ever be called upon to support. In
697:
Working in parallel to the onsite construction process, the two central tube sections, which weighed 1,800 long tons (1,830 tonnes) apiece, were separately built on the nearby Caernarfon shoreline. Once they had been fully assembled, each of the central tubes was floated, one at a time, into the
543:
in 1826, one mile (1.6 km) to the east of where Britannia Bridge was later built, provided the first fixed road link between Anglesey and the mainland. The increasing popularity of rail travel shortly necessitated a second bridge to provide a direct rail link between London and the port of
617:
However, Fairbairn's experiments had moved on from those covered by Hodgkinson's theory to include designs in which the top plate was stiffened by 'corrugation' (the incorporation of cylindrical tubes). The results of these later experiments he found very encouraging; whilst it was still to be
636:
Stephenson's report drew attention to the difference of opinion between his experts, but reassured the directors that the design of the masonry piers allowed for the tubes to be given suspension support, and no view need yet be taken as to the need for it, which would be resolved by further
724:, a professional rival and personal friend of Stephenson's, was claimed to have remarked to him: "If your bridge succeeds, then mine have all been magnificent failures". On 20 June 1849, Brunel and Stephenson had both looked on as the first of the bridge's tubes was floated out on its 467:. In order to meet the diverse requirements, Stephenson, the project's chief engineer, performed in-depth studies on the concept of tubular bridges. For the detailed design of the structure's girders, Stephenson gained the assistance of distinguished engineer 853:. Following an in-depth investigation of the site performed by the company, it was determined that the cast iron beams inside the towers had suffered substantial cracking and tilting, meaning that the tubes required immediate support at all three towers. The 878:
tube to be removed and replaced with a concrete deck (which is used only for service access) by 1974. Finally the upper road deck was installed and by July 1980, over 10 years after the fire, the new road crossing was completed, and formally opened by the
968:
alongside. Building a separate bridge would allow the existing bridge to be used as normal during construction. The bridge would require support pillar(s) in the Menai Strait, which is an environmental issue as the strait is a
598:, an old friend of his father and described by Stephenson as "well known for his thorough practical knowledge in such matters". Fairbairn began a series of practical experiments on various tube shapes and enlisted the help of 861:
units to fill the original jacking slots in the masonry towers. By the end of July 1970, a total of eight Bailey bridge steel towers had been erected, each being capable of bearing a vertical load of around 200 tonnes.
649:
section was adopted. Fairbairn was responsible both for the cellular construction of the top part of the tubes, and for developing the stiffening of the side panels. Each main span weighed roughly 1,830 tonnes.
1481: 450:
had been completed, but this structure carried a road rather than track; there was no rail connection to Anglesey before its construction. After many years of deliberation and proposals, on 30 June 1845, a
1229: 631:
A view of the entrance to the Britannia Bridge from the Bangor side, showing a steam train entering the bridge, people watching, two large stone lions and an inscription relating to the engineer, Robert
980:. This would eliminate the need for pillars in the Strait, but the bridge would have a large impact on the landscape due to the height of the cable support pillars. This is also the most costly option. 666:
On 10 April 1846, the foundation stone for the Britannia Bridge was laid, marking the official commencement of construction work at the site. The resident engineer for the structure's construction was
493:
support not one but two decks, as the new Britannia Bridge was to function as a combined road-and-rail bridge. The bridge was rebuilt in phases, initially reopening in 1972 as a single-tier steel
728:. The construction techniques employed on the Britannia Bridge had obviously influenced Brunel as he later made use of the same method of floating bridge sections during the construction of the 1035:
The Conwy railway bridge remains in use, and is the only remaining tubular bridge; however, intermediate piers have been added to strengthen it. The bridge can be seen at close quarters from
720:
For its time, the Britannia Bridge was a structure of "magnitude and singular novelty", far surpassing in length both contemporary cast beam or plate girder iron bridges. The noted engineer
1046:
The Victoria Bridge was the first bridge to cross the St. Lawrence River, and was the longest bridge in the world when it was completed in 1859. It was rebuilt as a truss bridge in 1898.
761:
years in operation owing to low passenger volumes. In the present day, little remains of this station, other than the remnants of the lower-level station building. A new station named
996:
Very few other tubular iron bridges were ever built since more economical bridge designs were soon developed. The most notable of the other tubular bridges were Stephenson's
914: 1485: 690:
inch (16 mm) thick, complete with sheeted sides and cellular roofs and bases. The same technique as used for the Britannia Bridge was also used on the smaller
849:
In light of events, the chief civil engineer of British Railways' London Midland region, W.F. Beatty, sought structural advice from consulting engineering company
1226: 793:, two at either end. Each was constructed from 11 pieces of limestone. They are 25 ft (7.6 m) long, 12 ft (3.7 m) tall, and weigh 30 tons. 873:
The bridge was rebuilt in stages. The first stage was to erect the new steel arches under the two original wrought-iron tubes. The arches were completed, and
953:
Widen existing bridge. To do this, the towers would have to be removed to make room for the extra lanes. This is an issue as the bridge is a Grade 2
1778: 1838: 926:
In November 2007, a public consultation exercise into the ‘A55 Britannia Bridge Improvement’ commenced. The perceived problems stated include:
54: 1843: 1788: 478:
tubes was derived from contemporary shipbuilding practices; the same technique as used for the Britannia Bridge was also used on the smaller
1346: 1798: 1098:
The Britannia and Conway tubular bridges With general inquires on beams and on the properties of materials used in construction, Vol. 2
1833: 867: 1366: 961:. The extra lanes would have to be of reduced width as the existing structure is not capable of supporting four full-width lanes. 1783: 1215: 1858: 1508: 984:
Respondents were overwhelmingly in favour of seeing some improvements, with 70 per cent favouring the solution of building
713:. A 12 foot (3.7 m) wide central walkway was present above the roof for the purpose of producing maintenance access. 743:
There was originally a railway station located on the east side of the bridge at the entrance to the tunnel, run by the
482:. On 5 March 1850, Stephenson himself fitted the last rivet of the structure, marking the bridge's official completion. 463:'s insistence, the bridge elements were required to be relatively high in order to permit the passage of a fully rigged 1763: 1464: 1808: 1654: 1612: 1579: 1540: 1060: 471:. On 10 April 1846, the foundation stone for the Britannia Bridge was laid. The construction method used for the 698:
causeway and directly below the structure. The in-place sections were gradually raised into place using powerful
796:
These were immortalised in the following Welsh rhyme by the bard John Evans (1826–1888), who was born in nearby
627: 1848: 1813: 1627: 1594: 1823: 1745:
A community project and museum celebrating the two bridges over the Menai Strait and the town of Menai Bridge
1758: 1724:
In 1969 the BBC show Bird's Eye View captured an aerial view of a train crossing the bridge in the episode
1440: 970: 762: 744: 670: 549: 428: 427:
rectangular box-section spans for carrying rail traffic. Its importance was to form a critical link of the
47: 1853: 1768: 1698: 1689: 1190: 837:
below. The idea of raising them to road level has been suggested by local campaigners from time to time.
747:
company, which served local rail traffic in both directions. However, this station was closed after only
564:
including Britannia Bridge, would not be granted until 30 June 1845, the date on which the corresponding
594:
For the detailed design of the girders, Stephenson secured the assistance of the distinguished engineer
1021: 973:. Visual impact would be low as the pillars and road surface would be aligned with the current bridge. 1803: 898: 1313: 1112:
Dreicer, Gregory K. (2010). "Building Bridges and Boundaries: The Lattice and the Tube, 1820–1860".
1773: 1719:
General description of the Britannia and Conway tubular bridges on the Chester and Holyhead Railway
1055: 879: 98: 1622:. Monograph series / Society for the History of Technology, no. 10. Cambridge, Mass.: MIT Press. 1040: 1009: 883: 833:, which crosses the modern bridge on the same site, although they can be seen from trains on the 721: 540: 447: 1343: 1328: 1728:. Available in the online BBC Archives, the Britannia Bridge segment appears at the 25:47 mark. 1707: 1678: 1114: 834: 790: 89: 1818: 603: 344: 1216:
https://cadwpublic-api.azurewebsites.net/reports/listedbuilding/FullReport?lang=&id=3674
1299:
Baughan, P.E., 'Chester and Holyhead Railway: vol. 1' (1972), pub. David & Charles plc.
1025: 997: 985: 691: 565: 498: 479: 452: 1725: 1482:"A55 Britannia Bridge – Release of the Results of the recent Public Consultation Exercise" 1382: 662:
A section of the original wrought-iron tubular bridge standing beside the modern crossing.
8: 1793: 1533:
Crossing the Menai: an illustrated history of the ferries and bridges of the Menai Strait
1017: 977: 874: 729: 1718: 1284: 658: 637:
experiments. A 75-foot (23 m) span model was constructed and tested at Fairbairn's
1139: 1131: 699: 694:, which was built around the same time. On 10 August 1847, the first rivet was driven. 638: 583:'s insistence, any bridge would have to permit passage of the strait by a fully rigged 509: 1660: 1650: 1623: 1608: 1590: 1575: 1550: 1536: 1143: 965: 919: 902: 595: 580: 573: 560: 494: 468: 460: 416: 236: 143: 1250: 36: 1123: 725: 599: 408: 1732: 1554: 1096: 1828: 1350: 1233: 954: 854: 486: 412: 218: 1367:"Petition calls for Britannia Bridge lions to be raised so people can see them." 946:
In the document, four options are presented, each with their own pros and cons:
517: 1036: 922:(seated centre) with the engineers who designed and built the Britannia Bridge. 850: 710: 667: 556: 420: 392: 158: 137: 1752: 1664: 858: 531: 69: 56: 1403: 523: 958: 942:
Traffic is expected to significantly increase over the next ten years or so
894: 797: 777:
One of four Monumental lions that stand at each corner of Britannia Bridge.
677: 569: 475: 456: 424: 404: 154: 108: 1556:
An Account of the Construction of the Britannia and Conway Tubular Bridges
1286:
An account of the construction of the Britannia and Conway tubular bridges
610:
enough to support their own weight, and advised auxiliary suspension from
1620:
The Britannia Bridge: the generation and diffusion of technical knowledge
733: 122: 1135: 1127: 773: 1712: 1683: 857:
were quickly brought in to save the bridge, rapidly deploying vertical
611: 588: 584: 464: 1001: 786: 646: 607: 415:. It was originally designed and built by the noted railway engineer 1013: 555:
Other railway schemes were proposed, including one in 1838 to cross
1029: 887: 830: 545: 436: 167: 118: 1742: 1565:
Bridging the Years – a short history of British Civil Engineering
737: 642: 950:
Do nothing. Congestion will increase as traffic levels increase.
440: 432: 1005: 674: 472: 400: 163: 1314:
Details of Britannia Bridge railway station (with pictures)
782: 455:
covering the construction of the Britannia Bridge received
1736: 1479: 930:
It is the only non-dual-carriageway section along the A55
707: 446:
Decades before the building of the Britannia Bridge, the
1702: 1693: 1329:"Britannia Bridge campaign to raise the "hidden" lions." 936:
Congestion from seasonal and ferry traffic from Holyhead
602:"distinguished as the first scientific authority on the 485:
On 3 March 1966, the Britannia Bridge received Grade II
1589:(new revised ed.). Llanrwst: Gwasg Carreg Gwalch. 1509:"70% public backing for third bridge over Menai Strait" 1699:
Britannia Bridge, Bangor entrance showing lion (1905)
431:'s route, enabling trains to directly travel between 1605:
George and Robert Stephenson: The Railway Revolution
933:
Congestion during morning and afternoon peak periods
186:
221.25 ft (67.44 m) to top of centre tower
893:During 2011, national railway infrastructure owner 576:, was appointed as chief engineer for the project. 1617: 1750: 1618:Rosenberg, Nathan; Vincenti, Walter G. (1978). 1278: 1276: 1274: 1272: 1270: 1268: 882:, carrying a single-carriageway section of the 1214:CADW Summary Description of a Listed Building 1063:, museum about the Menai and Britannia bridges 909: 535:Postcard picture of the bridge from circa 1902 223:103 ft (31 m) to bottom of rail deck 1649:. West Sussex: Middleton Press. figs. 18–25. 1644: 1101:. Day & Son. pp. 540, 545, 585, 587. 1480:Welsh Assembly Government (12 August 2008). 1265: 1245: 1243: 1241: 1185: 1183: 1181: 1179: 1177: 1175: 1173: 521:The original box section Britannia Bridge, 1460: 1458: 1171: 1169: 1167: 1165: 1163: 1161: 1159: 1157: 1155: 1153: 1105: 868:Cleveland Bridge & Engineering Company 840: 572:. Around the same time, Stephenson's son, 559:'s existing Menai Bridge. Railway pioneer 1549: 1282: 1238: 1090: 1088: 1086: 1084: 1082: 1584: 1465:"Rail Improvement for Britannia Bridge." 913: 866:the structure was completely rebuilt by 772: 657: 626: 530: 516: 508: 1779:Road-rail bridges in the United Kingdom 1572:The Britannia and other Tubular Bridges 1455: 1383:"Britannia Bridge Official Fire Report" 1150: 1111: 1020:bridge, which was the prototype of the 781:The bridge was decorated by four large 653: 1751: 1435: 1079: 939:Queuing at the junctions at either end 16:Road-rail bridge over the Menai Strait 1839:Grade II listed buildings in Anglesey 1530: 1433: 1431: 1429: 1427: 1425: 1423: 1421: 1419: 1417: 1415: 1094: 1844:Grade II listed buildings in Gwynedd 1789:1970 disasters in the United Kingdom 1645:Mitchell, Vic; Smith, Keith (2011). 1507:Live, North Wales (13 August 2008). 1506: 1404:"The Night the Bridge Caught Fire." 13: 1638: 1412: 991: 829:The lions cannot be seen from the 645:in section, Fairbairn's preferred 439:, thus facilitating a sea link to 14: 1870: 1799:1970s fires in the United Kingdom 1672: 1061:Menai Heritage Bridges Exhibition 1834:Grade II listed bridges in Wales 1733:The Night the Bridge Caught Fire 1567:, Edward Arnold (Publishers) Ltd 178:1,510.25 ft (460.32 m) 93: 35: 1721:, 1849, from Google Book Search 1563:Norrie, Charles Matthew (1956) 1523: 1500: 1473: 1397: 1375: 1359: 1337: 1322: 802: 765:was opened shortly afterwards. 1302: 1293: 1220: 1208: 499:construction of a third bridge 199: 1: 1784:Train and rapid transit fires 1344:"The Britannia Bridge Lions." 1067: 1531:Jones, Reg Chambers (2011). 971:Special Area of Conservation 745:Chester and Holyhead Railway 550:Chester and Holyhead Railway 429:Chester and Holyhead Railway 312:; 174 years ago 280:; 174 years ago 248:; 178 years ago 41:The modern Britannia Bridge. 7: 1859:Cross-sea bridges in Europe 1443:. engineering-timelines.com 1283:Fairbairn, William (1849). 1049: 910:Proposed bridge improvement 364:; 50 years ago 325:; 50 years ago 293:; 44 years ago 261:; 52 years ago 10: 1875: 1703:Grandad's Photograph Album 1694:Grandad's Photograph Album 918:An 1868 engraving showing 336:1980 (road, second bridge) 1764:Bridges completed in 1850 1535:. Wrexham: Bridge Books. 1441:"Britannia Bridge (1974)" 1356:, Retrieved: 24 May 2018. 1318:Disused Stations' website 1232:27 September 2007 at the 1191:"Britannia Bridge (1850)" 899:Welsh Assembly Government 513:Britannia Bridge entrance 504: 382: 377: 358: 340: 306: 274: 242: 232: 227: 217: 209: 198: 190: 182: 174: 150: 133: 128: 114: 104: 85: 46: 34: 23: 1809:Railway bridges in Wales 1585:Richards, Robin (2004). 1227:Special.st-andrews.ac.uk 1072: 1056:List of bridges in Wales 768: 194:460 ft (140 m) 1708:Britannia Bridge (1971) 1690:Britannia Bridge (1905) 1679:Britannia Bridge (1850) 1603:Rolt, L. T. C. (1960). 1041:Conwy Suspension Bridge 1010:Sainte-Anne-de-Bellevue 903:English Highways Agency 841:Fire and reconstruction 722:Isambard Kingdom Brunel 448:Menai Suspension Bridge 1587:Two Bridges over Menai 1251:"Menai Strait Bridges" 1115:Technology and Culture 923: 835:North Wales Coast Line 827: 814: 778: 663: 633: 625: 604:strength of iron beams 536: 528: 514: 396: 345:May 23, 1970 90:North Wales Coast Line 1849:Double-decker bridges 1814:Road bridges in Wales 1570:Rapley, John (2003). 1559:. London: John Weale. 1289:. London: John Weale. 1195:Engineering Timelines 1095:Clark, Edwin (1850). 917: 815: 776: 661: 630: 620: 534: 520: 512: 334:(rail, second bridge) 1824:Llanfairpwllgwyngyll 1026:Saint Lawrence River 998:Conwy railway bridge 692:Conwy Railway Bridge 654:Construction and use 480:Conwy Railway Bridge 321:(rail, first bridge) 70:53.21639°N 4.18583°W 1759:Bridges in Anglesey 1607:, Penguin, Ch. 15, 1372:, 26 November 2016. 1354:raisethelions.co.uk 1349:24 May 2018 at the 1334:, 25 November 2016. 1128:10.1353/tech.0.0406 1018:Grand Trunk Railway 978:cable-stayed bridge 966:concrete box bridge 875:single-line working 824:And two over there 730:Royal Albert Bridge 700:hydraulic cylinders 539:The opening of the 66: /  1854:Bridges in Gwynedd 1769:Truss arch bridges 1647:Bangor to Holyhead 1551:Fairbairn, William 1470:, 10 January 2011. 1409:, 25 August 2011 . 1253:. Anglesey History 1002:Llandudno Junction 924: 779: 664: 634: 566:Parliamentary Bill 537: 529: 515: 453:Parliamentary Bill 243:Construction start 75:53.21639; -4.18583 1039:'s adjacent 1826 920:Robert Stephenson 811:A dau 'ochr drew 639:Millwall shipyard 596:William Fairbairn 574:Robert Stephenson 561:George Stephenson 495:truss arch bridge 469:William Fairbairn 417:Robert Stephenson 403:that crosses the 399:) is a bridge in 386: 385: 237:Robert Stephenson 144:truss arch bridge 1866: 1804:Fires in England 1668: 1633: 1600: 1560: 1546: 1517: 1516: 1513:North Wales Live 1504: 1498: 1497: 1495: 1493: 1484:. Archived from 1477: 1471: 1462: 1453: 1452: 1450: 1448: 1437: 1410: 1401: 1395: 1394: 1392: 1390: 1379: 1373: 1363: 1357: 1341: 1335: 1326: 1316: 1309: 1300: 1297: 1291: 1290: 1280: 1263: 1262: 1260: 1258: 1247: 1236: 1224: 1218: 1212: 1206: 1205: 1203: 1201: 1187: 1148: 1147: 1109: 1103: 1102: 1092: 976:New single span 957:and is owned by 955:listed structure 851:Husband & Co 822:Two on this side 820:Without any hair 760: 759: 755: 752: 689: 688: 684: 600:Eaton Hodgkinson 435:and the port of 409:Isle of Anglesey 389:Britannia Bridge 372: 370: 365: 352: 350: 333: 331: 326: 320: 318: 313: 301: 299: 294: 288: 286: 281: 275:Construction end 269: 267: 262: 256: 254: 249: 201: 97: 96: 81: 80: 78: 77: 76: 71: 67: 64: 63: 62: 59: 39: 25:Britannia Bridge 21: 20: 1874: 1873: 1869: 1868: 1867: 1865: 1864: 1863: 1774:Tubular bridges 1749: 1748: 1726:Man on the Move 1675: 1657: 1641: 1639:Further reading 1636: 1630: 1597: 1543: 1526: 1521: 1520: 1505: 1501: 1491: 1489: 1478: 1474: 1463: 1456: 1446: 1444: 1439: 1438: 1413: 1402: 1398: 1388: 1386: 1381: 1380: 1376: 1364: 1360: 1351:Wayback Machine 1342: 1338: 1327: 1323: 1312: 1303: 1298: 1294: 1281: 1266: 1256: 1254: 1249: 1248: 1239: 1234:Wayback Machine 1225: 1221: 1213: 1209: 1199: 1197: 1189: 1188: 1151: 1110: 1106: 1093: 1080: 1075: 1070: 1052: 1022:Victoria Bridge 994: 992:Similar bridges 964:New multi-span 912: 880:Prince of Wales 855:Royal Engineers 843: 826: 823: 821: 819: 813: 810: 808: 806: 805:Pedwar llew tew 771: 757: 753: 750: 748: 686: 682: 681: 656: 507: 368: 366: 363: 348: 346: 335: 329: 327: 324: 322: 316: 314: 311: 302:(second bridge) 297: 295: 292: 290: 284: 282: 279: 270:(second bridge) 265: 263: 260: 258: 252: 250: 247: 219:Clearance above 170:(second bridge) 162: 146:(second bridge) 141: 129:Characteristics 94: 92: 74: 72: 68: 65: 60: 57: 55: 53: 52: 42: 30: 27: 26: 17: 12: 11: 5: 1872: 1862: 1861: 1856: 1851: 1846: 1841: 1836: 1831: 1826: 1821: 1816: 1811: 1806: 1801: 1796: 1791: 1786: 1781: 1776: 1771: 1766: 1761: 1747: 1746: 1743:Menai Heritage 1740: 1739:programme page 1729: 1722: 1716: 1705: 1696: 1687: 1674: 1673:External links 1671: 1670: 1669: 1655: 1640: 1637: 1635: 1634: 1628: 1615: 1601: 1595: 1582: 1568: 1561: 1547: 1541: 1527: 1525: 1522: 1519: 1518: 1499: 1488:on 24 May 2011 1472: 1454: 1411: 1396: 1374: 1358: 1336: 1321: 1301: 1292: 1264: 1237: 1219: 1207: 1149: 1122:(1): 126–163. 1104: 1077: 1076: 1074: 1071: 1069: 1066: 1065: 1064: 1058: 1051: 1048: 1037:Thomas Telford 993: 990: 986:another bridge 982: 981: 974: 962: 951: 944: 943: 940: 937: 934: 931: 911: 908: 842: 839: 818:Four fat lions 816: 803: 770: 767: 668:civil engineer 655: 652: 557:Thomas Telford 506: 503: 421:tubular bridge 397:Pont Britannia 384: 383: 380: 379: 375: 374: 373:(first bridge) 360: 356: 355: 354:(first bridge) 342: 338: 337: 308: 304: 303: 289:(first bridge) 276: 272: 271: 257:(first bridge) 244: 240: 239: 234: 230: 229: 225: 224: 221: 215: 214: 211: 210:Piers in water 207: 206: 203: 196: 195: 192: 188: 187: 184: 180: 179: 176: 172: 171: 161:(first bridge) 152: 148: 147: 140:(first bridge) 138:Tubular bridge 135: 131: 130: 126: 125: 116: 112: 111: 106: 102: 101: 87: 83: 82: 50: 44: 43: 40: 32: 31: 29:Pont Britannia 28: 24: 15: 9: 6: 4: 3: 2: 1871: 1860: 1857: 1855: 1852: 1850: 1847: 1845: 1842: 1840: 1837: 1835: 1832: 1830: 1827: 1825: 1822: 1820: 1817: 1815: 1812: 1810: 1807: 1805: 1802: 1800: 1797: 1795: 1792: 1790: 1787: 1785: 1782: 1780: 1777: 1775: 1772: 1770: 1767: 1765: 1762: 1760: 1757: 1756: 1754: 1744: 1741: 1738: 1735: 1734: 1730: 1727: 1723: 1720: 1717: 1715: 1714: 1709: 1706: 1704: 1700: 1697: 1695: 1691: 1688: 1686: 1685: 1680: 1677: 1676: 1666: 1662: 1658: 1656:9781908174017 1652: 1648: 1643: 1642: 1631: 1625: 1621: 1616: 1614: 1613:0-14-007646-8 1610: 1606: 1602: 1598: 1592: 1588: 1583: 1581: 1580:0-7524-2753-9 1577: 1573: 1569: 1566: 1562: 1558: 1557: 1552: 1548: 1544: 1542:9781844940745 1538: 1534: 1529: 1528: 1514: 1510: 1503: 1487: 1483: 1476: 1469: 1466: 1461: 1459: 1442: 1436: 1434: 1432: 1430: 1428: 1426: 1424: 1422: 1420: 1418: 1416: 1408: 1405: 1400: 1384: 1378: 1371: 1368: 1365:Crump, Eryl. 1362: 1355: 1352: 1348: 1345: 1340: 1333: 1330: 1325: 1319: 1317: 1315: 1308: 1307: 1296: 1288: 1287: 1279: 1277: 1275: 1273: 1271: 1269: 1252: 1246: 1244: 1242: 1235: 1231: 1228: 1223: 1217: 1211: 1196: 1192: 1186: 1184: 1182: 1180: 1178: 1176: 1174: 1172: 1170: 1168: 1166: 1164: 1162: 1160: 1158: 1156: 1154: 1145: 1141: 1137: 1133: 1129: 1125: 1121: 1117: 1116: 1108: 1100: 1099: 1091: 1089: 1087: 1085: 1083: 1078: 1062: 1059: 1057: 1054: 1053: 1047: 1044: 1042: 1038: 1033: 1031: 1027: 1023: 1019: 1015: 1011: 1007: 1003: 999: 989: 987: 979: 975: 972: 967: 963: 960: 956: 952: 949: 948: 947: 941: 938: 935: 932: 929: 928: 927: 921: 916: 907: 904: 900: 896: 891: 889: 885: 881: 876: 871: 869: 863: 860: 859:Bailey bridge 856: 852: 847: 838: 836: 832: 825: 812: 809:Dau 'ochr yma 807:Heb ddim blew 801: 799: 794: 792: 788: 784: 775: 766: 764: 746: 741: 739: 735: 731: 727: 723: 718: 714: 712: 709: 703: 701: 695: 693: 679: 676: 672: 669: 660: 651: 648: 644: 640: 629: 624: 619: 615: 613: 609: 605: 601: 597: 592: 590: 586: 582: 577: 575: 571: 567: 562: 558: 553: 551: 547: 542: 533: 526: 525: 519: 511: 502: 500: 496: 490: 488: 487:listed status 483: 481: 477: 474: 470: 466: 462: 458: 454: 449: 444: 442: 438: 434: 430: 426: 422: 418: 414: 410: 406: 402: 398: 394: 390: 381: 376: 361: 357: 353: 343: 339: 309: 305: 277: 273: 245: 241: 238: 235: 231: 226: 222: 220: 216: 212: 208: 204: 197: 193: 189: 185: 181: 177: 173: 169: 165: 160: 156: 153: 149: 145: 139: 136: 132: 127: 124: 120: 117: 113: 110: 107: 103: 100: 91: 88: 84: 79: 51: 49: 45: 38: 33: 22: 19: 1819:Menai Strait 1731: 1711: 1682: 1646: 1619: 1604: 1586: 1571: 1564: 1555: 1532: 1524:Bibliography 1512: 1502: 1490:. Retrieved 1486:the original 1475: 1468:Network Rail 1467: 1445:. Retrieved 1406: 1399: 1387:. Retrieved 1385:. 2d53.co.uk 1377: 1369: 1361: 1353: 1339: 1331: 1324: 1311: 1310: 1306: 1305: 1295: 1285: 1255:. Retrieved 1222: 1210: 1198:. Retrieved 1194: 1119: 1113: 1107: 1097: 1045: 1034: 1008:, the first 995: 983: 959:Network Rail 945: 925: 895:Network Rail 892: 872: 864: 848: 844: 828: 817: 804: 798:Menai Bridge 795: 785:sculpted in 780: 763:Menai Bridge 742: 719: 715: 704: 696: 678:wrought iron 665: 635: 621: 616: 593: 578: 570:royal assent 554: 541:Menai Bridge 538: 522: 491: 484: 476:wrought iron 457:royal assent 445: 425:wrought iron 411:and city of 407:between the 405:Menai Strait 388: 387: 191:Longest span 175:Total length 155:Wrought iron 109:Menai Strait 18: 1447:18 November 1024:across the 791:John Thomas 734:River Tamar 732:across the 671:Edwin Clark 647:rectangular 612:link chains 589:box girders 443:, Ireland. 123:North Wales 73: / 48:Coordinates 1794:1970 fires 1753:Categories 1713:Structurae 1684:Structurae 1629:0262180871 1596:1845241304 1574:, Tempus, 1389:24 January 1370:Daily Post 1257:24 January 1200:28 October 1068:References 643:elliptical 632:Stephenson 585:man-of-war 465:man-of-war 349:1970-05-23 58:53°12′59″N 1665:795179106 1492:13 August 1144:110334486 886:(now the 787:limestone 717:traffic. 581:Admiralty 568:received 461:Admiralty 459:. At the 341:Destroyed 142:Two-tier 1553:(1849). 1347:Archived 1332:BBC News 1230:Archived 1136:40646995 1050:See also 1030:Montreal 1000:between 901:and the 726:pontoons 546:Holyhead 437:Holyhead 378:Location 233:Designer 202:of spans 168:concrete 151:Material 119:Anglesey 61:4°11′9″W 884:A5 road 756:⁄ 738:Saltash 711:hessian 685:⁄ 680:plates 675:riveted 579:At the 473:riveted 367: ( 347: ( 328: ( 315: ( 296: ( 283: ( 264: ( 251: ( 228:History 105:Crossed 86:Carried 1829:Pentir 1663:  1653:  1626:  1611:  1593:  1578:  1539:  1142:  1134:  1014:Québec 897:, the 708:tarred 548:, the 505:Design 441:Dublin 433:London 413:Bangor 359:Closed 307:Opened 183:Height 134:Design 115:Locale 1140:S2CID 1132:JSTOR 1073:Notes 1006:Conwy 783:lions 769:Lions 608:stiff 527:1852. 524:circa 419:as a 401:Wales 393:Welsh 164:Steel 159:stone 1661:OCLC 1651:ISBN 1624:ISBN 1609:ISBN 1591:ISBN 1576:ISBN 1537:ISBN 1494:2008 1449:2016 1391:2013 1259:2013 1202:2017 1004:and 369:1974 362:1974 330:1974 323:1974 317:1850 310:1850 298:1980 291:1980 285:1850 278:1850 266:1972 259:1972 253:1846 246:1846 205:Four 166:and 157:and 1737:BBC 1710:at 1701:at 1692:at 1681:at 1407:BBC 1124:doi 1028:at 890:). 888:A55 831:A55 789:by 736:at 423:of 213:One 200:No. 99:A55 1755:: 1659:. 1511:. 1457:^ 1414:^ 1320:. 1267:^ 1240:^ 1193:. 1152:^ 1138:. 1130:. 1120:51 1118:. 1081:^ 1043:. 1032:. 1016:) 988:. 800:: 740:. 614:. 552:. 501:. 489:. 395:: 121:, 1667:. 1632:. 1599:. 1545:. 1515:. 1496:. 1451:. 1393:. 1304:' 1261:. 1204:. 1146:. 1126:: 1012:( 758:2 754:1 751:+ 749:8 687:8 683:5 391:( 371:) 351:) 332:) 319:) 300:) 287:) 268:) 255:)

Index


Coordinates
53°12′59″N 4°11′9″W / 53.21639°N 4.18583°W / 53.21639; -4.18583
North Wales Coast Line
A55
Menai Strait
Anglesey
North Wales
Tubular bridge
truss arch bridge
Wrought iron
stone
Steel
concrete
Clearance above
Robert Stephenson
May 23, 1970 (1970-05-23)
Welsh
Wales
Menai Strait
Isle of Anglesey
Bangor
Robert Stephenson
tubular bridge
wrought iron
Chester and Holyhead Railway
London
Holyhead
Dublin
Menai Suspension Bridge

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.