Knowledge

Saint-Just-Saint-Rambert Bridge

Source 📝

654: 296: 487: 1137: 585: 645:
30 and then 36 wires. The anticorrosion protection of the TMC was done differently on the main cables and on the hangers. For the main cables, in addition to galvanizing the wires, a bitumen-based paint protection was applied to the assembled cable. For the hangers, the galvanized wires were coated with petroleum wax during cable manufacture to fill the voids, and then the cable was sheathed with extruded HDPE under vacuum.
593:
plate connected to its neighbor by a reinforced concrete anchor. Due to the asymmetry of the site, the pylon on the left bank measures 38 m, while that on the right bank measures 41 m. Similarly, the left bank bases each rest on eight Ø 1,500 piles, while those on the right bank are flat and constructed inside a cofferdam.
644:
In the first pass, the first four layers of wires can be wrapped around the cable core, namely 6, 12, 18, and then 24 wires, for a total of 61 wires with the core. To achieve the desired diameter, the cable passes back through the coiling machine where additional reels are coupled to create layers of
592:
The inverted V-shaped pylons are made of B60 concrete. The legs have a rectangular section inclined at 20.5°. This section varies from 2.20 x 1.80 at the top to 2.20 x 3.00 at the deck level. The lower part has an additional wall on the inside, on which the deck rests. Each leg is embedded in a base
353:
Assembly and tensioning took place during the summer of 2007. Waterproofing and the first layer of asphalt were completed in September - October 2007. Approximately 100 to 150 meters of embankments and roadways on each side of the bridge and the installation of equipment were completed by the end of
234:
cables thus form inclined planes instead of being parallel. Moreover, it has the particularity of being self-anchored. The anchoring structures are indeed connected to the deck, which results in a portion of the traction forces being transformed into compression in the deck. As a result, the size of
668:
The hangers were positioned by crane from the deck. Each hanger foot was equipped with a basket for access and a jacking equipment for tensioning and load transfer. During this operation, the suspension cables were lengthened and the deck was shortened. This caused a movement of the saddles towards
333:
After preliminary studies, the departmental assembly opted for a participatory approach for the final choice of the structure's architecture. Two proposals were put to the Internet users: a classic bridge with parallel cables supported by two trapezoidal-shaped frames, and an innovative bridge with
661:
The installation of the main cables and deviation saddles required the installation of working platforms at the head of the pylon and a cable walkway. The strands were installed using winches and carts supporting the anchoring sockets. The cables slid through a PEHD chute. Installation was mainly
499:
In suspended bridges, all forces are transmitted through the suspension cables, which in turn are anchored to anchor masses on both sides of the structure. These must be absolutely stable in both horizontal sliding and tipping. This leads to the construction of abutments and anchoring masses with
562:
Manufacturing was carried out conventionally using a machine for welded reconstituted profiled sections (PRS). The main difficulty lay in the manufacture of the main brackets, which were all different and had very tight geometric tolerances on the suspension tube. Their manufacture required the
571:
The structure crosses the river at a relatively low level, and the Loire divides at this point into a minor bed and a secondary branch separated by an island. This configuration allowed for the consideration, from the outset, of an original assembly method for this type of structure: the metal
503:
In the Saint-Just-Saint-Rambert bridge, an original solution was chosen: the abutments and the deck are rigidly connected, the whole resting on foundation masses. Each cable thus transfers the horizontal component of the forces to the deck in compression, reducing the volume of the necessary
342:
The first earthworks began in January 2006. The bases of the four legs of the pylons were completed during the summer of 2006. The rest of their construction continued in the second half of 2006, and they were ready to receive the suspension equipment in April 2007.
680:
After the load transfer, the complex sealing/wearing course and superstructures were installed. This additional load required a further displacement of the saddles, which were immobilized after adjustment, and then the suspension was definitively adjusted.
606:
The two suspension cables, approximately 305 m long, consist of 19 strands of 77.8 mm diameter assembled in a hexagonal configuration. They pass over a fixed saddle, inclined at 20.5 degrees, before branching out into a fan shape for anchorage in the ears.
754: 311:
The studies for the structure were conducted from 2003 to 2006 by a project team consisting of a technical engineering firm, QUADRIC; an architectural firm, STRATES; and a team of agents from the Delegation to Infrastructure of the Loire Department.
934: 346:
From mid-August to mid-October 2006, the first 150 meters of the steel deck frame were assembled on site. The second half of the steel structure was then transported and assembled. By mid-December, the entire structure had been assembled.
507:
The suspension cables are anchored in reinforced concrete abutments of 7,000 tons due to a reinforced concrete lattice structure. The embedding of the deck is ensured by a transition zone prestressed transversely by eleven 19T15 cables.
750: 575:
Once the composite slabs were in place, the deck was cast and the suspension was installed from the deck. The suspenders’ tensioning at the end of the assembly straightened the deck and allowed the struts to be removed.
614:. They range in length from 23 m near the pylons to 3 m at mid-span. The upper attachments are made of cast steel. The lower attachment is by means of a bolted base housed in a tube welded to the end of the brackets. 894: 768: 527:
The main bridge sections, numbering 25 and spaced every 7.692 m, have a constant height between the girders, and have brackets of varying heights. The brackets have a metal tube at the end to receive the
888: 911: 824: 637:. Each layer of wires has six more wires than the previous one and is wound in the opposite direction on the cable. Therefore, the coils are placed in multiples of six on coupled 483:
The structure supports a 2x2 lane road. It has a usable width of 20.55 meters and includes a 3.0 meter wide fast lane and a 3.50 wide slow lane on each side of a central median.
861: 829: 350:
On 18 December 2006 the deck was pushed approximately 40 meters to the left bank. The last two pushes, of 50 meters and then 30 meters, took place on 11 and 12 January 2007.
572:
framework of the deck was launched on five temporary struts, three in the Loire bed and two on the pylons. In addition, a 20 m cantilever was used to relieve the overhang.
334:
cables converging at the top of two triangular frames. 84% of Internet users voted for the triangular bridge. This is the architecture chosen by the Departmental Assembly.
724: 1112:
Suchet, J-L; Berlottier, J; Vadon, H; Lawnicki, J; Chenot, J-M; Guillaume, M-L; Dumont, J; Dubois, R (March 2009). "Le nouveau pont suspendu sur la Loire à Andrézieux".
1093:
Suchet, J-L; Berlottier, J; Vadon, H; Lawnicki, J; Chenot, J-M; Guillaume, M-L; Dumont, J; Dubois, R (March 2009). "Le nouveau pont suspendu sur la Loire à Andrézieux".
1074:
Suchet, J-L; Berlottier, J; Vadon, H; Lawnicki, J; Chenot, J-M; Guillaume, M-L; Dumont, J; Dubois, R (March 2009). "Le nouveau pont suspendu sur la Loire à Andrézieux".
1055:
Suchet, J-L; Berlottier, J; Vadon, H; Lawnicki, J; Chenot, J-M; Guillaume, M-L; Dumont, J; Dubois, R (March 2009). "Le nouveau pont suspendu sur la Loire à Andrézieux".
1036:
Suchet, J-L; Berlottier, J; Vadon, H; Lawnicki, J; Chenot, J-M; Guillaume, M-L; Dumont, J; Dubois, R (March 2009). "Le nouveau pont suspendu sur la Loire à Andrézieux".
1014:
Suchet, J-L; Berlottier, J; Vadon, H; Lawnicki, J; Chenot, J-M; Guillaume, M-L; Dumont, J; Dubois, R (March 2009). "Le nouveau pont suspendu sur la Loire à Andrézieux".
992:
Suchet, J-L; Berlottier, J; Vadon, H; Lawnicki, J; Chenot, J-M; Guillaume, M-L; Dumont, J; Dubois, R (March 2009). "Le nouveau pont suspendu sur la Loire à Andrézieux".
798:
Suchet, J-L; Berlottier, J; Vadon, H; Lawnicki, J; Chenot, J-M; Guillaume, M-L; Dumont, J; Dubois, R (March 2009). "Le nouveau pont suspendu sur la Loire à Andrézieux".
278:
The new road has seen a diversion of vehicles ranging from 15,000 to 22,000 per day. This represents a significant portion of the 30,000 that cross the Loire daily at
303:
The western section, 2.6 km long, completes the project between the RD 8 interchange and the end interchange on the RD 498. Construction was completed in early 2011.
1236: 292:
The central section connecting the RD 12 to the RD 8 (Bonson) includes the Loire crossing and is 2.7 km long. It has been open to traffic since 15 December 2008.
623: 529: 424: 698: 957: 524:
The deck is a twin-girder structure of mixed framing consisting of bridge sections and brackets. It has three continuous spans (35 m - 200 m - 35 m).
275:
This new road improves the residents’ living environment and reduces travel times by 20 to 30 minutes on the considered route with 2 x 2 lanes.
532:. The secondary bridge sections, 1 m high at the axis, have variable heights and are placed between the main bridge sections and on the spans. 856: 962: 36: 1172: 1216: 940: 669:
the central span. These were positioned accordingly at the time of cable laying and therefore had to be moved by jacks with a
1246: 1221: 662:
done at night to ensure that various expansions did not interfere with the geometric adjustment of the cable network.
230:
The bridge’s design is notable for its unique triangular portal that supports the carrying cables. The two sets of
511:
The abutments are supported by 4 x 2 supports of 800 x 700 x 8 (16 + 5) on beams supporting 1,500 diameter piles.
1231: 563:
development of a pre-assembly bench to accurately align the tube to the console web and control the geometry.
1241: 784: 379: 249: 224: 699:"Saint-Just-Saint-Rambert . Grand-pont sur la Loire : un chef-d'oeuvre architectural inauguré en 2008" 665:
The two cable networks were installed vertically before being inclined in phases during the load transfer.
29: 1226: 917: 611: 1150: 289:
The Eastern section, connecting the A72 to RD 12 in Saint-Just-sur-Loire, was opened in July 2005.
283: 279: 261: 205: 81: 552: 670: 1201: 219:
As of 26 February 2021 the bridge has been given the name "Pont Pascal Clément," in honor of
773:. Conseil général de la Loire. October 2007. Archived from the original on November 4, 2021. 610:
The hangers, 25 per side, are single-strand cables with a diameter of 88.6 mm sheathed in
8: 96: 1155: 778: 197: 1168: 627: 315:
The founding principles of the project were gradually developed by the project team:
193: 220: 536: 866: 834: 751:"Le grand pont sur la Loire baptisé pont Pascal Clément - Département de la Loire" 223:, who played a key role in its construction during his tenure as president of the 674: 357:
The bridge was inaugurated on 13 December 2008 and put into service on the 15th.
320: 653: 622:
The multilayer cables (TMC) constituting the bundles of the main cables and the
208:. It facilitates the deviation of the departmental road D 498, which links the 329:
Innovate by adopting self-anchoring to save materials and financial resources.
265: 1210: 556: 540: 257: 253: 231: 213: 209: 51: 38: 1163: 1142: 323:
without intermediate support in a single span, thus preserving the biotope;
326:
Dare to create an emblematic structure marking the crossing of the river;
295: 269: 939:(in French). Conseil général de la Loire. December 2007. Archived from 916:(in French). Conseil général de la Loire. February 2007. Archived from 725:"Hommage - Le Grand pont sur la Loire baptisé du nom de Pascal Clément" 486: 584: 633:
Galvanized wires were first wound onto coils, arranged onto cable
559:
to the assembly platform located on the left bank of the Loire.
504:
anchoring mass, which now only supports the vertical component.
1159: 1111: 1092: 1073: 1054: 1035: 1013: 991: 797: 248:
The TD 498 deviation is a development project managed by the
201: 106: 71: 638: 634: 464: 337: 171: 161: 264:. The RD 498 is a relevant route connecting the motorway, 16:
Suspension bridge located in the Loire department, France.
967: 893:(in French). Conseil général de la Loire. February 2008. 551:
The beams were manufactured in nine sections each at the
626:
were manufactured according to the process developed by
319:
Respect the natural river by crossing it along with its
1132: 252:
that aims to connect the airport interchange on the
192:, also known as the "Grand Pont sur la Loire", is a 1187:
Les ponts de la Loire - De sa source à l’Atlantique
1208: 416:Groupement GFC Construction and DV Construction 494: 1237:Buildings and structures in Loire (department) 722: 478: 235:these structures is significantly reduced. 490:Saint-Just-Saint-Rambert bridge elevation. 153:GFC Construction Group and DV Construction 958:"Inauguration du Grand Pont sur la Loire" 906: 904: 1031: 1029: 1009: 1007: 987: 985: 819: 817: 815: 813: 652: 583: 485: 338:2006-2008: Construction of the structure 294: 1184: 1173:List of longest suspension bridge spans 927: 881: 761: 684: 1209: 901: 897:from the original on November 4, 2021. 1105: 1086: 1067: 1048: 1026: 1004: 982: 950: 857:"Le Grand Pont suspendu sur la Loire" 810: 449: 430: 409: 401: 393: 385: 375: 370: 367: 306: 1200:Architectural resource (in French): 641:that rotate in opposite directions. 849: 825:"Déviation de la RD 498 (RD 3 498)" 791: 723:Centre France (February 26, 2021). 539:was cast on 0.12 m thick composite 243: 13: 617: 14: 1258: 1194: 657:Suspension in place - August 2007 648: 1135: 601: 555:plant and then transported by a 546: 519: 389:Infrastructure Delegation CG 42 145:Strates / Berlottier architectes 1178: 566: 360: 256:to the existing RD 498 between 190:Saint-Just-Saint-Rambert bridge 23:Saint-Just-Saint-Rambert Bridge 743: 716: 691: 473: 364: 1: 1217:2008 establishments in France 1185:Vannier, Serge (April 2005). 596: 380:Departmental Council of Loire 250:Departmental Council of Loire 225:Departmental Council of Loire 1247:Suspension bridges in France 495:Abutments and Self-Anchorage 7: 1128: 966:(in French). Archived from 865:(in French). Archived from 833:(in French). Archived from 514: 212:to the west of the town of 10: 1263: 1114:Bulletin Ponts métalliques 1095:Bulletin Ponts métalliques 1076:Bulletin Ponts métalliques 1057:Bulletin Ponts métalliques 1038:Bulletin Ponts métalliques 1016:Bulletin Ponts métalliques 994:Bulletin Ponts métalliques 800:Bulletin Ponts métalliques 479:Functional Characteristics 238: 1222:Bridges completed in 2008 783:: CS1 maint: unfit URL ( 579: 182: 177: 167: 157: 149: 141: 136: 128: 120: 112: 102: 92: 87: 77: 67: 28: 21: 1151:Saint-Just-Saint-Rambert 936:Lettre du grand Pont n°4 913:Lettre du grand Pont n°3 280:Saint-Just-Saint-Rambert 262:Saint-Marcellin-en-Forez 206:Saint-Just-Saint-Rambert 82:Saint-Just-Saint-Rambert 862:Site du Conseil général 830:Site du Conseil général 467:Engineering Department 421:Framing and suspension 1232:Bridges over the Loire 658: 589: 491: 300: 656: 587: 553:Châteauneuf-sur-Loire 489: 453:Construction studies 431:Construction studies 298: 150:Engineering design by 1242:Architectural design 970:on February 24, 2011 946:on November 4, 2021. 923:on November 4, 2021. 869:on February 23, 2011 837:on February 23, 2011 685:Notes and references 588:Bridge cross-section 500:very large volumes. 52:45.51667°N 4.24917°E 461:External framework 445:Baudin-Chateauneuf 284:Andrézieux-Bouthéon 97:Reinforced concrete 93:Trough construction 48: /  1156:Loire (department) 757:on March 25, 2024. 659: 590: 492: 434:Civil engineering 425:Baudin-Chateauneuf 413:Civil engineering 307:2004-2006: Studies 301: 158:Construction start 1227:Bridges in France 1189:(in French). CPE. 1169:Suspension bridge 890:Dossier de presse 770:Dossier de presse 628:Ferdinand Arnodin 471: 470: 402:Technical design 194:suspension bridge 186: 185: 103:Pier construction 57:45.51667; 4.24917 1254: 1190: 1145: 1140: 1139: 1138: 1122: 1121: 1109: 1103: 1102: 1090: 1084: 1083: 1071: 1065: 1064: 1052: 1046: 1045: 1033: 1024: 1023: 1011: 1002: 1001: 989: 980: 979: 977: 975: 954: 948: 947: 945: 931: 925: 924: 922: 908: 899: 898: 885: 879: 878: 876: 874: 853: 847: 846: 844: 842: 821: 808: 807: 795: 789: 788: 782: 774: 765: 759: 758: 753:. Archived from 747: 741: 740: 738: 736: 720: 714: 713: 711: 710: 703:www.leprogres.fr 695: 677:sliding device. 386:Main contractor 365: 321:riparian forests 244:TD 498 deviation 198:Loire department 168:Construction end 63: 62: 60: 59: 58: 53: 49: 46: 45: 44: 41: 19: 18: 1262: 1261: 1257: 1256: 1255: 1253: 1252: 1251: 1207: 1206: 1197: 1181: 1141: 1136: 1134: 1131: 1126: 1125: 1110: 1106: 1091: 1087: 1072: 1068: 1053: 1049: 1034: 1027: 1012: 1005: 990: 983: 973: 971: 956: 955: 951: 943: 933: 932: 928: 920: 910: 909: 902: 887: 886: 882: 872: 870: 855: 854: 850: 840: 838: 823: 822: 811: 796: 792: 776: 775: 767: 766: 762: 749: 748: 744: 734: 732: 721: 717: 708: 706: 697: 696: 692: 687: 651: 620: 604: 599: 582: 569: 549: 522: 517: 497: 481: 476: 363: 340: 309: 246: 241: 200:that spans the 196:located in the 88:Characteristics 56: 54: 50: 47: 42: 39: 37: 35: 34: 24: 17: 12: 11: 5: 1260: 1250: 1249: 1244: 1239: 1234: 1229: 1224: 1219: 1205: 1204: 1196: 1195:External links 1193: 1192: 1191: 1180: 1177: 1176: 1175: 1166: 1153: 1147: 1146: 1130: 1127: 1124: 1123: 1104: 1085: 1066: 1047: 1025: 1003: 981: 949: 926: 900: 880: 848: 809: 790: 760: 742: 729:www.le-pays.fr 715: 689: 688: 686: 683: 650: 647: 619: 616: 603: 600: 598: 595: 581: 578: 568: 565: 548: 545: 541:concrete slabs 521: 518: 516: 513: 496: 493: 480: 477: 475: 472: 469: 468: 462: 458: 457: 454: 451: 447: 446: 443: 439: 438: 435: 432: 428: 427: 422: 418: 417: 414: 411: 407: 406: 403: 399: 398: 395: 391: 390: 387: 383: 382: 377: 376:Project owner 373: 372: 369: 362: 359: 339: 336: 331: 330: 327: 324: 308: 305: 245: 242: 240: 237: 221:Pascal Clément 184: 183: 180: 179: 175: 174: 169: 165: 164: 159: 155: 154: 151: 147: 146: 143: 139: 138: 134: 133: 130: 126: 125: 122: 118: 117: 114: 110: 109: 104: 100: 99: 94: 90: 89: 85: 84: 79: 75: 74: 69: 65: 64: 32: 26: 25: 22: 15: 9: 6: 4: 3: 2: 1259: 1248: 1245: 1243: 1240: 1238: 1235: 1233: 1230: 1228: 1225: 1223: 1220: 1218: 1215: 1214: 1212: 1203: 1199: 1198: 1188: 1183: 1182: 1174: 1170: 1167: 1165: 1161: 1157: 1154: 1152: 1149: 1148: 1144: 1133: 1119: 1116:(in French). 1115: 1108: 1100: 1097:(in French). 1096: 1089: 1081: 1078:(in French). 1077: 1070: 1062: 1059:(in French). 1058: 1051: 1043: 1040:(in French). 1039: 1032: 1030: 1021: 1018:(in French). 1017: 1010: 1008: 999: 996:(in French). 995: 988: 986: 969: 965: 964: 959: 953: 942: 938: 937: 930: 919: 915: 914: 907: 905: 896: 892: 891: 884: 868: 864: 863: 858: 852: 836: 832: 831: 826: 820: 818: 816: 814: 805: 802:(in French). 801: 794: 786: 780: 772: 771: 764: 756: 752: 746: 730: 726: 719: 704: 700: 694: 690: 682: 678: 676: 672: 666: 663: 655: 646: 642: 640: 636: 631: 629: 625: 618:Manufacturing 615: 613: 608: 594: 586: 577: 573: 564: 560: 558: 557:oversize load 554: 547:Manufacturing 544: 542: 538: 533: 531: 525: 512: 509: 505: 501: 488: 484: 466: 463: 460: 459: 455: 452: 448: 444: 441: 440: 436: 433: 429: 426: 423: 420: 419: 415: 412: 408: 404: 400: 396: 392: 388: 384: 381: 378: 374: 366: 358: 355: 351: 348: 344: 335: 328: 325: 322: 318: 317: 316: 313: 304: 297: 293: 290: 287: 285: 281: 276: 273: 271: 267: 263: 259: 255: 254:A72 autoroute 251: 236: 233: 228: 226: 222: 217: 215: 211: 210:A72 autoroute 207: 203: 199: 195: 191: 181: 176: 173: 170: 166: 163: 160: 156: 152: 148: 144: 140: 135: 131: 127: 123: 119: 115: 111: 108: 105: 101: 98: 95: 91: 86: 83: 80: 76: 73: 70: 66: 61: 33: 31: 27: 20: 1186: 1179:Bibliography 1164:Loire Valley 1143:Roads portal 1117: 1113: 1107: 1098: 1094: 1088: 1079: 1075: 1069: 1060: 1056: 1050: 1041: 1037: 1019: 1015: 997: 993: 972:. Retrieved 968:the original 961: 952: 941:the original 935: 929: 918:the original 912: 889: 883: 871:. Retrieved 867:the original 860: 851: 839:. Retrieved 835:the original 828: 803: 799: 793: 769: 763: 755:the original 745: 733:. Retrieved 728: 718: 707:. Retrieved 702: 693: 679: 667: 664: 660: 649:Installation 643: 632: 621: 609: 605: 591: 574: 570: 567:Installation 561: 550: 534: 526: 523: 510: 506: 502: 498: 482: 371:Participant 361:Participants 356: 352: 349: 345: 341: 332: 314: 310: 302: 299:Location map 291: 288: 277: 274: 247: 229: 218: 189: 187: 113:Total length 731:(in French) 705:(in French) 602:Description 537:voided slab 535:The 0.27 m 520:Description 474:Description 270:Haute-Loire 266:Puy-de-Dôme 55: / 30:Coordinates 1211:Categories 1202:Structurae 709:2021-03-01 597:Suspension 410:Companies 394:Architect 40:45°31′00″N 963:zoom45.fr 779:cite book 530:suspender 450:Controls 232:suspender 142:Architect 43:4°14′57″E 1129:See also 895:Archived 735:March 1, 515:The deck 456:Quadric 405:Quadric 397:Strates 178:Location 974:May 20, 873:May 20, 841:May 20, 624:hangers 239:History 137:History 124:20,55 m 68:Crosses 671:Teflon 580:Pylons 442:Metal 437:SECOA 354:2007. 268:, and 258:Bonson 214:Bonson 129:Height 78:Locale 1160:Loire 1120:: 19. 1101:: 18. 1082:: 17. 1063:: 16. 1044:: 13. 1022:: 14. 1000:: 12. 944:(PDF) 921:(PDF) 639:reels 635:reels 368:Role 202:Loire 121:Width 116:270 m 107:Steel 72:Loire 976:2009 875:2009 843:2009 806:: 9. 785:link 737:2021 675:inox 612:HDPE 465:SNCF 282:and 260:and 188:The 172:2008 162:2006 132:40 m 204:at 1213:: 1171:– 1162:- 1158:- 1118:25 1099:25 1080:25 1061:25 1042:25 1028:^ 1020:25 1006:^ 998:25 984:^ 960:. 903:^ 859:. 827:. 812:^ 804:25 781:}} 777:{{ 727:. 701:. 673:/ 630:. 543:. 286:. 272:. 227:. 216:. 978:. 877:. 845:. 787:) 739:. 712:.

Index

Coordinates
45°31′00″N 4°14′57″E / 45.51667°N 4.24917°E / 45.51667; 4.24917
Loire
Saint-Just-Saint-Rambert
Reinforced concrete
Steel
2006
2008
suspension bridge
Loire department
Loire
Saint-Just-Saint-Rambert
A72 autoroute
Bonson
Pascal Clément
Departmental Council of Loire
suspender
Departmental Council of Loire
A72 autoroute
Bonson
Saint-Marcellin-en-Forez
Puy-de-Dôme
Haute-Loire
Saint-Just-Saint-Rambert
Andrézieux-Bouthéon

riparian forests
Departmental Council of Loire
Baudin-Chateauneuf
SNCF

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.