Knowledge

Mississippi River–Gulf Outlet Canal

Source 📝

425:" that could amplify storm surges 20 to 40 percent. Following the storm, an engineering investigation and computer modeling showed that the outlet intensified the initial surge by 20 percent, raised the height of the wall of water about three feet, and increased the velocity of the surge from 3 feet per second (0.9 m/s) to 8 feet per second (2.4 m/s) in the funnel-shaped region between the converging MRGO and Gulf Intracoastal Waterway. Mashriqui believes this funnel effect contributed to the scouring that undermined the levees and floodwalls along the Gulf Outlet, the Intracoastal Waterway, and the Industrial Canal. "Without MRGO, the flooding would have been much less," he said. "The levees might have overtopped, but they wouldn't have been washed away." The 387: 311: 231: 449: 43: 319: 833: 530:
and another across the Intracoastal Waterway, to permit the passage of barge and other small commercial traffic during normal weather conditions. The barrier, the largest of its kind in the United States, should protect against storm surges up to 28 feet in height. It was finished in 2011, and is far
377:
According to a congressional hearing statement made in late 2005 by Scott Faber of the Environmental Defense Fund, "Traffic on the MR-GO has fallen by more than 50 percent since 1986. As of 2005, less than one oceangoing vessel per day, on average, used the MRGO canal, which costs approximately $ 13
354:
The promised economic development along the 76 mile channel in poverty-stricken St. Bernard Parish has yet to materialize. What the MRGO has delivered is an $ 8-plus million yearly maintenance plan for commercial and recreational waterborne traffic. The nearly $ 1 billion price tag for the less than
456:
In May 2007 the Corps of Engineers announced it would close the MRGO to all traffic and would build an earthen dam across the MRGO in alignment with the natural ridge paralleling Bayou La Loutre. The Bayou La Loutre ridge siting was selected to complement future wetland restoration efforts, as the
503:
The MRGO Ecosystem Restoration Plan was never implemented due to a disagreement about funding. The U.S. Army Corps of Engineers' District Engineer stated "I further recommend Federal and Non-Federal Sponsor responsibilities and cost sharing requirements...," while the State of Louisiana viewed the
273:
In 1943, the proposed project was initially presented to the U.S. Army Corps of Engineers by the Dock Board of New Orleans under the name "Alexander Seaway", in reference to Col. Lester F. Alexander, a member of the Dock Board who was one of the architects behind the New Orleans plan. A competing
301:
of the surrounding marsh, the canal was already as much as four times wider by 2005 than as originally constructed. When MRGO was built, the channel was 650 feet (200 m) wide at the surface. By 2005 the channel had opened to up to 3,000 feet in some locations and had been dredged annually.
221:
to the Gulf of Mexico near Gardner Island. Much criticized for its negative environmental effects, such as saltwater intrusion, wetlands erosion and storm surge amplification during Hurricane Katrina, the MRGO was closed in 2009. Maritime traffic was barred on April 22, 2009.
285:
connecting the Industrial Canal to the Mississippi River obsolete; the MRGO as promoted in the 1950s was to help rectify this deficiency by permitting deep-draft vessels to access the Industrial Canal inner harbor. Authorization for the MRGO was formally provided by the
338:
After the abandonment of the Centroport project, the Port of New Orleans refocused its efforts on improving its infrastructure along the Mississippi River, and what little maritime traffic the MRGO hosted progressively dwindled, opening it up to withering critiques.
531:
more significant than the Bayou La Loutre closure structure. It is two feet lower than the levees it will connect to in New Orleans East and St. Bernard Parish. This will allow water to spill over the control structure before it overtops these levees.
335:, never secured sufficient funding and was quietly jettisoned by the port in the mid-1980s. The France Road Container Terminal and the Jourdan Road Wharf were the only two elements realized according to the Centroport plan. 330:
advanced a plan to largely abandon its wharfs along the Mississippi River and relocate its activities to the inner harbor created by the Industrial Canal, the Intracoastal Waterway, and the MRGO. This vast project, termed
197:
experienced by the region's hurricane protection network. In the aftermath the channel was closed. A permanent storm surge barrier was constructed in the MRGO in 2009, and the channel has been closed to maritime shipping.
545: 429:
disputes this causality and maintains Katrina would have overwhelmed the levees with or without the contributing effect of MRGO since the storm surge was perpendicular to the length of the canal.
504:"project should be undertaken at full Federal expense and that the state should have no financial obligations with respect to the Mississippi River Gulf Outlet Ecosystem Restoration Project." 526:
and the southern edge of the MRGO, preventing future storm surges from penetrating into the inner harbor of the Industrial Canal and Intracoastal Waterway. Two gates were built, one at
522:
costing more than $ 1 billion was constructed. The surge barrier closed the narrow end of the "funnel" described by the convergence of the levees bounding the northern edge of the
378:
million annually to maintain. Like many waterways constructed by the Corps, the MR-GO failed to attract as much traffic as the Corps predicted when the project was constructed."
436:
immediately opposed its reopening. Maritime interests called for re-opening the Gulf Outlet but equipping it with protective floodgates, or accelerating construction of the
970: 234:
The MRGO and an outlet into Lake Borgne, approximately 50 miles (80 km) up the canal from its mouth and 15 miles (24 km) east of New Orleans (view towards the southwest)
911: 60: 828: 464: 496:
71 miles of shoreline protection in Lake Borgne, along the MRGO, and in the Biloxi Marsh, including 5.8 miles of oyster reef restoration in the Biloxi Marsh
107: 17: 79: 467:. The plan outline key components of revitalizing the wetlands and water bodies that had been damaged by the construction and resulting factors (e.g. 355:
two large container ships a day that use the channel is baffling, especially considering that the channel only shaved 37 miles off the original route.
783: 733:
Southeastern Louisiana University, The SLU Poll: Attitudes Among St. Bernard Parish Voters About The Mississippi River Gulf Outlet, Date: 5/26/2004
632: 614: 238:
Conceptually, the MRGO was first envisioned early in the 20th century as a way to provide shipping with a shorter route to the Gulf of Mexico. The
86: 757:"Investigators Link Levee Failures to Design Flaws; Three Teams of Engineers Find Weakened Soil, Navigation Canal Contributed to La. Collapses" 460:
Construction began in late 2008, and the Corps of Engineers completed the closure structure across the MRGO at Bayou La Loutre in July 2009.
93: 374:. MRGO was derisively termed a "Hurricane Highway" in Katrina's wake, due to its apparent role in amplifying the impacts of storm surges. 432:
Katrina's passage caused extensive shoaling of the MRGO, resulting in its impassability for deep-draft oceangoing vessels. Officials of
75: 194: 893: 980: 363:, environmentalists and others, including voters in St. Bernard Parish whom the canal was intended to help, called for its closure. 661: 246:
from the Gulf to the port's wharfs, versus the much closer proximity to open water offered by its emerging competitors. The modern
955: 426: 159: 756: 555: 100: 883: 721: 398:
Levees along the MRGO and the Intracoastal Waterway were breached in approximately 20 places, directly flooding most of
242:
felt increasingly disadvantaged by the length of time oceangoing vessels needed to navigate the twists and turns of the
350:
organization dedicated to "the principles of free enterprise and limited government" attacked it on economic grounds:
126: 812: 744:
Faber, Scott (2005), U.S. Senate Committee on Environment & Public Works, Hearing Statements, Date: 11/09/2005
577: 457:
natural ridge could regain its historic function of sheltering the marsh and swamp behind from the Gulf of Mexico.
343: 960: 975: 965: 950: 513: 64: 433: 399: 371: 214: 662:"New Orleans District > Missions > Environmental > MRGO Ecosystem Restoration > History of MRGO" 274:
plan was also presented by Jefferson Parish, referred to as the "Arrow to the Americas,' also known as the
796: 687:"How a Navigational Channel Contributed to Most of the Flooding of New Orleans During Hurricane Katrina" 686: 640: 618: 593: 421:'s Hurricane Center, called MRGO a "critical and fundamental flaw" in the Corps' hurricane defenses, a " 791: 523: 418: 206: 440:, which when completed would allow MRGO to be closed without affecting deep-draft commercial traffic. 406:. Storm surge from the MRGO is also a leading suspect in the three breaches of floodwalls along the 366:
Criticism intensified following the hurricane, when engineers implicated the MRGO in the failure of
874: 734: 53: 546:
U.S. Army Corps of Engineers civil works controversies (New Orleans)#Legal issues in New Orleans
291: 287: 281:
In a matter of decades, the rapid growth of average ship size in the 20th century rendered the
162:
at the direction of Congress in the mid-20th century that provided a shorter route between the
314:
Intersection of MRGO (to right) with the Gulf Intracoastal Waterway, as seen from I-510 Bridge
282: 175: 391: 251: 8: 745: 468: 463:
Supplementing construction of the closure, the Army Corps of Engineers also produced the
403: 327: 267: 239: 210: 190: 259: 865: 452:
Closure structure across MRGO at Bayou La Loutre shortly before completion, July 2009
360: 254:
in 1914. New Orleans' initial response debuted in 1923, with the inauguration of the
243: 182: 701: 550: 540: 437: 407: 275: 263: 255: 171: 581: 527: 247: 482: 347: 202: 163: 706: 944: 926: 913: 837: 519: 386: 310: 230: 31: 422: 250:, in particular, came into being as a consequence of the completion of the 414: 218: 186: 167: 898: 574: 724:" Competitive Enterprise Institute, May 1, 1997 (archived 2006-12-08) 448: 42: 836:
This article incorporates text from this source, which is in the
298: 594:"Goodbye MRGO: Work begins to close shortcut to Gulf of Mexico" 390:
Inscription on house in storm-surge devastated neighborhood of
318: 633:"Inner Harbor Navigation Canal Evaluation Report, March 1997" 367: 322:
Tugboat and barge in MRGO at Shell Beach, St. Bernard Parish
158:) is a 76 mi (122 km) channel constructed by the 894:
U.S. Waterborne Container Traffic by Port/Waterway in 2003
903: 471:) of the MRGO. The roughly $ 2.9 billion plan included: 899:
U.S. Seaports: At the Crossroads of the Global Economy
381: 866:
Army Corps liable for Katrina damage, US court finds
475:
A freshwater diversion at or near Violet, Louisiana
67:. Unsourced material may be challenged and removed. 971:Flood control in the New Orleans metropolitan area 413:Three months before Katrina, Hassan Mashriqui, a 305: 942: 30:"MR-GO" redirects here. Not to be confused with 294:of 1956. Construction was completed in 1968. 394:suggests that the ruins be used to fill MRGO. 478:14,123 acres of fresh and intermediate marsh 438:Inner Harbor Navigational Canal lock project 141:Route of Mississippi River–Gulf Outlet Canal 684: 850:Surge barrier spells death knell for MR-GO 370:and flood-walls protecting large parts of 884:"Canal May Have Worsened City's Flooding" 705: 518:Closer to New Orleans, a robust 1.8 mile 493:54 acres of Bayou La Loutre ridge habitat 326:With the completion of MRGO in 1965, the 127:Learn how and when to remove this message 829:MRGO Ecosystem Restoration Plan by USACE 637:Corps of Engineers, New Orleans District 447: 385: 317: 309: 229: 195:subsequent multiple engineering failures 27:Former canal in Louisiana, United States 852:, The Times-Picayune, October 22, 2009. 625: 617:. WWLtv.com. 2009-04-22. Archived from 14: 943: 824: 822: 820: 781: 160:United States Army Corps of Engineers 76:"Mississippi River–Gulf Outlet Canal" 193:, contributing significantly to the 65:adding citations to reliable sources 36: 782:Brown, Matthew (October 24, 2005). 685:van Heerden, I. L. (October 2009). 556:List of canals in the United States 148:Mississippi River–Gulf Outlet Canal 24: 18:Mississippi River-Gulf Outlet Canal 817: 784:"Katrina may mean MR-GO has to go" 382:Role in Hurricane Katrina disaster 258:linking the Mississippi River and 25: 992: 859: 981:1965 establishments in Louisiana 831: 507: 344:Competitive Enterprise Institute 41: 890:, Wednesday, September 14, 2005 843: 806: 775: 749: 465:MRGO Ecosystem Restoration Plan 52:needs additional citations for 956:Canals in Saint Bernard Parish 738: 727: 714: 678: 654: 607: 586: 568: 514:IHNC Lake Borgne Surge Barrier 306:MRGO's operational performance 13: 1: 487:10,318 acres of cypress swamp 213:and takes a path SSE through 201:The MRGO begins just west of 181:In 2005, the MRGO channeled 7: 534: 10: 997: 792:New Orleans Times-Picayune 694:Public Organization Review 615:"MRGO now closed to ships" 511: 443: 419:Louisiana State University 225: 207:Gulf Intracoastal Waterway 29: 869:Christian Science Monitor 707:10.1007/s11115-009-0093-8 490:466 acres of saline marsh 720:Barrett, David (1997), " 561: 427:Army Corps of Engineers 262:, thereby creating the 961:History of New Orleans 666:www.mvn.usace.army.mil 596:. NOLA.com. 2009-01-31 453: 395: 357: 323: 315: 292:Rivers and Harbors Act 288:United States Congress 235: 217:wetlands just west of 976:Canals opened in 1965 966:Intracoastal Waterway 951:Canals in New Orleans 927:29.89126°N 89.75744°W 877:The Control of Nature 722:Washington Waterworld 524:Intracoastal Waterway 499:2 recreation features 451: 389: 352: 321: 313: 233: 176:Intracoastal Waterway 802:on 3 September 2006. 469:salt water intrusion 392:Chalmette, Louisiana 252:Houston Ship Channel 61:improve this article 932:29.89126; -89.75744 923: /  904:Port of New Orleans 761:The Washington Post 372:Greater New Orleans 328:Port of New Orleans 240:Port of New Orleans 191:Greater New Orleans 763:. October 24, 2005 580:2012-03-12 at the 454: 434:St. Bernard Parish 400:St. Bernard Parish 396: 324: 316: 260:Lake Pontchartrain 236: 215:St. Bernard Parish 189:into the heart of 871:November 19, 2009 361:Hurricane Katrina 333:Centroport U.S.A. 244:Mississippi River 183:Hurricane Katrina 137: 136: 129: 111: 16:(Redirected from 988: 938: 937: 935: 934: 933: 928: 924: 921: 920: 919: 916: 853: 847: 841: 835: 834: 826: 815: 810: 804: 803: 801: 795:. Archived from 788: 779: 773: 772: 770: 768: 753: 747: 742: 736: 731: 725: 718: 712: 711: 709: 691: 682: 676: 675: 673: 672: 658: 652: 651: 649: 648: 639:. Archived from 629: 623: 622: 611: 605: 604: 602: 601: 590: 584: 572: 551:Jefferson Seaway 541:Containerization 481:32,511 acres of 408:Industrial Canal 404:New Orleans East 276:Jefferson Seaway 268:New Orleans East 256:Industrial Canal 211:New Orleans East 205:crossing of the 172:Industrial Canal 150:(abbreviated as 132: 125: 121: 118: 112: 110: 69: 45: 37: 21: 996: 995: 991: 990: 989: 987: 986: 985: 941: 940: 931: 929: 925: 922: 917: 914: 912: 910: 909: 888:Washington Post 862: 857: 856: 848: 844: 832: 827: 818: 811: 807: 799: 786: 780: 776: 766: 764: 755: 754: 750: 743: 739: 732: 728: 719: 715: 689: 683: 679: 670: 668: 660: 659: 655: 646: 644: 631: 630: 626: 613: 612: 608: 599: 597: 592: 591: 587: 582:Wayback Machine 575:History of MRGO 573: 569: 564: 537: 528:Bayou Bienvenue 516: 510: 446: 384: 308: 248:Port of Houston 228: 170:' inner harbor 144: 143: 142: 133: 122: 116: 113: 70: 68: 58: 46: 35: 28: 23: 22: 15: 12: 11: 5: 994: 984: 983: 978: 973: 968: 963: 958: 953: 907: 906: 901: 896: 891: 881: 879:by John McPhee 872: 861: 860:External links 858: 855: 854: 842: 816: 805: 774: 748: 737: 726: 713: 700:(4): 291–308. 677: 653: 624: 621:on 2009-04-26. 606: 585: 566: 565: 563: 560: 559: 558: 553: 548: 543: 536: 533: 512:Main article: 509: 506: 501: 500: 497: 494: 491: 488: 485: 483:brackish marsh 479: 476: 445: 442: 383: 380: 307: 304: 264:Lower 9th Ward 227: 224: 164:Gulf of Mexico 140: 139: 138: 135: 134: 49: 47: 40: 26: 9: 6: 4: 3: 2: 993: 982: 979: 977: 974: 972: 969: 967: 964: 962: 959: 957: 954: 952: 949: 948: 946: 939: 936: 905: 902: 900: 897: 895: 892: 889: 885: 882: 880: 878: 875:Excerpt from 873: 870: 867: 864: 863: 851: 846: 839: 838:public domain 830: 825: 823: 821: 813: 809: 798: 794: 793: 785: 778: 762: 758: 752: 746: 741: 735: 730: 723: 717: 708: 703: 699: 695: 688: 681: 667: 663: 657: 643:on 2006-06-21 642: 638: 634: 628: 620: 616: 610: 595: 589: 583: 579: 576: 571: 567: 557: 554: 552: 549: 547: 544: 542: 539: 538: 532: 529: 525: 521: 520:surge barrier 515: 508:Surge Barrier 505: 498: 495: 492: 489: 486: 484: 480: 477: 474: 473: 472: 470: 466: 461: 458: 450: 441: 439: 435: 430: 428: 424: 420: 416: 411: 409: 405: 401: 393: 388: 379: 375: 373: 369: 364: 362: 356: 351: 349: 345: 342:In 1997, the 340: 336: 334: 329: 320: 312: 303: 300: 297:Due to rapid 295: 293: 289: 284: 279: 277: 271: 269: 265: 261: 257: 253: 249: 245: 241: 232: 223: 220: 216: 212: 208: 204: 199: 196: 192: 188: 184: 179: 177: 173: 169: 165: 161: 157: 153: 149: 131: 128: 120: 109: 106: 102: 99: 95: 92: 88: 85: 81: 78: –  77: 73: 72:Find sources: 66: 62: 56: 55: 50:This article 48: 44: 39: 38: 33: 32:Mr. Go (film) 19: 908: 887: 876: 868: 849: 845: 808: 797:the original 790: 777: 765:. Retrieved 760: 751: 740: 729: 716: 697: 693: 680: 669:. Retrieved 665: 656: 645:. Retrieved 641:the original 636: 627: 619:the original 609: 598:. Retrieved 588: 570: 517: 502: 462: 459: 455: 431: 423:Trojan Horse 412: 397: 376: 365: 358: 353: 341: 337: 332: 325: 296: 280: 272: 237: 200: 180: 155: 151: 147: 145: 123: 114: 104: 97: 90: 83: 71: 59:Please help 54:verification 51: 930: / 415:storm surge 348:libertarian 283:canal locks 219:Lake Borgne 187:storm surge 168:New Orleans 945:Categories 918:89°45′27″W 915:29°53′29″N 671:2018-07-09 647:2006-04-02 600:2009-01-31 417:expert at 117:April 2010 87:newspapers 359:Prior to 814:MRGO.gov 578:Archived 535:See also 174:via the 767:May 15, 444:Closure 299:erosion 290:in the 226:History 203:I-510's 101:scholar 368:levees 103:  96:  89:  82:  74:  800:(PDF) 787:(PDF) 690:(PDF) 562:Notes 152:MR-GO 108:JSTOR 94:books 769:2011 402:and 346:, a 266:and 166:and 156:MRGO 146:The 80:news 702:doi 209:in 185:'s 178:. 154:or 63:by 947:: 886:, 819:^ 789:. 759:. 696:. 692:. 664:. 635:. 410:. 278:. 270:. 840:. 771:. 710:. 704:: 698:9 674:. 650:. 603:. 130:) 124:( 119:) 115:( 105:· 98:· 91:· 84:· 57:. 34:. 20:)

Index

Mississippi River-Gulf Outlet Canal
Mr. Go (film)

verification
improve this article
adding citations to reliable sources
"Mississippi River–Gulf Outlet Canal"
news
newspapers
books
scholar
JSTOR
Learn how and when to remove this message
United States Army Corps of Engineers
Gulf of Mexico
New Orleans
Industrial Canal
Intracoastal Waterway
Hurricane Katrina
storm surge
Greater New Orleans
subsequent multiple engineering failures
I-510's
Gulf Intracoastal Waterway
New Orleans East
St. Bernard Parish
Lake Borgne

Port of New Orleans
Mississippi River

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.