management peer reviews of major construction projects, which include civil construction projects and the construction of large experimental equipment. While the Office of Science is exempt from DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets for independent project and peer review, a Lehman Review will typically meet the requirements of the order. During a project's proposal and construction phase, Lehman Reviews are generally held twice a year, although a review may be held by request.
28:. Lehman Reviews evaluate all aspects of a construction project's current status, including technical aspects, cost, schedule and management, and they are usually held twice a year. Lehman Reviews are widely known in DOE, other agencies and abroad. The reviews are named after Daniel Lehman, Director of the DOE Office of Science's Office of Project Assessment since 1991. 44:
Lehman Reviews typically include dozens of independent technical experts. These experts may be divided into six or more subpanels to address all aspects of a project. A Lehman Review can potentially result in modifications to a project's cost, scope or schedule, and could also prompt work stoppage
40:
provides independent advice relating to those activities essential to the construction and operation of major research facilities, as well as professional management and staff support regarding these functions. Within this mission, the office conducts independent technical, cost, schedule and
95:
were called "Temple Reviews," named after Ed Temple, Director of the Construction Management Support Division in the Office of Energy Research (January 1980 - December 1990).
348: 297: 209: 68:. Other non- or non-exclusively DOE projects that have conducted reviews in the style of a Lehman Review include the construction project for the 522: 571: 57: 566: 417:. New Century of X-ray Astronomy, ASP Conference Proceedings Vol. 251, San Francisco: Astronomical Society of the Pacific, 2001, p. 196. 374: 266: 528: 199:
Chemical Sciences Roundtable, et al. "Assessing the Value of Research in the Chemical Sciences". National Academy Press, 1998 p. 104
65: 48:
Some major projects that have been subject to Lehman Reviews within the DOE complex include the ongoing construction of the
534: 53: 535:
DOE National Laboratories Improvement Council’s White Paper on Management of Major Research Facility Construction Projects
452: 251:
Office of Science Has Kept Majority of Projects within Budget and on Schedule, but Funding and Other Challenges May Grow
119: 21: 352: 238: 69: 49: 301: 486:
on December 19, 2008, Niels Bohr Library & Archives, American Institute of Physics, College Park, MD USA
52:; construction of the Linac Coherent Light Source (LCLS) and subsequent construction of its upgrade at the 504:
on May 6, 2009, Niels Bohr Library & Archives, American Institute of Physics, College Park, MD USA
400: 546: 20:
is an independent peer review and evaluation of the status of a major construction project in the
378: 144: 334: 283: 61: 375:"The U.S. Department of Energy's Thomas Jefferson National Accelerator Facility - on Target" 576: 8: 501: 483: 114: 109: 124: 92: 37: 25: 56:; the 12 GeV Upgrade of the Continuous Electron Beam Accelerator Facility at the 496: 478: 172: 91:
Before Lehman Reviews, peer reviews of major construction projects within DOE's
456: 85: 517: 560: 250: 104: 322: 427: 298:"Independent review finds FRIB ready to baseline | frib.msu.edu" 349:"DOE Performs Important CD-2 Review for LCLS-II | SLAC Today" 551: 531:
PMWG EFCOG Meeting presentation, December 2013, Daniel R. Lehman
81: 529:
Successful Project Management Practices in Office of Science
77: 73: 413:
Kamae, T. & GLAST Large Area Telescope Collaboration.
76:
and InterAction Collaboration Peer Reviews (conducted for
249:
United States Government Accountability Office (2008),
60:; and construction of the User Support Building at the 525:
Frank Munger's Atomic City Underground on Knoxnews.com
552:
DOE's Office of Science Office of Project Assessment
335:"LCLS - Linac Coherent Light Source Project Reviews" 210:"Removal of EM Projects from the GAO High Risk List" 36:The Office of Project Assessment within the DOE's 415:Science with Gamma-ray Large Area Space Telescope 558: 261: 259: 88:'s Science & Technology Facilities Council. 58:Thomas Jefferson National Accelerator Facility 256: 195: 193: 428:"Latest Lehman Review completed at US ITER" 284:"DOE cancels NCSX. - Free Online Library" 190: 453:"InterAction Collaboration Peer Reviews" 518:Congressman Foster honors Daniel Lehman 559: 231: 167: 165: 572:Public inquiries in the United States 323:http://www.nuclearmatters.org/?p=1682 66:Lawrence Berkeley National Laboratory 145:"Office of Project Assessment (OPA)" 54:SLAC National Accelerator Laboratory 162: 13: 567:United States Department of Energy 523:Moving toward 20 petaflops at ORNL 511: 120:United States Department of Energy 22:United States Department of Energy 14: 588: 540: 479:Interview of Dr. Alan Schriesheim 547:Project Management Working Group 489: 471: 445: 420: 407: 393: 367: 341: 327: 316: 70:Fermi Gamma-ray Space Telescope 50:Facility for Rare Isotope Beams 290: 276: 243: 202: 137: 1: 130: 7: 98: 10: 593: 497:Interview of Joanne S. Day 31: 45:and management changes. 237:Congressional Record, 62:Advanced Light Source 459:on November 28, 2009 401:"ALSNews Newsletter" 253:, GAO-08-641, page 1 219:. September 15, 2010 381:on February 3, 2014 304:on February 7, 2014 267:"Office of Science" 173:"Office of Science" 502:Catherine Westfall 484:Catherine Westfall 115:Project management 110:Independent review 125:Office of Science 93:Office of Science 38:Office of Science 26:Office of Science 584: 505: 493: 487: 475: 469: 468: 466: 464: 455:. Archived from 449: 443: 442: 440: 438: 424: 418: 411: 405: 404: 397: 391: 390: 388: 386: 377:. Archived from 371: 365: 364: 362: 360: 351:. Archived from 345: 339: 338: 331: 325: 320: 314: 313: 311: 309: 300:. Archived from 294: 288: 287: 280: 274: 273: 271: 263: 254: 247: 241: 239:January 14, 2014 235: 229: 228: 226: 224: 214: 206: 200: 197: 188: 187: 185: 183: 169: 160: 159: 157: 155: 141: 592: 591: 587: 586: 585: 583: 582: 581: 557: 556: 543: 514: 512:Further reading 509: 508: 494: 490: 476: 472: 462: 460: 451: 450: 446: 436: 434: 426: 425: 421: 412: 408: 399: 398: 394: 384: 382: 373: 372: 368: 358: 356: 355:on July 1, 2013 347: 346: 342: 333: 332: 328: 321: 317: 307: 305: 296: 295: 291: 282: 281: 277: 269: 265: 264: 257: 248: 244: 236: 232: 222: 220: 212: 208: 207: 203: 198: 191: 181: 179: 171: 170: 163: 153: 151: 143: 142: 138: 133: 101: 34: 12: 11: 5: 590: 580: 579: 574: 569: 555: 554: 549: 542: 541:External links 539: 538: 537: 532: 526: 520: 513: 510: 507: 506: 488: 470: 444: 419: 406: 392: 366: 340: 326: 315: 289: 275: 255: 242: 230: 201: 189: 161: 135: 134: 132: 129: 128: 127: 122: 117: 112: 107: 100: 97: 86:United Kingdom 33: 30: 9: 6: 4: 3: 2: 589: 578: 575: 573: 570: 568: 565: 564: 562: 553: 550: 548: 545: 544: 536: 533: 530: 527: 524: 521: 519: 516: 515: 503: 499: 498: 492: 485: 481: 480: 474: 458: 454: 448: 433: 429: 423: 416: 410: 402: 396: 380: 376: 370: 354: 350: 344: 336: 330: 324: 319: 303: 299: 293: 285: 279: 268: 262: 260: 252: 246: 240: 234: 218: 211: 205: 196: 194: 178: 174: 168: 166: 150: 146: 140: 136: 126: 123: 121: 118: 116: 113: 111: 108: 106: 103: 102: 96: 94: 89: 87: 83: 79: 75: 71: 67: 63: 59: 55: 51: 46: 42: 39: 29: 27: 23: 19: 18:Lehman Review 495: 491: 477: 473: 461:. Retrieved 457:the original 447: 435:. Retrieved 431: 422: 414: 409: 395: 383:. Retrieved 379:the original 369: 357:. Retrieved 353:the original 343: 329: 318: 306:. Retrieved 302:the original 292: 278: 245: 233: 221:. Retrieved 216: 204: 180:. Retrieved 176: 152:. Retrieved 148: 139: 90: 47: 43: 35: 17: 15: 577:Peer review 105:Peer review 24:'s (DOE's) 561:Categories 463:January 9, 385:January 9, 359:January 9, 308:January 9, 217:energy.gov 177:Energy.gov 149:Energy.gov 131:References 437:June 29, 223:June 29, 182:June 29, 154:June 29, 99:See also 84:and the 32:History 82:TRIUMF 500:, by 482:, by 270:(PDF) 213:(PDF) 465:2014 439:2023 432:ITER 387:2014 361:2014 310:2014 225:2023 184:2023 156:2023 78:CERN 74:ITER 64:at 563:: 430:. 258:^ 215:. 192:^ 175:. 164:^ 147:. 80:, 72:, 16:A 467:. 441:. 403:. 389:. 363:. 337:. 312:. 286:. 272:. 227:. 186:. 158:.

Index

United States Department of Energy
Office of Science
Office of Science
Facility for Rare Isotope Beams
SLAC National Accelerator Laboratory
Thomas Jefferson National Accelerator Facility
Advanced Light Source
Lawrence Berkeley National Laboratory
Fermi Gamma-ray Space Telescope
ITER
CERN
TRIUMF
United Kingdom
Office of Science
Peer review
Independent review
Project management
United States Department of Energy
Office of Science
"Office of Project Assessment (OPA)"


"Office of Science"


"Removal of EM Projects from the GAO High Risk List"
January 14, 2014
Office of Science Has Kept Majority of Projects within Budget and on Schedule, but Funding and Other Challenges May Grow

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.