1199:
795:
1159:
63:
2328:
1240:
of 365 MW were reduced to 150 MW and were not extended beyond 2007. Notwithstanding this forced reduction in supply from
Argentina over the low hydrology period of 2004–06, UTE was able to maintain energy imports through a noticeable increase of imports from Brazil and purchase of energy from the Argentine spot market. In 2008, supply costs increased substantially as the drought, high fuel costs and low availability of power in neighboring countries.
1249:
power generation; (iii) increasing regional energy trade; and (iv) facilitating availability and acquisition of energy efficient goods and services, including efforts to raise public awareness regarding demand-side management interventions. According to the
National Directorate for Energy and Nuclear Technology (DNETN), grid-connected wind power generation is one of the domestic resources with both medium and long term potential in Uruguay.
1144:
180:
22:
99:
807:", is being built in the Punta del Tigre site; construction started in late 2013 and final completion is expected by late 2018. The existing large hydroelectric potential has already been developed and the existing thermal units are low performing. Total generation in the year 2008 was 8,019 GWh, 56.1% of which were from hydroelectric sources, with 42.2% being thermal.
1227:
into a competitive market. The market did not develop as planned and demand actually decreased due to the economic crisis in the region. For instance, natural gas provision, which could have supplied new power generating units, did not materialize. Although URSEA and ADME were established, they cannot yet fulfil most of the functions established in their mandate.
1236:
production facilities during this extended period was the product of a conscious, strategic decision to take advantage of market developments in
Argentina and in the region, which would allow imports to fill any Uruguayan shortfalls, while exporting hydropower surplus production to Argentina and Brazil during wet years.
1256:
Interconnecting with Brazil is also particularly attractive. The expansion of the interconnection capacity with Brazil may be carried out either along the Coast or from Salto Grande. This expansion would contribute to diversifying the supply sources and could be done in order to take advantage of the
1226:
The reform has not been effectively implemented. After passing the modifications to the electricity law, secondary legislation was not forthcoming and the system continued to operate without any significant change. The new model was regulated in 2002 and it was expected that new operators would enter
1239:
Dependence on imports from
Argentina started to become problematic in 2004. Before 2004, UTE was able to supply its demand through a combination of contracts and purchases on the Argentinean spot market. As a result of the Argentine energy difficulties, UTE's contracts with Argentina for firm supply
1058:
Access to electricity in
Uruguay is very high, above 98.7%. This coverage is above average for countries with public electricity services. Quality of service is perceived to be good both by companies and residential users. Companies suffer losses of just about 1.1% of their sales due to electricity
1235:
For a full decade no power capacity was added to the power system. Prior to the completion of the 100 MW Punta del Tigre diesel power plant in August 2005, UTE had not added a power station to the system since 1995, when the last unit of Salto Grande came online. The absence of commissioning of new
1037:
In the period 2002–2007, after the 2002-2003 economic and financial crisis, electricity demand increased 4.9% per year on average. Electricity demand increased by 7.5% between 2006 and 2007, from 6,613 GWh to 7,112 GWh, reaching a per capita value of 2,143 kWh. Yearly demand increase is expected to
1252:
The government has taken action to promote RE development. In March 2006, the executive power issued Decree No.77/2006 to foster private generation through wind, biomass and small hydropower plants. A target of 60 MW was established for the first tender, which was conducted by UTE in August 2006.
815:
In the years leading up to 2009, the
Uruguayan electricity system has faced difficulties to supply the increasing demand from its domestic market. In years of low rainfall, there is a high dependency on imports from Brazil and Argentina. Exports have historically been negligible. In particular, no
1342:. The objective this project is to increase the demand for and competitive supply of energy efficiency goods and services, contributing to improved efficiency of energy use, reduced reliance of the Uruguayan economy on imported electricity and fuels, and reduced emissions from the energy sector.
1248:
The Energy
Strategy Guidelines for Uruguay were defined in 2006 by the Ministry of Industry, Energy and Mines (MIEM). This strategy includes: (i) diversifying energy sources to reduce costs and emissions, as well as increase energy security; (ii) increasing private participation in new renewable
1173:
The
National Environmental Directorate (DINAMA) received several requests for new wind projects by 2009 and UTE had a very positive response to the bidding process launched that year. In August 2009, the government of Uruguay approved a Decree that allows UTE to bid 150 MW of wind power. USD 300
1222:
In 1997, the national electricity law was updated following the principles of the so-called “standard model,” which contemplated the separation of regulatory/governance functions from corporate functions, and put in place the regulatory agency URSEA and a market administrator, ADME. The reform
1091:
Currently, there are four private companies that generate electricity for their own consumption and sell their surplus to the grid: Botnia (biomass, 161 MW), Agroland (wind, 0.3 MW), Nuevo
Manantial (wind, 10 MW) and Zenda (natural gas, 3.2 MW). The Azucarlito plant (5 MW) operates in the spot
1082:
The
National Directorate of Energy and Nuclear Technology (DNTEN) formulates energy-sector policies. The regulatory functions are assigned to URSEA, the regulatory body. Both transmission and distribution activities are fully under the control of UTE, as established by the 1997 law.
556:
The shift to renewable energy sources in recent years has been achieved thanks to modernization efforts, based on legal and regulatory reforms in 1997, 2002, and 2006, which have led to large new investments in electrical production capacity including from the
622:, the national utility. The remaining capacity corresponds to the Salto Grande hydroelectric plant (945 MW), to co-generation or to small private investments in renewable sources. The table below shows the plants that are operated and owned by UTE as of 2008:
2135:
1178:, started operations in October 2008. A few months later, in January 2009, UTE's 10 MW wind farm in Sierra de los Caracoles also started operations. By 2016 Uruguay had enough wind power to export to Argentina and Brazil at times of high generation.
1184:
based on renewable sources such as rice husk could generate up to 20 MW at competitive prices. Firewood has already been used as a substitute for fuel oil in the 1980s, and cellulose projects expect to generate up to 65 MW for sales to the network.
548:
from petroleum fired power plants, activated during peak demand, used to provide the remaining installed production capacity. Generation from fossil fuel decreased substantially in recent years, with renewables accounting for 94.5% of
1073:
UTE has implemented a series of measures to reduce electricity losses, which were particularly high during the 2002-2003 crisis. In December 2007, losses were still high, about 18%, of which 7% to 8% were of technical nature.
606:
The power system exhibits characteristics and issues of hydro-based generation. The apparently wide reserve margin conceals the vulnerability to hydrology. In dry years it is necessary to import over 25% of the demand from
802:
Installed capacity had barely changed between 1995 and 2008. The most recent addition was the 300 MW Punta del Tigre Plant, whose last units started operations in 2008. A 530 MW dual fuel (gas/light oil) CCGT power plant,
1394:
565:
capacity has gone from negligible in 2012 to 10% of installed capacity by 2014. A new, highly efficient combined cycle power plant which can run on either gas or oil has been installed. A number of photovoltaic
2125:
1253:
Although bids received for wind and biomass projects were all higher than US$ 70/MWh, this can be attributed to the small size of the proposed projects and the uncertainty of contractual arrangements.
1155:
projects in Uruguay has already been developed. Existing plants are Terra (152 MW), Baygorria (108 MW), Constitucion (333 MW) and the bi-national Salto Grande, with a total capacity of 1,890 MW.
2130:
1223:
contemplated the remuneration of generators in order of merit, the creation of a wholesale market with regulated prices in transmission and distribution, where competition is not possible.
2092:
1390:
2072:
1046:
Maximum demand on the order of 1,500 MW (historic peak demand, 1,668 MW happened in July 2009) is met with a generation system of about 2,200 MW capacity. This apparently wide
1335:
741:
1682:
542:. The production from these hydropower sources is dependent on seasonal rainfall patterns, but under normal hydrological conditions, can supply off-peak domestic demand.
1615:
2314:
1594:
1456:
1899:
1015:
Total electricity consumption in 2008 was 7,114 GWh, which corresponds to a per capita consumption of 2,729 kWh. Share of consumption by sector was as follows:
1207:
1425:
1996:
804:
561:. Purchasing agreement offered by the government in the final reform in 2006 incentivized a rapid growth of sustainable energy capacity in the country.
1980:
530:
provides a large percentage of installed production capacity in Uruguay, almost all of it produced by four hydroelectric facilities, three on the
2689:
1092:
market. The current 6% private contribution to the generation park is expected to increase as investments in new wind power plants materialize.
1066:
region. In 2004, the average number of interruptions per subscriber was 7.23, while duration of interruptions per subscriber was 9.8 hours. The
35:
2024:
1536:
1503:
1837:
2217:
2684:
2963:
2170:
1004:
1689:
999:(1) January–June 2009 These energy exchanges happen through two existing interconnections, a 500kv line with Argentina, through
116:
2805:
2306:
1919:
1174:
million of private investment was expected as a result. The first wind farm in Uruguay, the 10 MW Nuevo Manantial project in
2209:
2628:
2481:
2204:
1619:
1870:
1371:
1891:
1452:
2958:
1477:
41:
1391:"Unos 9.000 kilómetros de tendido de electricidad en última década completaron cobertura para 99,85 % de Uruguay"
2916:
2765:
2694:
2422:
2183:
2017:
1366:
156:
138:
49:
2714:
2438:
2375:
2102:
2047:
1063:
338:
324:
274:
197:
1595:"UTE inauguró planta de ciclo combinado Punta del Tigre B, la mayor inversión de una empresa pública en 40 años"
1418:
2412:
2082:
2067:
1933:
816:
electricity has been exported in 2009.The table below shows the evolution of imported electricity since 1999:
2704:
2052:
1339:
1562:
2576:
2491:
2163:
2077:
2057:
2010:
1810:
1781:
2733:
2496:
2348:
2251:
2062:
1303:
475:
467:
1752:
Benchmarking data of the electricity distribution sector in Latin America and Caribbean Region 1995-2005
2870:
2795:
2745:
2581:
2407:
2087:
1977:
1170:. Installed wind power capacity reached 1,000 MW by 2016, generating 17% of the country's electricity.
120:
109:
2633:
2535:
2427:
2417:
2387:
2380:
2353:
479:
2664:
2618:
2545:
2280:
2039:
1047:
595:, accounting for 1,538 MW which includes half of the capacity of the Argentina-Uruguay bi-national
1845:
512:
at times of peak demand. Over the last 10 years, investments in renewable energy sources such as
2785:
2760:
2755:
2750:
2669:
2591:
2571:
2520:
2156:
2780:
2659:
2586:
2370:
2246:
550:
1315:
1311:
2775:
1307:
1137:
600:
545:
501:
2855:
2850:
2845:
2800:
2719:
2525:
2515:
2486:
2471:
2336:
1751:
1198:
8:
2880:
2699:
2623:
2613:
2605:
2566:
2561:
2455:
2256:
2113:
1361:
794:
531:
1269:
average tariff was US$ 0.139/kWh. Average tariffs for some sectors are presented below:
553:
in 2015. Thermal power from biomass also provides additional power generation capacity.
76:
Please help update this article to reflect recent events or newly available information.
2909:
2885:
2820:
2709:
2647:
2540:
2476:
2402:
2365:
2288:
2191:
1356:
2002:
574:
interconnection has improved the ability to import or export electricity with Brazil.
2833:
2828:
2679:
1570:
1511:
1351:
1158:
2932:
2890:
2875:
2865:
2810:
2790:
2397:
2392:
1152:
1000:
665:
596:
592:
535:
521:
229:
2923:
2770:
2432:
2327:
1984:
1948:
1937:
571:
1717:
1062:
Interruption frequency and duration are considerably below the averages for the
2937:
2838:
2674:
2530:
2272:
2225:
1866:
1175:
591:) in 2009 and around 2,900 MW in 2013. Of the installed capacity, about 63% is
558:
520:
allowed the country to cover in early 2016 94.5% of its electricity needs with
248:
240:
2952:
2264:
1574:
1515:
1266:
1067:
539:
218:
1481:
2860:
2230:
1537:"Uruguay makes dramatic shift to nearly 95% electricity from clean energy"
1504:"Uruguay makes dramatic shift to nearly 95% electricity from clean energy"
1298:
emissions from electricity production in 2006 were 1.55 million tons of CO
1867:"La eólica en Uruguay – La UTE licitará la instalación de 150 MW eólicos"
567:
517:
1811:"How Uruguay Became a Wind Power Powerhouse | World Resources Institute"
2358:
2238:
1331:
1316:
partial substitution of fossil fuels with biomass in cement manufacture
1210:. Before, power supply in Montevideo was done by a thermal power plant
1167:
562:
527:
513:
497:
2199:
2301:
1206:
The first large hydroelectric power station was completed in 1945 in
608:
505:
1930:
1257:
installation of large thermal (coal) plants in the South of Brazil.
1136:
Renewables could play a role in future energy supply, in particular
588:
2296:
2148:
1166:
Uruguay has a favorable climate for generating electricity through
1143:
210:
179:
2179:
1972:
1181:
171:
1920:
Luis Giorgi: Las Obras Hidroeléctricas Del Rio Negro, S. 15
1782:"Uruguay has reached 1,000 MW in wind power - www.energynews.es"
262:
612:
587:
Installed electricity capacity in Uruguay was around 2,500 MW (
509:
1077:
437:
National Directorate of Energy and Nuclear Technology (DNTEN)
1563:"What Does Sustainable Living Look Like? Maybe Like Uruguay"
1318:. Total expected emissions reductions are 251,213 tons of CO
1294:(Organización Latinoamericana de Energía) estimated that CO
1990:
1728:
618:
About 56% of generation capacity is owned and operated by
1302:. As of September 2009, there were only three registered
1070:
for LAC were 13 interruptions and 14 hours respectively.
619:
1306:
projects in Uruguay, all of them related to energy: the
1140:, allowing Uruguay to reduce its dependence on imports.
2032:
1291:
196:
1453:"De gestionar los apagones a la revolución energética"
1202:
150 kV power line from Rincón del Bonete to Montevideo
1962:
ESMAP 2007. Strengthening Energy Security in Uruguay.
119:. Please help to ensure that disputed statements are
466:
1978:National Energy and Nuclear Technology Directorate
1713:
1711:
1709:
1610:
1608:
1606:
1604:
1413:
1411:
1733:
1447:
1445:
1338:(PERMER), with a US$ 6.88 million grant from the
1308:Montevideo Landfill Gas Capture and Flare Project
337:Large consumers: 0.047, medium consumers: 0.131 (
244:emissions from electricity generation (2006)
2950:
1683:"Portal UTE - Central Térmica "Punta del Tigre""
1032:
599:. The rest of the production capacity is mostly
577:
427:Unidad Reguladora de Servicios de Energia y Agua
1747:
1745:
1706:
1601:
1408:
1330:The only active energy project financed by the
1739:'World Bank Survey on Investment Climate, 2007
1656:
1442:
471:transactions related to the electricity sector
2164:
2018:
1668:
1666:
1654:
1652:
1650:
1648:
1646:
1644:
1642:
1640:
1638:
1636:
1131:
798:Satellite view of the Salto Grande Reservoir.
570:plants have been built. Additionally, a new
2137:South Georgia and the South Sandwich Islands
1892:"Uruguay to Export Wind Energy to Argentina"
1742:
1312:Fray Bentos Biomass Power Generation Project
1050:conceals a high vulnerability to hydrology.
445:National Directorate of Environment (DINAMA)
50:Learn how and when to remove these messages
2171:
2157:
2025:
2011:
1663:
1633:
1078:Responsibilities in the electricity sector
1038:be about 3.5% during the next ten years.
496:has traditionally been based on domestic
157:Learn how and when to remove this message
139:Learn how and when to remove this message
1808:
1230:
1197:
1157:
1142:
793:
115:Relevant discussion may be found on the
1560:
1397:from the original on September 20, 2019
1286:
1003:, and a 70kv line with Brazil, through
603:and a small share of wind and biomass.
391:Competitive supply to residential users
375:Share of private sector in distribution
367:Share of private sector in transmission
2951:
1832:
1830:
1804:
1802:
1561:Shannon, Noah Gallagher (2022-10-05).
1325:
1217:
1193:
810:
239:
2152:
2006:
1534:
1501:
582:
359:Share of private sector in generation
2178:
1722:
1086:
504:plants, and reliant on imports from
92:
56:
15:
2033:Electricity sector in South America
1827:
1799:
1756:
1535:Watts, Jonathan (3 December 2015).
1459:from the original on August 1, 2020
1431:from the original on August 1, 2020
1372:2019 Argentina and Uruguay blackout
258:Average electricity use (2018)
13:
1997:National Environmental Directorate
1478:"Balance Energético Nacional 2018"
1053:
442:Responsibility for the environment
14:
2975:
1966:
1788:(in European Spanish). 2016-10-21
1367:List of power stations in Uruguay
1243:
1162:Sierra de los Caracoles wind farm
1041:
434:Responsibility for policy-setting
383:Competitive supply to large users
31:This article has multiple issues.
2326:
1991:Electricity Market Administrator
1214:located at the Montevideo port.
234:98% (including large hydropower)
192:Electricity coverage (2019)
178:
97:
61:
20:
2964:Electric power in South America
1942:
1924:
1913:
1902:from the original on 2016-05-18
1884:
1873:from the original on 2009-12-26
1859:
1774:
1765:
1675:
1279:Medium consumers: US$ 0.131/kWh
1028:Public lighting and others: 15%
415:Responsibility for transmission
270:Distribution losses (2007)
39:or discuss these issues on the
1809:Thwaites, Joe (7 March 2016).
1587:
1554:
1528:
1502:Watts, Jonathan (2015-12-03).
1495:
1470:
1383:
1282:Public lighting: US$ 0.164/kWh
1276:Large consumers: US$ 0.047/kWh
538:shared with Argentina, on the
404:
206:Installed capacity (2020)
1:
1840:Asociación Empresarial Eólica
1340:Global Environmental Facility
1033:Demand and supply projections
578:Electricity supply and demand
494:electricity sector of Uruguay
423:Responsibility for regulation
1151:All the potential for large
305:Commercial and public sector
7:
2806:Water supply and sanitation
2252:Treaty of Montevideo (1828)
1345:
1273:Residential: US$ 0.177/kWh
486:annual emissions reductions
201:total average in 2007: 92%)
10:
2980:
1956:
1260:
1188:
1132:Renewable energy resources
1101:Private participation (%)
318:Average residential tariff
2959:Electric power in Uruguay
2903:
2819:
2741:
2732:
2655:
2646:
2604:
2554:
2508:
2467:
2463:
2454:
2344:
2335:
2324:
2281:Revolution of the Lances
2190:
2111:
2038:
1336:Energy Efficiency Project
1109:6% of installed capacity
1010:
827:
824:
779:
758:
719:
682:
635:
465:
457:
449:
441:
433:
422:
414:
403:
398:
390:
382:
374:
366:
358:
350:
345:
332:Average industrial tariff
331:
317:
312:
304:
296:
288:
281:
269:
257:
238:
227:
216:
205:
191:
186:
177:
70:This article needs to be
1377:
1048:installed reserve margin
764:Sierra de los Caracoles
631:Installed capacity (MW)
1616:"MIEM-DNETN Statistics"
1059:service interruptions
341:average in 2005: 0.107)
327:average in 2005: 0.115)
277:average in 2005: 13.6%)
2685:Science and technology
2247:Thirty-Three Orientals
1265:For 2008, the overall
1203:
1163:
1148:
799:
551:electricity generation
450:Electricity sector law
334:(US$ /kW·h, 2008)
320:(US$ /kW·h, 2008)
170:Electricity sector of
1231:Dependence on imports
1212:José Batlle y Ordóñez
1201:
1161:
1146:
797:
313:Tariffs and financing
282:Consumption by sector
2239:Cisplatina province
2205:Spanish colonization
1419:"Memoria anual 2019"
1287:Environmental impact
1147:The Salto Grande Dam
820:Electricity imports
478:projects; 251,213 t
458:Renewable energy law
407:of service providers
108:factual accuracy is
2289:Battle of Masoller
1869:. August 25, 2009.
1484:on October 12, 2020
1362:Politics of Uruguay
1326:External assistance
1218:Power sector reform
1194:Early installations
828:Average power (MW)
821:
811:Imports and exports
174:
2705:Telecommunications
2218:British invasions
1983:2009-08-25 at the
1936:2007-09-28 at the
1896:Wind Power Monthly
1672:UTE en cifras 2008
1567:The New York Times
1357:Economy of Uruguay
1334:in Uruguay is the
1204:
1164:
1149:
819:
800:
583:Installed capacity
169:
2946:
2945:
2899:
2898:
2728:
2727:
2642:
2641:
2600:
2599:
2577:Human trafficking
2497:General Assembly
2492:Foreign relations
2482:Political parties
2450:
2449:
2309:(1973–1985)
2283:(1870–1872)
2275:(1864–1870)
2267:(1864–1865)
2259:(1839–1851)
2241:(1821–1828)
2233:(1815–1820)
2220:(1806–1807)
2212:(1776–1814)
2146:
2145:
2118:other territories
1786:www.energynews.es
1352:Energy in Uruguay
1314:and a project on
1208:Rincón del Bonete
1129:
1128:
1087:Private companies
1068:weighted averages
997:
996:
805:Punta del Tigre B
792:
791:
490:
489:
351:Sector unbundling
195:99.85% (total), (
167:
166:
159:
149:
148:
141:
91:
90:
54:
2971:
2926:
2919:
2912:
2739:
2738:
2653:
2652:
2500:
2465:
2464:
2461:
2460:
2441:
2342:
2341:
2330:
2318:
2310:
2292:
2284:
2276:
2268:
2260:
2242:
2234:
2221:
2213:
2173:
2166:
2159:
2150:
2149:
2138:
2126:Falkland Islands
2040:Sovereign states
2027:
2020:
2013:
2004:
2003:
1951:
1946:
1940:
1928:
1922:
1917:
1911:
1910:
1908:
1907:
1888:
1882:
1881:
1879:
1878:
1863:
1857:
1856:
1854:
1853:
1844:. Archived from
1834:
1825:
1824:
1822:
1821:
1806:
1797:
1796:
1794:
1793:
1778:
1772:
1769:
1763:
1760:
1754:
1749:
1740:
1737:
1731:
1726:
1720:
1715:
1704:
1703:
1701:
1700:
1694:
1688:. Archived from
1687:
1679:
1673:
1670:
1661:
1658:
1631:
1630:
1628:
1627:
1618:. Archived from
1612:
1599:
1598:
1591:
1585:
1584:
1582:
1581:
1558:
1552:
1551:
1549:
1547:
1532:
1526:
1525:
1523:
1522:
1499:
1493:
1492:
1490:
1489:
1480:. Archived from
1474:
1468:
1467:
1465:
1464:
1449:
1440:
1439:
1437:
1436:
1430:
1423:
1415:
1406:
1405:
1403:
1402:
1387:
1095:
1094:
1019:Residential: 41%
822:
818:
625:
624:
536:Salto Grande dam
522:renewable energy
470:
406:
243:
230:renewable energy
200:
182:
175:
168:
162:
155:
144:
137:
133:
130:
124:
121:reliably sourced
101:
100:
93:
86:
83:
77:
65:
64:
57:
46:
24:
23:
16:
2979:
2978:
2974:
2973:
2972:
2970:
2969:
2968:
2949:
2948:
2947:
2942:
2929:
2922:
2915:
2908:
2895:
2815:
2796:Public holidays
2724:
2690:State companies
2638:
2596:
2582:Law enforcement
2550:
2536:Nationality law
2504:
2498:
2446:
2437:
2331:
2322:
2316:
2308:
2290:
2282:
2274:
2273:Paraguayan War
2266:
2258:
2240:
2232:
2219:
2211:
2186:
2177:
2147:
2142:
2136:
2119:
2117:
2107:
2034:
2031:
1985:Wayback Machine
1969:
1959:
1954:
1947:
1943:
1938:Wayback Machine
1929:
1925:
1918:
1914:
1905:
1903:
1890:
1889:
1885:
1876:
1874:
1865:
1864:
1860:
1851:
1849:
1836:
1835:
1828:
1819:
1817:
1807:
1800:
1791:
1789:
1780:
1779:
1775:
1770:
1766:
1761:
1757:
1750:
1743:
1738:
1734:
1727:
1723:
1718:CIER Statistics
1716:
1707:
1698:
1696:
1692:
1685:
1681:
1680:
1676:
1671:
1664:
1659:
1634:
1625:
1623:
1614:
1613:
1602:
1593:
1592:
1588:
1579:
1577:
1559:
1555:
1545:
1543:
1533:
1529:
1520:
1518:
1500:
1496:
1487:
1485:
1476:
1475:
1471:
1462:
1460:
1451:
1450:
1443:
1434:
1432:
1428:
1421:
1417:
1416:
1409:
1400:
1398:
1389:
1388:
1384:
1380:
1348:
1328:
1321:
1301:
1297:
1289:
1263:
1246:
1233:
1220:
1196:
1191:
1134:
1089:
1080:
1056:
1054:Service quality
1044:
1035:
1025:Commercial: 20%
1022:Industrial: 24%
1013:
813:
742:Punta del Tigre
585:
580:
572:electrical grid
483:
333:
319:
283:
252:
163:
152:
151:
150:
145:
134:
128:
125:
114:
106:This article's
102:
98:
87:
81:
78:
75:
66:
62:
25:
21:
12:
11:
5:
2977:
2967:
2966:
2961:
2944:
2943:
2941:
2940:
2935:
2928:
2927:
2920:
2913:
2905:
2904:
2901:
2900:
2897:
2896:
2894:
2893:
2888:
2883:
2878:
2873:
2868:
2863:
2858:
2853:
2848:
2843:
2842:
2841:
2831:
2825:
2823:
2817:
2816:
2814:
2813:
2808:
2803:
2798:
2793:
2788:
2783:
2778:
2773:
2768:
2763:
2758:
2753:
2748:
2742:
2736:
2730:
2729:
2726:
2725:
2723:
2722:
2717:
2712:
2707:
2702:
2697:
2692:
2687:
2682:
2677:
2672:
2667:
2662:
2656:
2650:
2644:
2643:
2640:
2639:
2637:
2636:
2631:
2626:
2621:
2616:
2610:
2608:
2602:
2601:
2598:
2597:
2595:
2594:
2589:
2584:
2579:
2574:
2569:
2564:
2558:
2556:
2552:
2551:
2549:
2548:
2543:
2538:
2533:
2528:
2523:
2518:
2512:
2510:
2506:
2505:
2503:
2502:
2494:
2489:
2484:
2479:
2474:
2468:
2458:
2452:
2451:
2448:
2447:
2445:
2444:
2443:
2442:
2430:
2425:
2423:National parks
2420:
2418:Municipalities
2415:
2410:
2405:
2400:
2395:
2390:
2388:Extreme points
2385:
2384:
2383:
2381:Climate change
2373:
2368:
2363:
2362:
2361:
2351:
2345:
2339:
2333:
2332:
2325:
2323:
2321:
2320:
2312:
2304:
2299:
2294:
2286:
2278:
2270:
2265:Uruguayan War
2262:
2254:
2249:
2244:
2236:
2228:
2226:Banda Oriental
2223:
2215:
2207:
2202:
2200:Charrúa people
2196:
2194:
2188:
2187:
2176:
2175:
2168:
2161:
2153:
2144:
2143:
2141:
2140:
2133:
2128:
2122:
2120:
2112:
2109:
2108:
2106:
2105:
2100:
2095:
2090:
2085:
2080:
2075:
2070:
2065:
2060:
2055:
2050:
2044:
2042:
2036:
2035:
2030:
2029:
2022:
2015:
2007:
2001:
2000:
1994:
1988:
1975:
1968:
1967:External links
1965:
1964:
1963:
1958:
1955:
1953:
1952:
1941:
1923:
1912:
1883:
1858:
1826:
1798:
1773:
1764:
1755:
1741:
1732:
1721:
1705:
1674:
1662:
1632:
1600:
1586:
1553:
1527:
1494:
1469:
1441:
1407:
1381:
1379:
1376:
1375:
1374:
1369:
1364:
1359:
1354:
1347:
1344:
1327:
1324:
1319:
1299:
1295:
1288:
1285:
1284:
1283:
1280:
1277:
1274:
1262:
1259:
1245:
1244:Policy options
1242:
1232:
1229:
1219:
1216:
1195:
1192:
1190:
1187:
1133:
1130:
1127:
1126:
1123:
1119:
1118:
1115:
1111:
1110:
1107:
1103:
1102:
1099:
1088:
1085:
1079:
1076:
1055:
1052:
1043:
1042:Reserve margin
1040:
1034:
1031:
1030:
1029:
1026:
1023:
1020:
1012:
1009:
995:
994:
991:
988:
985:
981:
980:
977:
974:
971:
967:
966:
963:
960:
957:
953:
952:
949:
946:
943:
939:
938:
935:
932:
929:
925:
924:
921:
918:
915:
911:
910:
907:
904:
901:
897:
896:
893:
890:
887:
883:
882:
879:
876:
873:
869:
868:
865:
862:
859:
855:
854:
851:
848:
845:
841:
840:
837:
834:
830:
829:
826:
812:
809:
790:
789:
786:
782:
781:
777:
776:
773:
769:
768:
765:
761:
760:
756:
755:
752:
748:
747:
744:
738:
737:
734:
730:
729:
726:
722:
721:
717:
716:
713:
709:
708:
705:
701:
700:
697:
693:
692:
689:
685:
684:
683:Steam thermal
680:
679:
676:
672:
671:
668:
662:
661:
658:
654:
653:
650:
646:
645:
642:
638:
637:
636:Hydroelectric
633:
632:
629:
584:
581:
579:
576:
559:private sector
488:
487:
481:
472:
463:
462:
459:
455:
454:
451:
447:
446:
443:
439:
438:
435:
431:
430:
424:
420:
419:
416:
412:
411:
408:
401:
400:
396:
395:
392:
388:
387:
384:
380:
379:
376:
372:
371:
368:
364:
363:
360:
356:
355:
352:
348:
347:
343:
342:
335:
329:
328:
321:
315:
314:
310:
309:
306:
302:
301:
298:
294:
293:
290:
286:
285:
279:
278:
271:
267:
266:
259:
255:
254:
250:
245:
236:
235:
232:
225:
224:
221:
214:
213:
207:
203:
202:
193:
189:
188:
184:
183:
165:
164:
147:
146:
105:
103:
96:
89:
88:
69:
67:
60:
55:
29:
28:
26:
19:
9:
6:
4:
3:
2:
2976:
2965:
2962:
2960:
2957:
2956:
2954:
2939:
2936:
2934:
2931:
2930:
2925:
2921:
2918:
2914:
2911:
2907:
2906:
2902:
2892:
2889:
2887:
2884:
2882:
2879:
2877:
2874:
2872:
2869:
2867:
2864:
2862:
2859:
2857:
2854:
2852:
2849:
2847:
2844:
2840:
2837:
2836:
2835:
2832:
2830:
2827:
2826:
2824:
2822:
2818:
2812:
2809:
2807:
2804:
2802:
2799:
2797:
2794:
2792:
2789:
2787:
2784:
2782:
2779:
2777:
2774:
2772:
2769:
2767:
2766:Ethnic groups
2764:
2762:
2759:
2757:
2754:
2752:
2749:
2747:
2744:
2743:
2740:
2737:
2735:
2731:
2721:
2718:
2716:
2713:
2711:
2708:
2706:
2703:
2701:
2698:
2696:
2695:Stockbreeding
2693:
2691:
2688:
2686:
2683:
2681:
2678:
2676:
2673:
2671:
2668:
2666:
2663:
2661:
2658:
2657:
2654:
2651:
2649:
2645:
2635:
2632:
2630:
2627:
2625:
2622:
2620:
2617:
2615:
2612:
2611:
2609:
2607:
2603:
2593:
2590:
2588:
2585:
2583:
2580:
2578:
2575:
2573:
2570:
2568:
2565:
2563:
2560:
2559:
2557:
2553:
2547:
2546:Supreme Court
2544:
2542:
2539:
2537:
2534:
2532:
2529:
2527:
2524:
2522:
2519:
2517:
2514:
2513:
2511:
2507:
2501:
2495:
2493:
2490:
2488:
2485:
2483:
2480:
2478:
2475:
2473:
2470:
2469:
2466:
2462:
2459:
2457:
2453:
2440:
2436:
2435:
2434:
2431:
2429:
2426:
2424:
2421:
2419:
2416:
2414:
2411:
2409:
2406:
2404:
2401:
2399:
2396:
2394:
2391:
2389:
2386:
2382:
2379:
2378:
2377:
2374:
2372:
2369:
2367:
2364:
2360:
2357:
2356:
2355:
2352:
2350:
2347:
2346:
2343:
2340:
2338:
2334:
2329:
2319:
2313:
2311:
2307:Dictatorship
2305:
2303:
2300:
2298:
2295:
2293:
2287:
2285:
2279:
2277:
2271:
2269:
2263:
2261:
2255:
2253:
2250:
2248:
2245:
2243:
2237:
2235:
2231:Liga Federal
2229:
2227:
2224:
2222:
2216:
2214:
2208:
2206:
2203:
2201:
2198:
2197:
2195:
2193:
2189:
2185:
2181:
2174:
2169:
2167:
2162:
2160:
2155:
2154:
2151:
2139:
2134:
2132:
2131:French Guiana
2129:
2127:
2124:
2123:
2121:
2115:
2110:
2104:
2101:
2099:
2096:
2094:
2091:
2089:
2086:
2084:
2081:
2079:
2076:
2074:
2071:
2069:
2066:
2064:
2061:
2059:
2056:
2054:
2051:
2049:
2046:
2045:
2043:
2041:
2037:
2028:
2023:
2021:
2016:
2014:
2009:
2008:
2005:
1998:
1995:
1992:
1989:
1986:
1982:
1979:
1976:
1974:
1971:
1970:
1961:
1960:
1950:
1945:
1939:
1935:
1932:
1927:
1921:
1916:
1901:
1897:
1893:
1887:
1872:
1868:
1862:
1848:on 2009-12-16
1847:
1843:
1841:
1833:
1831:
1816:
1812:
1805:
1803:
1787:
1783:
1777:
1768:
1759:
1753:
1748:
1746:
1736:
1730:
1725:
1719:
1714:
1712:
1710:
1695:on 2015-05-09
1691:
1684:
1678:
1669:
1667:
1657:
1655:
1653:
1651:
1649:
1647:
1645:
1643:
1641:
1639:
1637:
1622:on 2011-10-09
1621:
1617:
1611:
1609:
1607:
1605:
1596:
1590:
1576:
1572:
1568:
1564:
1557:
1542:
1538:
1531:
1517:
1513:
1509:
1505:
1498:
1483:
1479:
1473:
1458:
1454:
1448:
1446:
1427:
1420:
1414:
1412:
1396:
1392:
1386:
1382:
1373:
1370:
1368:
1365:
1363:
1360:
1358:
1355:
1353:
1350:
1349:
1343:
1341:
1337:
1333:
1323:
1317:
1313:
1309:
1305:
1293:
1281:
1278:
1275:
1272:
1271:
1270:
1268:
1258:
1254:
1250:
1241:
1237:
1228:
1224:
1215:
1213:
1209:
1200:
1186:
1183:
1179:
1177:
1171:
1169:
1160:
1156:
1154:
1153:hydroelectric
1145:
1141:
1139:
1124:
1122:Distribution
1121:
1120:
1116:
1114:Transmission
1113:
1112:
1108:
1105:
1104:
1100:
1097:
1096:
1093:
1084:
1075:
1071:
1069:
1065:
1060:
1051:
1049:
1039:
1027:
1024:
1021:
1018:
1017:
1016:
1008:
1006:
1002:
992:
989:
986:
983:
982:
978:
975:
972:
969:
968:
964:
961:
958:
955:
954:
950:
947:
944:
941:
940:
936:
933:
930:
927:
926:
922:
919:
916:
913:
912:
908:
905:
902:
899:
898:
894:
891:
888:
885:
884:
880:
877:
874:
871:
870:
866:
863:
860:
857:
856:
852:
849:
846:
843:
842:
838:
835:
832:
831:
823:
817:
808:
806:
796:
787:
784:
783:
778:
774:
771:
770:
766:
763:
762:
757:
753:
750:
749:
745:
743:
740:
739:
735:
732:
731:
727:
724:
723:
720:Gas turbines
718:
714:
711:
710:
706:
703:
702:
698:
695:
694:
690:
687:
686:
681:
677:
674:
673:
669:
667:
664:
663:
659:
657:Constitución
656:
655:
651:
648:
647:
643:
640:
639:
634:
630:
627:
626:
623:
621:
616:
614:
610:
604:
602:
598:
594:
590:
575:
573:
569:
564:
560:
554:
552:
547:
546:Thermal power
543:
541:
540:Uruguay River
537:
534:and one, the
533:
529:
525:
523:
519:
515:
511:
507:
503:
502:thermal power
499:
495:
485:
477:
474:3 registered
473:
469:
464:
460:
456:
452:
448:
444:
440:
436:
432:
428:
425:
421:
417:
413:
409:
402:
397:
393:
389:
385:
381:
377:
373:
369:
365:
361:
357:
353:
349:
344:
340:
336:
330:
326:
322:
316:
311:
307:
303:
299:
295:
291:
287:
280:
276:
272:
268:
264:
260:
256:
253:
246:
242:
237:
233:
231:
226:
222:
220:
219:fossil energy
215:
212:
208:
204:
199:
194:
190:
185:
181:
176:
173:
161:
158:
143:
140:
132:
122:
118:
112:
111:
104:
95:
94:
85:
73:
68:
59:
58:
53:
51:
44:
43:
38:
37:
32:
27:
18:
17:
2924:Bibliography
2756:Demographics
2751:Coat of arms
2715:Trade unions
2670:Central Bank
2592:Prostitution
2572:Human rights
2567:Cannabis use
2555:Legal issues
2521:Constitution
2509:Legal system
2499:(parliament)
2210:Viceroyalty
2114:Dependencies
2097:
1944:
1926:
1915:
1904:. Retrieved
1895:
1886:
1875:. Retrieved
1861:
1850:. Retrieved
1846:the original
1839:
1818:. Retrieved
1814:
1790:. Retrieved
1785:
1776:
1767:
1758:
1735:
1724:
1697:. Retrieved
1690:the original
1677:
1624:. Retrieved
1620:the original
1589:
1578:. Retrieved
1566:
1556:
1544:. Retrieved
1541:the Guardian
1540:
1530:
1519:. Retrieved
1508:The Guardian
1507:
1497:
1486:. Retrieved
1482:the original
1472:
1461:. Retrieved
1433:. Retrieved
1399:. Retrieved
1385:
1329:
1322:e per year.
1290:
1264:
1255:
1251:
1247:
1238:
1234:
1225:
1221:
1211:
1205:
1180:
1172:
1165:
1150:
1135:
1090:
1081:
1072:
1061:
1057:
1045:
1036:
1014:
1001:Salto Grande
998:
814:
801:
688:3rd and 4th
666:Salto Grande
617:
605:
597:Salto Grande
586:
555:
544:
526:
493:
491:
426:
399:Institutions
284:(% of total)
153:
135:
126:
107:
79:
71:
47:
40:
34:
33:Please help
30:
2781:Immigration
2660:Agriculture
2587:LGBT rights
2413:Lighthouses
2376:Environment
2371:Departments
2315:Expiry Law
1815:www.wri.org
1106:Generation
609:Argentinian
568:solar power
518:solar power
500:along with
289:Residential
265:per capita
247:1.55 Mt of
82:August 2020
2953:Categories
2856:Literature
2776:Healthcare
2761:Emigration
2516:Civil Code
2359:Montevideo
2257:Civil War
1906:2021-12-16
1877:2021-12-16
1852:2009-09-24
1820:2017-10-03
1792:2017-10-03
1771:World Bank
1699:2021-12-16
1660:ESMAP 2007
1626:2009-09-24
1580:2022-10-06
1546:20 January
1521:2016-04-12
1488:2021-12-16
1463:2021-12-16
1435:2021-12-16
1401:2021-12-16
1332:World Bank
1168:wind power
1138:wind power
993:1,170,861
951:2,832,392
945:2,023,753
937:1,585,209
923:2,347,917
917:1,934,774
867:1,328,077
861:1,328,015
833:Argentina
649:Baygorria
563:Wind power
528:Hydropower
514:wind power
498:hydropower
453:Yes (1997)
297:Industrial
129:April 2016
36:improve it
2851:Languages
2846:Education
2801:Squatting
2720:Transport
2624:Air Force
2526:Judiciary
2487:Elections
2472:President
2337:Geography
2302:Tupamaros
2103:Venezuela
2048:Argentina
1575:0362-4331
1516:0261-3077
1098:Activity
984:2009 (1)
615:markets.
613:Brazilian
589:megawatts
532:Rio Negro
524:sources.
506:Argentina
228:Share of
217:Share of
117:talk page
42:talk page
2933:Category
2881:Religion
2700:Taxation
2675:Currency
2606:Military
2562:Abortion
2541:Passport
2456:Politics
2297:Batllism
2184:articles
2093:Suriname
2083:Paraguay
2068:Colombia
1999:(DINAMA)
1981:Archived
1934:Archived
1900:Archived
1871:Archived
1457:Archived
1426:Archived
1395:Archived
1346:See also
1267:weighted
990:433,249
987:737,613
979:961,442
976:128,794
973:832,648
965:788,589
962:214,960
959:573,629
948:808,638
934:750,346
931:834,863
920:413,143
909:434,228
903:433,913
895:559,111
889:558,958
881:122,692
875:116,815
853:707,701
847:707,640
346:Services
323:0.177; (
110:disputed
2910:Outline
2886:Smoking
2871:Museums
2834:Cuisine
2821:Culture
2734:Society
2710:Tourism
2665:Banking
2648:Economy
2629:History
2477:Cabinet
2408:Islands
2403:Geology
2366:Climate
2349:Borders
2192:History
2180:Uruguay
2098:Uruguay
2073:Ecuador
2053:Bolivia
1987:(DNTEN)
1957:Sources
1261:Tariffs
1189:History
1182:Biomass
836:Brazil
780:Diesel
601:thermal
429:(URSEA)
410:1 (UTE)
172:Uruguay
72:updated
2938:Portal
2829:Cinema
2791:People
2746:Anthem
2680:Energy
2428:Rivers
2354:Cities
2317:(1986)
2291:(1904)
2182:
2078:Guyana
2058:Brazil
1993:(ADME)
1949:UNFCCC
1573:
1514:
1310:, the
1011:Demand
1005:Garabi
878:5,877
839:Total
785:Total
772:Total
751:Total
712:Total
678:2,491
675:Total
641:Terra
628:Plant
510:Brazil
273:18%; (
261:3,275
2917:Index
2891:Sport
2876:Music
2866:Media
2811:Women
2634:Ranks
2398:Flora
2393:Fauna
2063:Chile
1931:OLADE
1693:(PDF)
1686:(PDF)
1429:(PDF)
1422:(PDF)
1378:Notes
1292:OLADE
1176:Rocha
970:2008
956:2007
942:2006
928:2005
914:2004
900:2003
886:2002
872:2001
858:2000
844:1999
825:Year
759:Wind
670:1890
593:hydro
2861:Mate
2839:Wine
2786:LGBT
2771:Flag
2619:Navy
2614:Army
2433:Time
2088:Peru
1729:ADME
1571:ISSN
1548:2018
1512:ISSN
906:315
892:153
754:532
746:300
736:212
733:CTR
715:255
707:125
704:6th
696:5th
660:333
652:108
644:160
611:and
516:and
508:and
492:The
263:kW·h
209:4.6
187:Data
2531:Law
2439:DST
2116:and
1973:UTE
1762:UTE
1304:CDM
1125:0%
1117:0%
1064:LAC
864:62
850:61
775:10
767:10
728:20
725:AA
699:80
691:50
620:UTE
476:CDM
468:CDM
418:UTE
405:No.
339:LAC
325:LAC
308:35%
300:24%
292:41%
275:LAC
241:GHG
198:LAC
2955::
1898:.
1894:.
1829:^
1813:.
1801:^
1784:.
1744:^
1708:^
1665:^
1635:^
1603:^
1569:.
1565:.
1539:.
1510:.
1506:.
1455:.
1444:^
1424:.
1410:^
1393:.
1007:.
788:2
480:CO
461:No
394:No
386:No
378:0%
370:0%
362:6%
354:No
249:CO
223:2%
211:GW
45:.
2172:e
2165:t
2158:v
2026:e
2019:t
2012:v
1909:.
1880:.
1855:.
1842:"
1838:"
1823:.
1795:.
1702:.
1629:.
1597:.
1583:.
1550:.
1524:.
1491:.
1466:.
1438:.
1404:.
1320:2
1300:2
1296:2
803:"
484:e
482:2
251:2
160:)
154:(
142:)
136:(
131:)
127:(
123:.
113:.
84:)
80:(
74:.
52:)
48:(
Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.