Knowledge

Mont d'Ambin Base Tunnel

Source đź“ť

416: 403: 36: 1044: 372:. The 11.25 m (36 ft 11 in) diameter hard rock single shield TBM started its journey in the summer of 2016 from the Saint-Martin-de-la-Porte access adit and managed to maintain an average speed of 15–20 m (49 ft 3 in â€“ 65 ft 7 in)/day. This first €390 million lot of the base tunnel was constructed by a joint venture of Batignolles TPCI, Eiffage TP, 345:, which has stated its intention to finance 40% of the tunnel construction costs, and has indicated its willingness to increase its contribution to 55%, as well as to help fund its French accesses if those go beyond mere adaptations of the existing infrastructure. In January 2017, a treaty was ratified between the two countries, confirming the project's approval. 337:
during 2003, and at La Praz two years later. During 2011, excavations in support of the survey work started on the Italian side at La Maddalena. Between 2016 and 2017, while full-rate construction of the tunnel had not officially commenced, a 9 km (5.6 mi) reconnaissance gallery had been
316:
8 billion. During September 2016, a key agreement towards the tunnel's construction was reached by France and Italy. Three years later, competitive tenders to perform packaged elements of the construction work were sought. As of late-2022, the expected completion date for the base tunnel was 2032.
497:
The tunnel will be used by both freight trains and freight shuttles running at 100 km/h (62 mph), as well and by higher speed passenger trains operating at 220 km/h (140 mph); this design speed of slightly below the 250 km/h (160 mph) threshold used by the European
356:
had been awarded a contract for the construction of several major elements of tunnel, including four Avrieux shafts of up to 500 m (1,640 ft 5 in) depth, and the conventional excavation of multiple galleries and seven caverns at the foot of the Villarodin Bourget–Modane decline.
434:
movement. As a result of protests against the original alignment of the tunnel in the Susa valley, it was decided to increase its length from 52 to 57.5 km (32.3 to 35.7 mi). Upon opening, the tunnel will be the longest rail tunnel in the world, followed by the
352:(RFP) for the construction of the French portion of the base tunnel; in July 2019, a second RFP was released for the Italian portion of the tunnel. During July 2020, it was announced that a consortium headed by the French civil engineering firm 281:. Once completed, it will facilitate the principal high-speed rail link between Italy and France, conveying both high-speed passenger trains and rail freight between the two countries. At 57.5 kilometres (35.7 mi), that tunnel will be the 485:
The cost of the joint Franco-Italian section (from Saint Jean de Maurienne to Val Susa) has been estimated at 8 billion euros (in January 2018 value). This cost will be borne by the French and Italian governments, as well as drawing upon
338:
tunneled from Saint Martin de la Porte towards Italy; it was bored along the intended axis of the South tube of the tunnel and was driven at its final diameter. It will comprise the first eight percent of the tunnel's final length.
490:(EU) funds. The EU has agreed to provide 40% of the financing, but has indicated its willingness to increase its contribution to 55%, as well as to conditionally partially fund its French accesses. However, a 2012 report by the 394:
The approach routes are less advanced; planning is under way on the French side, but on the Italian side the proposed route has had fierce controversy, particularly in the Susa Valley the location of the Eastern portal, with a
389:
Lot 3 (€228 million) for 3 km (1.9 mi) between Saint-Martin-de-la-Porte and the Western (French) Portal at Saint-Julien-Mont-Denis; the shortest, but with difficult geology requiring all blasting; expected to take 70
360:
All four of the access tunnels, three in France and one in Italy, have been completed and work began in early 2019 on the artificial tunnel that will be the entrance to the base tunnel on the French side.
813: 341:
During September 2016, it was announced that France and Italy had reached a mutual agreement for the construction of the tunnel. Furthermore, the tunnel has been approved and part-financed by the
795: 999: 739: 399:(no to high-speed rail) movement. The 2016 approval legislation could require extension of the tunnel by 5 km (3.1 mi) to reduce the impact on the local landscape. 974: 1026:"Decision No 661/2010/EU of the European Parliament and of the Council of 7 July 2010 on Union guidelines for the development of the trans-European transport network" 917: 1065: 502:. A stated aim of the project is a modal shift from road to rail for freight traffic over the Alps, as well as more passengers travelling by train rather than 368:(TBMs) to be used on the project finished excavation of the first 9 km (5.6 mi) of the southern tube of the base tunnel, reaching the La Praz access 862: 717: 764: 383:
Lot 1 (€1.47 billion) for 22 km (13.7 mi) between Villarodin-Bourget/Modane and the Eastern (Italian) portal; expected to take 72 months
1048: 1119: 1003: 1129: 982: 386:
Lot 2 (€1.43 billion) for 23 km (14.3 mi) between Saint-Martin-de-la-Porte/La Praz and Modane; expected to take 65 months
643: 580: 427:. During 2019, it was stated that the tunnel's construction phase had been projected to take approximately ten years to complete. 876: 902: 289:. It represents one third of the estimated overall cost of the project and is the only part of the line where work has started. 960: 942: 687: 555: 1104: 1025: 1109: 529: 424: 278: 62: 612:"The European Commission welcomes the agreement between France and Italy to move ahead with the Lyon-Turin project" 1000:"Situation et perspectives des finances publiques 2012 / Publications / Publications / Accueil - Cour des comptes" 611: 781: 1114: 978: 673: 669: 1134: 470:
side. The geology adjacent to the French portal is heavily composed of fractured and sheared coal-bearing
995: 494:
questioned the reliability of the estimated costs of the tunnel, as well the projected traffic volumes.
814:"Ligne ferroviaire Lyon-Turin : malgrĂ© les tensions, Rome valide le lancement des appels d'offres" 491: 334: 740:"Telt annonce le percement de la section du tunnel de base entre Saint-Martin-la-Porte et La Praz" 459: 282: 209: 718:"Manuel Valls inaugure le tunnelier Federica au chantier du Lyon-Turin Ă  Saint-Martin-La-Porte" 691: 519: 161: 918:"What is happening with the Lyon Turin high-speed line? Euronews traces the route to find out" 1124: 479: 475: 406:
Profile of Mont d'Ambin Base Tunnel (sections excavated in blue, sections in progress in red)
365: 835: 22: 436: 349: 286: 214: 629: 423:
The Mont d'Ambin Base Tunnel is the principal engineering challenge of the in-development
8: 440: 647: 584: 499: 796:"L'accord franco-italien pour la ligne ferroviaire Lyon-Turin définitivement adopté" 534: 402: 373: 415: 695: 452: 258: 115: 487: 463: 448: 342: 201: 863:"Vinci consortium wins contract for preparatory work for Lyon–Turin rail line" 1098: 1080: 1067: 444: 119: 430:
Opposition to the project is mostly organised under the loose banner of the
166: 297: 173: 83: 765:"L'Union europĂ©enne confirme une participation accrue sur le Lyon-Turin" 376:, CMC, Cogeis and Sotrabas. Egis and Alpina provided project management 961:"Covid-19 : retour Ă  la normalitĂ© sur les chantiers du Lyon-Turin" 836:"Lyon-Turin : les avis de marchĂ© publiĂ©s pour le tronçon italien" 482:
has to be used for the corresponding 5 km (3.1 mi) section.
379:
Contracts for the Mount Cenis Base Tunnel were awarded in July 2021:
305: 145: 72: 503: 353: 301: 782:"Lyon-Turin : vers les 55 % de contribution europĂ©enne" 474:, as revealed by test drilling, which is poorly suited for using 16:
Railway tunnel through the Cottian Alps between France and Italy
1043: 471: 330: 326: 309: 35: 630:"TELT Lyon Turin • A new excavation front for the Lyon-Turin" 467: 443:(55 km (34 mi), currently under construction), the 1054: 524: 369: 313: 293: 149: 348:
During March 2019, the Italian government issued a formal
419:
Geothermal profile of new Turin-Lyon railway base tunnel
556:"After Earning World Record, Alpine Tunnels Move Ahead" 903:"Les travaux du Lyon-Turin dĂ©butent le 15 janvier" 857: 855: 853: 802:(in French). 26 January 2017 – via Le Monde. 325:During 2002, reconnaissance work commenced on the 329:side. Initially, access points were excavated at 1096: 915: 850: 455:in South Korea (50.3 km (31.3 mi)). 447:in Japan (53.85 km (33.46 mi)), the 865:. worldconstructionnetwork.com. 13 July 2020. 895: 892:, October 2021 (Volume 177 No 10), pp. 40–43 877:"Lyon-Turin begins base line tender process" 869: 788: 616:Mobility and Transport - European Commission 943:"Progressing the Lyon-Turin base rail link" 732: 285:, ahead of the 57.1 km (35.5 mi) 935: 606: 604: 602: 34: 916:Montalto Monella, Lillo (26 March 2019). 776: 774: 759: 757: 506:, both of which achieve a reduction in CO 451:(50.45 km (31.35 mi)), and the 277:, is the largest engineering work of the 975:"Brenner base tunnel wins TEN-T funding" 414: 401: 599: 1097: 771: 754: 364:In September 2019, the first of eight 953: 909: 553: 816:(in French). Le Monde. 11 March 2019 710: 636: 573: 439:(57.1 km (35.5 mi)), the 13: 1120:Proposed railway tunnels in Europe 1055:Lyon-Turin rail link official site 410: 14: 1146: 1058:(in Italian, French, and English) 1036: 981:. 11 January 2008. Archived from 354:Vinci Construction Grands Projets 1042: 283:longest rail tunnel in the world 1018: 989: 967: 883: 828: 806: 694:. 10 April 2016. Archived from 680: 662: 622: 547: 458:The tunnel portals will be in 312:. It has an estimated cost of 157: 1: 1130:France–Italy border crossings 979:Railway Gazette International 890:Railway Gazette International 674:Railway Gazette International 554:Reina, Peter (16 June 2016). 540: 530:Turin–Lyon high-speed railway 425:Turin–Lyon high-speed railway 63:Turin–Lyon high-speed railway 879:. Tunneltalk. 19 March 2020. 279:Lyon–Turin rail link project 234:220 km/h (140 mph) 7: 513: 333:; excavations commenced in 242:100 km/h (62 mph) 40:Cross-section of the tunnel 10: 1151: 320: 253:580 metres (1,900 ft) 20: 1105:Railway tunnels in France 257: 249: 222: 208: 172: 156: 140: 135: 125: 111: 103: 95: 90: 79: 68: 58: 50: 45: 33: 1110:Railway tunnels in Italy 1049:Mont d'Ambin Base Tunnel 688:"Decouvrez la Maddalena" 335:Saint-Martin-de-la-Porte 271:Mont d'Ambin Base Tunnel 218:25 kV 50 Hz AC 29:Mont d'Ambin Base Tunnel 21:Not to be confused with 560:Engineering News-Record 462:on the French side and 460:Saint-Jean-de-Maurienne 263:8.4 metres (28 ft) 1081:45.190748°N 6.781311°E 692:Lyon Turin Ferroviaire 520:Lyon Turin Ferroviaire 476:tunnel boring machines 420: 407: 366:tunnel boring machines 275:Mont Cenis Base Tunnel 1115:Transport in Piedmont 646:. LTF. Archived from 583:. LTF. Archived from 498:Commission to define 492:French Court of Audit 480:drilling and blasting 478:; thus, conventional 418: 405: 350:request for proposals 131:Passenger and freight 1051:at Wikimedia Commons 618:. 22 September 2016. 581:"The Alpine tunnels" 437:Gotthard Base Tunnel 287:Gotthard Base Tunnel 273:, also known as the 1135:Tunnels in the Alps 1086:45.190748; 6.781311 1077: /  905:. 18 December 2018. 650:on 22 February 2012 644:"Close-up on works" 500:high-speed railways 441:Brenner Base Tunnel 30: 963:. TELT Lyon-Turin. 947:www.tunneltalk.com 587:on 31 October 2006 421: 408: 54:Under construction 28: 23:FrĂ©jus Rail Tunnel 1047:Media related to 670:"Boring contract" 267: 266: 250:Highest elevation 1142: 1092: 1091: 1089: 1088: 1087: 1082: 1078: 1075: 1074: 1073: 1070: 1059: 1046: 1030: 1029: 1022: 1016: 1015: 1013: 1011: 1002:. Archived from 993: 987: 986: 971: 965: 964: 957: 951: 950: 939: 933: 932: 930: 928: 913: 907: 906: 899: 893: 887: 881: 880: 873: 867: 866: 859: 848: 847: 845: 843: 832: 826: 825: 823: 821: 810: 804: 803: 792: 786: 785: 778: 769: 768: 761: 752: 751: 749: 747: 736: 730: 729: 727: 725: 720:(in French). LTF 714: 708: 707: 705: 703: 698:on 25 April 2016 684: 678: 677: 666: 660: 659: 657: 655: 640: 634: 633: 626: 620: 619: 608: 597: 596: 594: 592: 577: 571: 570: 568: 566: 551: 535:Lists of tunnels 259:Tunnel clearance 204: 198: 196: 195: 191: 188: 180: 159: 116:passenger trains 38: 31: 27: 1150: 1149: 1145: 1144: 1143: 1141: 1140: 1139: 1095: 1094: 1085: 1083: 1079: 1076: 1071: 1068: 1066: 1064: 1063: 1057: 1039: 1034: 1033: 1024: 1023: 1019: 1009: 1007: 998: 994: 990: 985:on 31 May 2012. 973: 972: 968: 959: 958: 954: 941: 940: 936: 926: 924: 914: 910: 901: 900: 896: 888: 884: 875: 874: 870: 861: 860: 851: 841: 839: 834: 833: 829: 819: 817: 812: 811: 807: 794: 793: 789: 780: 779: 772: 763: 762: 755: 745: 743: 738: 737: 733: 723: 721: 716: 715: 711: 701: 699: 686: 685: 681: 676:. 1 March 2005. 668: 667: 663: 653: 651: 642: 641: 637: 628: 627: 623: 610: 609: 600: 590: 588: 579: 578: 574: 564: 562: 552: 548: 543: 516: 509: 453:Yulhyeon Tunnel 413: 411:Characteristics 323: 245: 223:Operating speed 217: 200: 193: 189: 186: 184: 183:4 ft  182: 178: 130: 41: 26: 17: 12: 11: 5: 1148: 1138: 1137: 1132: 1127: 1122: 1117: 1112: 1107: 1061: 1060: 1052: 1038: 1037:External links 1035: 1032: 1031: 1017: 1006:on 8 July 2012 988: 966: 952: 934: 908: 894: 882: 868: 849: 827: 805: 787: 770: 753: 731: 709: 679: 661: 635: 621: 598: 572: 545: 544: 542: 539: 538: 537: 532: 527: 522: 515: 512: 507: 488:European Union 449:Channel Tunnel 412: 409: 392: 391: 387: 384: 343:European Union 322: 319: 265: 264: 261: 255: 254: 251: 247: 246: 244: 243: 240: 235: 232: 226: 224: 220: 219: 212: 206: 205: 202:standard gauge 176: 170: 169: 164: 154: 153: 142: 138: 137: 133: 132: 127: 123: 122: 120:freight trains 113: 109: 108: 105: 101: 100: 97: 93: 92: 88: 87: 81: 77: 76: 70: 66: 65: 60: 56: 55: 52: 48: 47: 43: 42: 39: 15: 9: 6: 4: 3: 2: 1147: 1136: 1133: 1131: 1128: 1126: 1123: 1121: 1118: 1116: 1113: 1111: 1108: 1106: 1103: 1102: 1100: 1093: 1090: 1056: 1053: 1050: 1045: 1041: 1040: 1027: 1021: 1005: 1001: 996: 992: 984: 980: 976: 970: 962: 956: 948: 944: 938: 923: 919: 912: 904: 898: 891: 886: 878: 872: 864: 858: 856: 854: 837: 831: 815: 809: 801: 797: 791: 783: 777: 775: 766: 760: 758: 741: 735: 719: 713: 697: 693: 690:(in French). 689: 683: 675: 671: 665: 649: 645: 639: 631: 625: 617: 613: 607: 605: 603: 586: 582: 576: 561: 557: 550: 546: 536: 533: 531: 528: 526: 523: 521: 518: 517: 511: 505: 501: 495: 493: 489: 483: 481: 477: 473: 469: 465: 461: 456: 454: 450: 446: 445:Seikan Tunnel 442: 438: 433: 428: 426: 417: 404: 400: 398: 388: 385: 382: 381: 380: 377: 375: 371: 367: 362: 358: 355: 351: 346: 344: 339: 336: 332: 328: 318: 315: 311: 307: 303: 299: 295: 292:Crossing the 290: 288: 284: 280: 276: 272: 262: 260: 256: 252: 248: 241: 239: 236: 233: 231: 228: 227: 225: 221: 216: 213: 211: 207: 203: 179:1,435 mm 177: 175: 171: 168: 165: 163: 155: 151: 147: 143: 139: 134: 128: 124: 121: 117: 114: 110: 106: 102: 98: 94: 89: 85: 82: 78: 74: 71: 67: 64: 61: 57: 53: 49: 44: 37: 32: 24: 19: 1125:Base tunnels 1062: 1020: 1008:. Retrieved 1004:the original 991: 983:the original 969: 955: 946: 937: 925:. Retrieved 921: 911: 897: 889: 885: 871: 840:. Retrieved 830: 818:. Retrieved 808: 799: 790: 784:(in French). 767:(in French). 746:18 September 744:. Retrieved 734: 722:. Retrieved 712: 700:. Retrieved 696:the original 682: 664: 652:. Retrieved 648:the original 638: 624: 615: 589:. Retrieved 585:the original 575: 563:. Retrieved 559: 549: 496: 484: 457: 431: 429: 422: 396: 393: 378: 363: 359: 347: 340: 324: 296:between the 291: 274: 270: 268: 237: 229: 167:Double track 107:2019–present 18: 1084: / 838:(in French) 800:Le Monde.fr 742:(in French) 510:emissions. 298:Susa Valley 215:Electrified 210:Electrified 174:Track gauge 148:(35.7  104:Constructed 84:Susa Valley 1099:Categories 1069:45°11′27″N 541:References 230:Passenger: 144:57.5  96:Work begun 1072:6°46′53″E 1010:22 August 504:airliners 306:Maurienne 136:Technical 129:Twin tube 126:Character 91:Operation 73:Maurienne 922:Euronews 724:1 August 702:10 April 514:See also 302:Piedmont 238:Freight: 197: in 75:, France 46:Overview 842:18 July 820:18 July 654:2 March 591:2 March 565:20 June 472:schists 468:Italian 466:on the 321:History 192:⁄ 112:Traffic 86:, Italy 432:No TAV 397:No TAV 390:months 374:Ghella 331:Modane 327:French 310:Savoie 162:tracks 141:Length 59:System 51:Status 927:2 May 69:Start 1012:2012 929:2019 844:2019 822:2019 748:2019 726:2016 704:2016 656:2012 593:2012 567:2016 525:NRLA 464:Susa 370:adit 304:and 294:Alps 269:The 118:and 99:2002 308:in 300:in 160:of 158:No. 80:End 1101:: 997:, 977:. 945:. 920:. 852:^ 798:. 773:^ 756:^ 672:. 614:. 601:^ 558:. 199:) 150:mi 146:km 1028:. 1014:. 949:. 931:. 846:. 824:. 750:. 728:. 706:. 658:. 632:. 595:. 569:. 508:2 314:€ 194:2 190:1 187:+ 185:8 181:( 152:) 25:.

Index

Fréjus Rail Tunnel

Turin–Lyon high-speed railway
Maurienne
Susa Valley
passenger trains
freight trains
km
mi
tracks
Double track
Track gauge
standard gauge
Electrified
Electrified
Tunnel clearance
Lyon–Turin rail link project
longest rail tunnel in the world
Gotthard Base Tunnel
Alps
Susa Valley
Piedmont
Maurienne
Savoie
€
French
Modane
Saint-Martin-de-la-Porte
European Union
request for proposals

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.

↑