Knowledge

Prestressed concrete

Source 📝

1354: 937: 1338: 352: 971: 953: 1290: 403: 918: 1047: 491: 252: 195: 480: 317: 1306: 1009: 325: 1258: 1274: 340:
concrete has been cast and set, the tendons are tensioned ("stressed") by pulling the tendon ends through the anchorages while pressing against the concrete. The large forces required to tension the tendons result in a significant permanent compression being applied to the concrete once the tendon is "locked-off" at the anchorage. The method of locking the tendon-ends to the anchorage is dependent upon the tendon composition, with the most common systems being "button-head" anchoring (for wire tendons),
1226: 990: 1176:
stresses generated by in-service loading. This crack-resistance also allows individual slab sections to be constructed in larger pours than for conventionally reinforced concrete, resulting in wider joint spacings, reduced jointing costs and less long-term joint maintenance issues. Initial works have also been successfully conducted on the use of precast prestressed concrete for road pavements, where the speed and quality of the construction has been noted as being beneficial for this technique.
20: 1242: 222: 1028: 4514: 1322: 1066: 1370: 809:, 2018. The Ponte Morandi was a cable-stayed bridge characterised by a prestressed concrete structure for the piers, pylons and deck, very few stays, as few as two per span, and a hybrid system for the stays constructed from steel cables with prestressed concrete shells poured on. The concrete was only prestressed to 10 MPa, resulting in it being prone to cracks and water intrusion, which caused corrosion of the embedded steel. 244:) achievable between the freshly set concrete and the surface of the tendons is critical to the pre-tensioning process, as it determines when the tendon anchorages can be safely released. Higher bond strength in early-age concrete will speed production and allow more economical fabrication. To promote this, pre-tensioned tendons are usually composed of isolated single wires or strands, which provides a greater 1141:
at their far (internal) end, and have a significant "de-bonded" free-length at their external end which allows the tendon to stretch during tensioning. Tendons may be full-length bonded to the surrounding concrete or rock once tensioned, or (more commonly) have strands permanently encapsulated in corrosion-inhibiting grease over the free-length to permit long-term load monitoring and re-stressability.
1150:
tensioned, these tendons exert both axial (compressive) and radial (inward) forces onto the structure, which can directly oppose the subsequent storage loadings. If the magnitude of the prestress is designed to always exceed the tensile stresses produced by the loadings, a permanent residual compression will exist in the wall concrete, assisting in maintaining a watertight crack-free structure.
569:. Once cured, this grout can transfer the full tendon tension force to the concrete within a very short distance (approximately 1 metre). As a result, any inadvertent severing of the tendon or failure of an end anchorage has only a very localised impact on tendon performance, and almost never results in tendon ejection from the anchorage. 1393:(PTI) and the Precast/Prestressed Concrete Institute (PCI). Similar bodies include the Canadian Precast/Prestressed Concrete Institute (CPCI), the UK's Post-Tensioning Association, the Post Tensioning Institute of Australia and the South African Post Tensioning Association. Europe has similar country-based associations and institutions. 541:
strands are bundled to form a single unbonded tendon, an enveloping duct of plastic or galvanised steel is used and its interior free-spaces grouted after stressing. In this way, additional corrosion protection is provided via the grease, plastic sheathing, grout, external sheathing, and surrounding concrete layers.
836:
Building structures are typically required to satisfy a broad range of structural, aesthetic and economic requirements. Significant among these include: a minimum number of (intrusive) supporting walls or columns; low structural thickness (depth), allowing space for services, or for additional floors
557:
Both bonded and unbonded post-tensioning technologies are widely used around the world, and the choice of system is often dictated by regional preferences, contractor experience, or the availability of alternative systems. Either one is capable of delivering code-compliant, durable structures meeting
1140:
Most commonly, dam prestressing takes the form of post-tensioned anchors drilled into the dam's concrete structure and/or the underlying rock strata. Such anchors typically comprise tendons of high-tensile bundled steel strands or individual threaded bars. Tendons are grouted to the concrete or rock
771:
Following discovery of tendon corrosion in several bridges in England, the Highways Agency issued a moratorium on the construction of new internally grouted post-tensioned bridges and embarked on a 5-year programme of inspections on its existing post-tensioned bridge stock. The moratorium was lifted
1149:
Circular storage structures such as silos and tanks can use prestressing forces to directly resist the outward pressures generated by stored liquids or bulk-solids. Horizontally curved tendons are installed within the concrete wall to form a series of hoops, spaced vertically up the structure. When
540:
For individual strand tendons, no additional tendon ducting is used and no post-stressing grouting operation is required, unlike for bonded post-tensioning. Permanent corrosion protection of the strands is provided by the combined layers of grease, plastic sheathing, and surrounding concrete. Where
434:
of elements (e.g., strands or wires) placed inside a single tendon duct, with the exception of bars which are mostly used unbundled. This bundling makes for more efficient tendon installation and grouting processes, since each complete tendon requires only one set of end-anchorages and one grouting
236:
technique, where the resulting concrete element is manufactured off-site from the final structure location and transported to site once cured. It requires strong, stable end-anchorage points between which the tendons are stretched. These anchorages form the ends of a "casting bed" which may be many
677:
The durability of prestressed concrete is principally determined by the level of corrosion protection provided to any high-strength steel elements within the prestressing tendons. Also critical is the protection afforded to the end-anchorage assemblies of unbonded tendons or cable-stay systems, as
673:
Long-term durability is an essential requirement for prestressed concrete given its widespread use. Research on the durability performance of in-service prestressed structures has been undertaken since the 1960s, and anti-corrosion technologies for tendon protection have been continually improved
1158:
Prestressed concrete has been established as a reliable construction material for high-pressure containment structures such as nuclear reactor vessels and containment buildings, and petrochemical tank blast-containment walls. Using pre-stressing to place such structures into an initial state of
1175:
Heavily loaded concrete ground-slabs and pavements can be sensitive to cracking and subsequent traffic-driven deterioration. As a result, prestressed concrete is regularly used in such structures as its pre-compression provides the concrete with the ability to resist the crack-inducing tensile
1093:
Concrete is the most popular structural material for bridges, and prestressed concrete is frequently adopted. When investigated in the 1940s for use on heavy-duty bridges, the advantages of this type of bridge over more traditional designs was that it is quicker to install, more economical and
827:
Prestressed concrete is a highly versatile construction material as a result of it being an almost ideal combination of its two main constituents: high-strength steel, pre-stretched to allow its full strength to be easily realised; and modern concrete, pre-compressed to minimise cracking under
696:
Unbonded tendons comprise individual strands coated in an anti-corrosion grease or wax, and fitted with a durable plastic-based full-length sleeve or sheath. The sleeving is required to be undamaged over the tendon length, and it must extend fully into the anchorage fittings at each end of the
339:
The tendons are not placed in direct contact with the concrete, but are encapsulated within a protective sleeve or duct which is either cast into the concrete structure or placed adjacent to it. At each end of a tendon is an anchorage assembly firmly fixed to the surrounding concrete. Once the
268:
are located between the ends of the tendon to hold the tendon to the desired non-linear alignment during tensioning. Such deviators usually act against substantial forces, and hence require a robust casting-bed foundation system. Straight tendons are typically used in "linear"
1136:
Concrete dams have used prestressing to counter uplift and increase their overall stability since the mid-1930s. Prestressing is also frequently retro-fitted as part of dam remediation works, such as for structural strengthening, or when raising crest or spillway heights.
2309: 548:
process. The bare steel strand is fed into a greasing chamber and then passed to an extrusion unit where molten plastic forms a continuous outer coating. Finished strands can be cut-to-length and fitted with "dead-end" anchor assemblies as required for the project.
606:
Improved fire performance. The absence of strain redistribution in bonded tendons may limit the impact that any localised overheating has on the overall structure. As a result, bonded structures may display a higher capacity to resist fire conditions than unbonded
828:
tensile forces. Its wide range of application is reflected in its incorporation into the major design codes covering most areas of structural and civil engineering, including buildings, bridges, dams, foundations, pavements, piles, stadiums, silos, and tanks.
862:
The combination of reduced structural thickness, reduced conventional reinforcement quantities, and fast construction often results in prestressed concrete showing significant cost benefits in building structures compared to alternative structural
603:). With the tendons fixed to the concrete at each side of the crack, greater resistance to crack expansion is offered than with unbonded tendons, allowing many design codes to specify reduced reinforcement requirements for bonded post-tensioning. 499:
Unbonded slab post-tensioning. (Above) Installed strands and edge-anchors are visible, along with prefabricated coiled strands for the next pour. (Below) End-view of slab after stripping forms, showing individual strands and stressing-anchor
856:
Typically, prestressed concrete building elements are fully stressed and self-supporting within five days. At this point they can have their formwork stripped and re-deployed to the next section of the building, accelerating construction
3045: 237:
times the length of the concrete element being fabricated. This allows multiple elements to be constructed end-to-end in the one pre-tensioning operation, allowing significant productivity benefits and economies of scale to be realized.
797:
was detected in some of the prestressing tendons, necessitating initial closure of the road while additional investigations were done. Subsequent repairs and strengthening using external post-tensioning was carried out and completed in
647:
Simpler replacement and/or adjustment. Being permanently isolated from the concrete, unbonded tendons are able to be readily de-stressed, re-stressed and/or replaced should they become damaged or need their force levels to be modified
263:
Unlike those of post-tensioned concrete (see below), the tendons of pre-tensioned concrete elements generally form straight lines between end-anchorages. Where "profiled" or "harped" tendons are required, one or more intermediate
2305: 710:
and re-stressable dam anchors, will typically employ double-layer corrosion protection. Such tendons are composed of individual strands, grease-coated and sleeved, collected into a strand-bundle and placed inside encapsulating
2269: 1933: 3235: 536:
Bundled strands, individually greased-and-sheathed, forming a single tendon within an encapsulating duct that is placed either within or adjacent to the concrete (e.g., restressable anchors, external post-tensioning)
1162:
Nuclear reactor and containment vessels will commonly employ separate sets of post-tensioned tendons curved horizontally or vertically to completely envelop the reactor core. Blast containment walls, such as for
678:
the anchorages of both of these are required to retain the prestressing forces. Failure of any of these components can result in the release of prestressing forces, or the physical rupture of stressing tendons.
111:
in many situations. In a prestressed concrete member, the internal stresses are introduced in a planned manner so that the stresses resulting from the imposed loads are counteracted to the desired degree.
651:
Superior overload performance. Although having a lower ultimate strength than bonded tendons, unbonded tendons' ability to redistribute strains over their full length can give them superior pre-collapse
3189: 1971: 637:. Unbonded single-strand tendons have greater handling flexibility than bonded ducting during installation, allowing them a greater ability to be deviated around service penetrations or obstructions. 2149: 95:. The essence of prestressed concrete is that once the initial compression has been applied, the resulting material has the characteristics of high-strength concrete when subject to any subsequent 1389:
Worldwide, many professional organizations exist to promote best practices in the design and construction of prestressed concrete structures. In the United States, such organizations include the
687:
Bonded tendons consist of bundled strands placed inside ducts located within the surrounding concrete. To ensure full protection to the bundled strands, the ducts must be pressure-filled with a
3065: 2380: 2068: 644:. Unbonded tendons may allow some reduction in concrete element thickness, as their smaller size and increased corrosion protection may allow them to be placed closer to the concrete surface. 3454: 386:
Casting the tendon ducts/sleeves into the concrete before any tensioning occurs allows them to be readily "profiled" to any desired shape including incorporating vertical and/or horizontal
3292: 458:, placing the tendon ducting to the required curvature profiles, and reeving (or threading) the strands or wires through the ducting. Following concreting and tensioning, the ducts are 3111: 2459: 2261: 3635: 2008: 1159:
bi-axial or tri-axial compression increases their resistance to concrete cracking and leakage, while providing a proof-loaded, redundant and monitorable pressure-containment system.
3717: 3334: 2791: 1921: 3415: 851:
For a given span, lower in-service deflections allows thinner structural sections to be used, in turn resulting in lower floor-to-floor heights, or more room for building services.
840:
The prestressing of concrete allows "load-balancing" forces to be introduced into the structure to counter in-service loadings. This provides many benefits to building structures:
565:
Reduced reliance on end-anchorage integrity. Following tensioning and grouting, bonded tendons are connected to the surrounding concrete along their full length by high-strength
837:
in high-rise construction; fast construction cycles, especially for multi-storey buildings; and a low cost-per-unit-area, to maximise the building owner's return on investment.
2496: 715:
outer ducting. The remaining void space within the duct is pressure-grouted, providing a multi-layer polythene-grout-plastic-grease protection barrier system for each strand.
818:
The flyovers were closed in September 2018 after inspections revealed poor quality concrete, tendon corrosion and signs of structural distress. They were demolished in 2019.
186:
of it (external prestressing). While pre-tensioned concrete uses tendons directly bonded to the concrete, post-tensioned concrete can use either bonded or unbonded tendons.
3668: 1639:
Post-tensioned concreted is "structural concrete in which internal stresses have been introduced to reduce potential tensile stresses in the concrete resulting from loads."
1537: 1167:(LNG) tanks, will normally utilize layers of horizontally-curved hoop tendons for containment in combination with vertically looped tendons for axial wall pre-stressing. 3373: 2751: 75:
of high-strength "tendons" located within or adjacent to the concrete and is done to improve the performance of the concrete in service. Tendons may consist of single
785:
was added to the tendon grout to speed construction, leading to corrosion of the prestressing strands and the sudden collapse of one span, injuring many spectators.
2110: 1795: 846:
Load balancing results in lower in-service deflections, which allows spans to be increased (and the number of supports reduced) without adding to structural depth.
3532: 3178: 2714: 2673: 2203: 1956: 1895: 2133: 2984: 630:. The elimination of the post-stressing grouting process required in bonded structures improves the site-labour productivity of unbonded post-tensioning. 619:. Unbonded tendons can be readily prefabricated off-site complete with end-anchorages, facilitating faster installation during construction. Additional 363:
steel materials, and are classified into two main types: those where the tendon element is subsequently bonded to the surrounding concrete by internal
3019: 2369: 510:
movement relative to the concrete. This is most commonly achieved by encasing each individual tendon element within a plastic sheathing filled with a
2037: 1403:
Rules and requirements for the detailing of reinforcement and prestressing tendons are specified by individual national codes and standards such as:
1353: 394:
forces being imparted onto the hardened concrete, and these can be beneficially used to counter any loadings subsequently applied to the structure.
4452: 3499: 443:
steel, and can be either round or rectangular/oval in cross-section. The tendon sizes used are highly dependent upon the application, ranging from
3564: 2530: 423:; to permanently "lock-in" the tendon pre-tension, thereby removing the long-term reliance upon the end-anchorage systems; and to improve certain 936: 3273: 2635: 1626: 419:
of their encapsulating ducting (after tendon tensioning). This grouting is undertaken for three main purposes: to protect the tendons against
3438: 2864: 1573: 720:
In all post-tensioned installations, protection of the end-anchorages against corrosion is essential, and critically so for unbonded systems.
3088: 2436: 1109:
In short-span bridges of around 10 to 40 metres (30 to 130 ft), prestressing is commonly employed in the form of precast pre-tensioned
3627: 1997: 3694: 3318: 2780: 3399: 4545: 4473: 3601: 1337: 2886: 2180: 1400:
or standards, but rather exist to promote the understanding and development of prestressed concrete design, codes and best practices.
4190: 3900: 2485: 2238: 1858: 1819:"Tendons having one or more deviations from a straight line, either vertically or horizontally, between the ends of the structure" 115:
Prestressed concrete is used in a wide range of building and civil structures where its improved performance can allow for longer
3657: 2920: 2592: 1521: 64:) during production, in a manner that strengthens it against tensile forces which will exist when in service. It was patented by 4341: 1460: 970: 3874:
Historical Patents and the Evolution of Twentieth Century Architectural Construction with Reinforced and Pre-stressed Concrete
3409: 3367: 3357: 3328: 2827: 2740: 2143: 2104: 1586: 2833: 803:
One span of a 12-span viaduct collapsed on 7 July 2014, causing 4 injuries, due to corrosion of the post-tensioning tendons.
4015: 4432: 1263: 1204: 2343: 2094: 1784: 1289: 952: 2925: 917: 3866:
Guidelines for Sampling, Assessing, and Restoring Defective Grout in Prestressed Concrete Bridge Post-Tensioning Ducts
3557:
Construction of a Precast Prestressed Concrete Pavement Demonstration Project on Interstate 57 near Sikeston, Missouri
3524: 1113:
or planks. Medium-length structures of around 40 to 200 metres (150 to 650 ft), typically use precast-segmental,
1008: 3493: 3448: 1767: 1731: 1685: 1660: 1531: 2413: 1257: 1046: 4200: 2699: 2658: 2211: 1305: 776: 4555: 2561: 3257:
Cavill, Brian (20 March 1997). "Very High capacity Ground Anchors Used in Strengthening Concrete Gravity Dams".
1884: 1419: 1369: 1225: 454:
Fabrication of bonded tendons is generally undertaken on-site, commencing with the fitting of end-anchorages to
3930: 3868: 1273: 989: 3783: 2291: 4406: 3973: 3893: 1065: 923: 888: 1027: 4550: 3010: 1375: 1216: 904: 1241: 506:
Unbonded post-tensioning differs from bonded post-tensioning by allowing the tendons permanent freedom of
4540: 4447: 4422: 4336: 4303: 507: 3555: 3480: 2973: 596: 435:
operation. Ducting is fabricated from a durable and corrosion-resistant material such as plastic (e.g.,
355:
Balanced-cantilever bridge under construction. Each added segment is supported by post-tensioned tendons
4401: 4215: 3925: 2522: 104: 1321: 533:
Individual strand tendons placed directly into the concreted structure (e.g., buildings, ground slabs)
4437: 4379: 4298: 4238: 4053: 3968: 3873: 3809: 1390: 1231: 1180: 661: 581: 526:
force to the concrete, and are required to reliably perform this role for the life of the structure.
341: 2615: 1618: 1102:. By the 1960s, prestressed concrete largely superseded reinforced concrete bridges in the UK, with 1094:
longer-lasting with the bridge being less lively. One of the first bridges built in this way is the
584:
at that same location (i.e. no strain re-distribution occurs). This results in significantly higher
178:, where all strands or wires in a tendon are stressed simultaneously. Tendons may be located either 3886: 132: 2856: 1592: 4210: 3835: 3757: 3741: 3216:"Strengthening of existing concrete dams using post-tensioned anchors: A state-of-the-art review" 1444: 1359: 1196: 976: 884: 305: 3955: 3860: 4308: 4185: 4109: 4000: 3995: 2172: 1475: 1124:. For the longest bridges, prestressed concrete deck structures often form an integral part of 703: 277:; whereas profiled tendons are more commonly found in deeper precast bridge beams and girders. 1759: 225:
Pre-tensioned bridge girder in precasting bed, with single-strand tendons exiting through the
4391: 4134: 1470: 876: 573: 410:
In bonded post-tensioning, tendons are permanently bonded to the surrounding concrete by the
332:
Post-tensioned concrete is a variant of prestressed concrete where the tendons are tensioned
328:
Post-tensioned tendon anchorage; four-piece "lock-off" wedges are visible holding each strand
61: 3590: 1751: 681:
Modern prestressing systems deliver long-term durability by addressing the following areas:
202:
Pre-tensioned concrete is a variant of prestressed concrete where the tendons are tensioned
4427: 4328: 4323: 4195: 4058: 3149: 2894: 2890: 1455: 580:. With bonded post-tensioning, any flexure of the structure is directly resisted by tendon 156: 1450: 65: 8: 4374: 4293: 4063: 4005: 1439: 1425: 1125: 788: 707: 688: 589: 424: 120: 108: 3153: 2330: 2234: 4288: 4205: 2060: 1922:"Comparison of unbonded and bonded post-tensioned concrete slabs under fire conditions" 1847: 1164: 1121: 958: 868: 763:, leading to a progressive failure of the main bridge span and the death of one person. 515: 391: 376: 170:, which occurs after the concrete is cast. Tensioning systems may be classed as either 116: 96: 84: 3861:
The story of prestressed concrete from 1930 to 1945: A step towards the European Union
2584: 4517: 4273: 4268: 4243: 4225: 4139: 4119: 3940: 3489: 3444: 3405: 3363: 3324: 3215: 2823: 2627: 2139: 2100: 2064: 1763: 1752: 1727: 1681: 1656: 1650: 1582: 1527: 1117: 1103: 748: 585: 523: 459: 351: 211: 162:
First used in the late nineteenth century, prestressed concrete has developed beyond
100: 72: 4396: 4369: 4278: 4144: 4104: 3983: 3945: 3709: 3284: 3227: 3157: 3103: 3057: 2916: 2451: 2052: 1480: 731: 281: 274: 270: 256: 24: 2455: 4313: 4164: 4068: 3978: 3713: 3288: 3107: 3061: 2817: 2056: 1279: 1208: 1014: 892: 766: 297: 215: 3162: 3137: 867:
Some notable building structures constructed from prestressed concrete include:
734:
structure constructed in 1953 with longitudinal and transverse post-tensioning.
544:
Individually greased-and-sheathed tendons are usually fabricated off-site by an
402: 251: 4386: 4318: 4159: 4078: 4048: 4043: 3935: 2776: 781:
A multi-span steel and concrete structure constructed in 1995. An unauthorised
752: 641: 280:
Pre-tensioned concrete is most commonly used for the fabrication of structural
233: 210:, following which the end-anchoring of the tendons is released, and the tendon 4035: 1179:
Some notable civil structures constructed using prestressed concrete include:
782: 611:
The benefits that unbonded post-tensioning can offer over bonded systems are:
561:
The benefits that bonded post-tensioning can offer over unbonded systems are:
4534: 4359: 4258: 4248: 4154: 2631: 2332: 1397: 1311: 1247: 1200: 1184: 1052: 900: 806: 616: 285: 128: 794: 793:
Sixteen-span prestressed structure constructed in 1961. Corrosion from road
119:, reduced structural thicknesses, and material savings compared with simple 4263: 4149: 4124: 3917: 1327: 1188: 1095: 1071: 1033: 908: 896: 712: 627: 490: 479: 436: 345: 245: 92: 88: 4073: 316: 207: 19: 4364: 4083: 4020: 1343: 1192: 995: 872: 634: 558:
the structural strength and serviceability requirements of the designer.
552: 447:
works typically using between 2 and 6 strands per tendon, to specialized
301: 148: 124: 2405: 194: 4468: 4253: 4233: 4025: 3138:"Rock-engineering design of post-tensioned anchors for dams - A review" 1726:(2nd ed.). Melbourne, Australia: Longman Cheshire. pp. 1–13. 588:
strains in the tendons than if they were unbonded, allowing their full
440: 430:
Bonded post-tensioning characteristically uses tendons each comprising
360: 40:
After concrete solidifies, tendons apply compressive stress to concrete
3443:(Second ed.). New York: John Wiley & Sons. pp. 472–494. 2947: 2863:. Vol. 123. Simmons-Boardman Publishing Company. pp. 54–58. 2553: 1885:"Nonprestresed Bonded Reinforcement in Post-Tensioned Building Design" 1848:"Unbonded and bonded post-tensioning systems in building construction" 1680:. South Melbourne, Australia: Addison Welsley Longman. pp. 8–19. 324: 37:
Before concrete solidifies, tendons embedded in concrete are tensioned
4499: 3865: 3401:
Structures for Nuclear Facilities – Analysis, Design and Construction
1465: 813: 760: 735: 660:-type action instead of pure flexure, allowing significantly greater 653: 620: 545: 511: 463: 420: 387: 152: 80: 3356:
Gilbert, R. I.; Mickleborough, N. C.; Ranzi, G. (17 February 2016).
3274:"Analysis and Design of Prestressed Circular Concrete Storage Tanks" 3231: 371:
post-tensioning); and those where the tendon element is permanently
206:
to the concrete being cast. The concrete bonds to the tendons as it
4483: 4478: 4114: 3909: 3779: 2135:
Bridge Management 4: Inspection, Maintenance, Assessment and Repair
1412: 1295: 1212: 880: 756: 657: 455: 444: 241: 226: 57: 1676:
Warner, R. F.; Rangan, B. V.; Hall, A. S.; Faulkes, K. A. (1988).
1571: 599:, bonded tendons respond similarly to conventional reinforcement ( 174:, where each tendon's strand or wire is stressed individually, or 4442: 4010: 3554:
Merritt, David; Rogers, Richard; Rasmussen, Robert (March 2008).
1408: 577: 519: 412: 289: 221: 4169: 4129: 3963: 1110: 320:
Forces on post-tensioned concrete with profiled (curved) tendon
293: 136: 3176: 2331:
Australian Society for History of Engineering and Technology.
691:
grout, without leaving any voids, following strand-tensioning.
592:
to be realised, and producing a higher ultimate load capacity.
4088: 3990: 2435:
Knoll, Franz; Prosser, M. John; Otter, John (May–June 1976).
1998:"Survey on the Durability of Prestressed Concrete Structures" 668: 600: 566: 416: 364: 359:
Tendon encapsulation systems are constructed from plastic or
2204:"Corrosdion Failures: Lowe's Motor Speedway Bridge Collapse" 738:
attacked the under-protected tendons where they crossed the
390:. When the tendons are tensioned, this profiling results in 375:
bonded from the surrounding concrete, usually by means of a
3878: 3591:"Design of the Main Spans, Second Gateway Bridge, Brisbane" 2857:"Prestressed Concrete Bridge Beams Being Tested in England" 801:
Petrulla Viaduct ("Viadotto Petrulla"), Sicily, Italy, 2014
144: 76: 3831: 3805: 2370:"Structural Design of the 84 Storey World Tower in Sydney" 3355: 3012:
Bridge Construction Practices Using Incremental Launching
2232: 1749: 1422:: Building Code Requirements for Reinforced Concrete; and 903:, Madrid; Guoco Tower (Tanjong Pagar Centre), Singapore; 522:
based. Anchorages at each end of the tendon transfer the
448: 140: 103:. This can result in improved structural capacity and/or 60:
used in construction. It is substantially "prestressed" (
27:(top) and prestressed concrete beam (bottom) under load: 3589:
Connall, John; Wheeler, Paul; Pau, Andrew; Mihov, Miho.
2971: 2235:"TfL report warned of Hammersmith Flyover collapse risk" 742:
joints between the segments, leading to sudden collapse.
1675: 1616: 1526:(Third ed.). New York, US: John Wiley & Sons. 1099: 3753: 3553: 2551: 553:
Comparison between bonded and unbonded post-tensioning
182:
the concrete volume (internal prestressing) or wholly
3695:"1300-Ton-Capacity Prestressed Anchors Stabilize Dam" 3142:
Journal of Rock Mechnanics and Geological Engineering
2819:
Prestressed Concrete bridges: design and Construction
2038:"Corrosion of Prestressing Steels and its Mitigation" 1857:(5). Phoenix, Arizona US: Post-Tensioning Institute. 2292:"Giù il viadotto Petrulla, panico sulla Statale 626" 1572:
Federation Internationale du Beton (February 2005).
724:
Several durability-related events are listed below:
623:
may need to be allowed for this fabrication process.
595:
Improved crack-control. In the presence of concrete
2915: 2854: 2333:"An Engineering Walk around the Sydney Opera House" 99:and of ductile high-strength steel when subject to 3588: 2131: 1957:"Two way post-tensioned slabs with bonded tendons" 1384: 336:the surrounding concrete structure has been cast. 214:are transferred to the concrete as compression by 83:or threaded bars that are most commonly made from 3754:"Canadian Precast/Prestressed Concrete Institute" 3261:. London UK: Institution of Civil Engineers: 262. 2434: 1782: 4532: 4453:International Federation for Structural Concrete 3692: 3488:(Fourth ed.). New Delhi: Tata McGraw Hill. 3046:"Cable Stayed Bridges with Prestressed Concrete" 2582: 656:. In extremes, unbonded tendons can resort to a 3440:Construction of Prestressed Concrete Structures 3323:(Third ed.). CRC Press. pp. 149–165. 2379:. Council on Tall Buildings and Urban Habitat. 1396:These organizations are not the authorities of 728:Ynys-y-Gwas bridge, West Glamorgan, Wales, 1985 529:Unbonded post-tensioning can take the form of: 2691: 2486:"Kai Tak Cruise Terminal Building - Hong Kong" 2306:"Churchill Way Flyovers Deconstruction Scheme" 2132:Ryall, M. J.; Woodward, R.; Milne, D. (2000). 1919: 1758:(6th ed.). Phoenix, AZ US: PTI. pp.  3894: 3693:Eberhardt, A.; Veltrop, J. A. (August 1965). 3359:Design of Prestressed Concrete to AS3600-2009 2613: 2406:"The Tower, One St. George Wharf, London, UK" 2233:Ed Davey and Rebecca Cafe (3 December 2012). 1721: 1575:fib Bulletin 31: Post-tensioning in Buildings 462:and the tendon stressing-ends sealed against 3213: 2650: 2614:Martinez, Julio; Gomez, Miguel (July 2008). 2585:"Eureka Tower, Melbourne Victoria Australia" 2138:. London: Thomas Telford. pp. 170–173. 167: 3832:"South African Post Tensioning Association" 2697: 2656: 2262:"Extending the Life of Hammersmith Flyover" 2092: 1170: 1098:, a railway bridge constructed 1946 in the 674:since the earliest systems were developed. 469: 163: 3901: 3887: 3393: 3391: 3086: 3008: 2361: 2031: 2029: 1745: 1743: 1717: 1648: 844:Longer spans for the same structural depth 745:Scheldt River bridge, Melle, Belgium, 1991 669:Tendon durability and corrosion protection 311: 3563:. US DOT Federal Highway Administration. 3271: 3265: 3170: 3161: 3043: 2738: 1920:Bailey, Colin G.; Ellobody, Ehab (2009). 1841: 1839: 1837: 1835: 1833: 1831: 1829: 1827: 1825: 1715: 1713: 1711: 1709: 1707: 1705: 1703: 1701: 1699: 1697: 1655:. Princeton: Princeton University Press. 1523:Design of Prestressed Concrete Structures 702:Prestressing tendons requiring permanent 451:works using up to 91 strands per tendon. 397: 248:for bonding than bundled-strand tendons. 189: 3806:"Post Tensioning Institute of Australia" 3650: 3525:"Building Post-Tensioned Slabs on Grade" 2226: 1970:(2). US: Post-Tensioning Institute: 44. 1519: 401: 350: 323: 315: 250: 220: 193: 18: 3619: 3582: 3474: 3472: 3436: 3430: 3397: 3388: 3349: 3214:Xu, Haixue; Benmokrane, Brahim (1996). 2887:"History of Prestressed Concrete in UK" 2732: 2607: 2035: 2026: 1995: 1989: 1740: 1669: 1610: 1567: 1565: 1563: 1561: 1559: 1557: 1555: 1515: 1513: 1511: 1509: 1507: 1505: 1503: 1501: 1499: 1497: 4533: 3812:from the original on 25 September 2016 3786:from the original on 19 September 2016 3742:Precast/Prestressed Concrete Institute 3723:from the original on 16 September 2016 3607:from the original on 17 September 2016 3570:from the original on 15 September 2016 3535:from the original on 18 September 2016 3505:from the original on 11 September 2016 3298:from the original on 16 September 2016 3256: 3250: 3195:from the original on 14 September 2016 3117:from the original on 16 September 2016 3089:"Prestressed Concrete Dams: 1936–1964" 2990:from the original on 16 September 2016 2974:"Structures Engineering Design Manual" 2815: 2809: 2797:from the original on 17 September 2016 2720:from the original on 22 September 2016 2679:from the original on 22 September 2016 2576: 2564:from the original on 24 September 2016 2502:from the original on 14 September 2016 2477: 2465:from the original on 15 September 2016 2272:from the original on 15 September 2016 2259: 2074:from the original on 16 September 2016 2014:from the original on 16 September 2016 1936:from the original on 17 September 2016 1913: 1882: 1845: 1822: 1722:Warner, R. F.; Faulkes, K. A. (1988). 1694: 1625:. Farmington Hills, Michigan US: ACI. 1461:Glossary of prestressed concrete terms 831: 3882: 3674:from the original on 26 February 2017 3316: 3310: 3220:Canadian Journal of Civil Engineering 3135: 3129: 3025:from the original on 30 November 2016 2855:R. L. M'ilmoyle (20 September 1947). 2741:"Case Study: Capital Gate, Abu Dhabi" 2595:from the original on 13 February 2012 2545: 2533:from the original on 4 September 2016 2523:"International Commerce Centre (ICC)" 2398: 2367: 1954: 1948: 1876: 1864:from the original on 23 November 2016 1846:Aalami, Bijan O. (5 September 1994). 1629:from the original on 11 December 2016 751:constructed in the 1950s. Inadequate 16:Form of concrete used in construction 4016:Ground granulated blast-furnace slag 3628:"Incheon Bridge, Seoul, South Korea" 3478: 3469: 3437:Gerwick, Ben C. (13 February 1997). 3404:. London: Springer. pp. 36–37. 3177:Institution of Engineers Australia. 2965: 2775: 2638:from the original on 8 February 2017 2349:from the original on 8 February 2017 2241:from the original on 3 December 2012 1901:from the original on 8 February 2017 1801:from the original on 8 February 2017 1552: 1540:from the original on 8 February 2017 1494: 1153: 344:anchoring (for strand tendons), and 71:This compression is produced by the 4433:Institution of Structural Engineers 3638:from the original on 10 August 2016 3625: 3087:Roemermann, A. C. (February 1965). 3044:Leonhardt, Fritz (September 1987). 2616:"Torre Espacio. Building Structure" 2514: 2324: 1977:from the original on 28 August 2016 1955:Bondy, Kenneth B. (December 2012). 1083: 406:Multi-strand post-tensioning anchor 13: 3457:from the original on 17 April 2021 3418:from the original on 17 April 2021 3376:from the original on 17 April 2021 3337:from the original on 17 April 2021 3009:LaViolette, Mike (December 2007). 2926:National Heritage List for England 2867:from the original on 17 April 2021 2836:from the original on 17 April 2021 2428: 2416:from the original on 30 April 2021 2386:from the original on 14 April 2016 2152:from the original on 17 April 2021 2113:from the original on 17 April 2021 2093:De Schutter, Geert (10 May 2012). 2036:Podolny, Walter (September 1992). 1883:Aalami, Bijan O. (February 2001). 1750:Post-Tensioning Institute (2006). 1428:AS 3600-2009: Concrete Structures. 1144: 14: 4567: 4546:Concrete buildings and structures 3854: 3479:Raju, Krishna (1 December 2006). 3320:Circular Storage Tasnks and Silos 3272:Priestley, M. J. N. (July 1985). 3238:from the original on 29 June 2021 2952:Concrete Bridge Development Group 2757:from the original on 30 July 2016 2700:"Gateway to South Eastern Europe" 2312:from the original on 9 April 2021 2183:from the original on 11 June 2016 2170: 1996:Szilard, Rudolph (October 1969). 1619:"CT-13: ACI Concrete Terminology" 1520:Lin, T.Y.; Burns, Ned H. (1981). 1415:2: Design of Concrete Structures; 706:and/or force adjustment, such as 694:Tendon coating (unbonded tendons) 427:of the final concrete structure. 273:elements, such as shallow beams, 31:Non-prestressed beam without load 4513: 4512: 3838:from the original on 25 May 2016 2781:"Evolution of Bridge Technology" 2520: 2201: 1368: 1352: 1336: 1320: 1304: 1288: 1272: 1256: 1240: 1224: 1064: 1045: 1026: 1007: 988: 969: 951: 935: 916: 685:Tendon grouting (bonded tendons) 489: 478: 379:sheath over the tendon strands ( 3824: 3798: 3772: 3760:from the original on 5 May 2021 3746: 3735: 3686: 3547: 3517: 3207: 3080: 3037: 3002: 2940: 2909: 2879: 2848: 2769: 2483: 2298: 2284: 2253: 2195: 2164: 2125: 2086: 1385:Design agencies and regulations 822: 123:. Typical applications include 3931:Roman architectural revolution 3869:Federal Highway Administration 3362:(Second ed.). CRC Press. 3136:Brown, E. T. (February 2015). 3018:. AASHTO. p. Appendix A. 2972:Main Roads Western Australia. 1813: 1776: 1642: 1122:incrementally-launched designs 157:nuclear containment structures 34:Non-prestressed beam with load 23:Comparison of non-prestressed 1: 3780:"Post-Tensioning Association" 3186:www.engineersaustralia.org.au 2948:"History of Concrete Bridges" 2626:(249). Madrid, Spain: 19–43. 2456:10.15554/pcij.05011976.84.111 2099:. CRC Press. pp. 31–33. 2096:Damage to Concrete Structures 1617:American Concrete Institute. 1487: 889:International Commerce Centre 367:of the duct after stressing ( 348:anchoring (for bar tendons). 107:compared with conventionally 43:Prestressed beam without load 3908: 3714:10.15554/pcij.08011965.18.36 3529:www.concreteconstruction.net 3289:10.15554/pcij.07011985.64.85 3108:10.15554/pcij.02011965.76.88 3062:10.15554/pcij.09011987.52.80 2554:"Ocean Heights 2, Dubai UAE" 2552:CM Engineering Consultants. 2057:10.15554/pcij.09011992.34.55 1785:"CFCC Pre-tensioning Manual" 905:Zagreb International Airport 849:Reduced structural thickness 7: 4448:Portland Cement Association 4423:American Concrete Institute 3667:. SRG Limited. p. 10. 3317:Ghali, Amin (12 May 2014). 3163:10.1016/j.jrmge.2014.08.001 2788:IABSE Symposium Proceedings 2589:www.designbuild-network.com 2437:"Prestressing the CN Tower" 2368:Martin, Owen; Lal, Nalean. 1892:ADAPT Technical Publication 1623:American Concrete Institute 1432: 759:resulted in tie-down cable 232:Pre-tensioning is a common 10: 4572: 3926:Ancient Roman architecture 3398:Bangash, M. Y. H. (2011). 1649:Billington, David (1985). 1088: 779:, North Carolina, US, 2000 700:Double-layer encapsulation 664:before structural failure. 46:Prestressed beam with load 4508: 4492: 4461: 4438:Indian Concrete Institute 4415: 4352: 4224: 4178: 4097: 4034: 3954: 3916: 3531:. Concrete Construction. 2816:Hewson, Nigel R. (2012). 2173:"Post-Tensioning Systems" 1391:Post-Tensioning Institute 1106:being the dominant form. 747:A three-span prestressed 3179:"Catagunya Dam Tasmania" 2983:. MRWA. pp. 17–23. 2921:"Adam Viaduct (1061327)" 2739:Schofield, Jeff (2012). 2659:"Reaching for the Skies" 2591:. Design Build Network. 1652:The Tower and the Bridge 1445:Dyckerhoff & Widmann 1219:, Videbergshamn Sweden. 1217:Ringhals nuclear reactor 1171:Hardstands and pavements 812:Churchill Way flyovers, 777:Charlotte Motor Speedway 470:Unbonded post-tensioning 2981:www.mainroads.wa.gov.au 1926:The Structural Engineer 1783:Tokyo Rope Mfg Co Ltd. 1215:, Toronto, Canada; and 1207:, Itz Valley, Germany; 1131: 885:Kai Tak Cruise Terminal 312:Post-tensioned concrete 255:Pre-tensioned, precast 240:The amount of bond (or 4556:Structural engineering 4216:Alkali–silica reaction 3974:Energetically modified 3259:Conference Proceedings 2893:. 2004. Archived from 2583:Design Build Network. 2210:. NACE. Archived from 1754:Post-Tensioning Manual 1476:Properties of concrete 1376:Ringhals nuclear plant 1183:, Brisbane Australia; 942:Guoco Tower, Singapore 860:Reduced material costs 633:Improved installation 407: 398:Bonded post-tensioning 356: 329: 321: 260: 229: 199: 198:Pre-tensioning process 190:Pre-tensioned concrete 50: 3665:www.srglimited.com.au 3658:"SRG Remote Projects" 3632:www.dywidag-systems.a 1471:Prestressed structure 1379:Videbergshamn, Sweden 1199:, South Hook, Wales; 877:St George Wharf Tower 854:Faster stripping time 807:Genoa bridge collapse 791:London, England, 2011 405: 354: 327: 319: 288:, hollow-core slabs, 254: 224: 197: 22: 4201:Environmental impact 4059:Reversing drum mixer 3482:Prestressed Concrete 3068:on 16 September 2016 2891:Cambridge University 2698:BBR Network (2016). 2657:BBR Network (2016). 2237:. BBC News, London. 2214:on 24 September 2016 1724:Prestressed Concrete 1456:Freyssinet Test Arch 1126:cable-stayed designs 749:cantilever structure 718:Anchorage protection 689:corrosion-inhibiting 425:structural behaviors 153:industrial pavements 54:Prestressed concrete 4551:Reinforced concrete 3154:2015JRMGE...7....1B 1855:PTI Technical Notes 1678:Concrete Structures 1440:Cable stayed bridge 1426:Australian Standard 1267:Itz Valley, Germany 1205:Autobahn A73 bridge 1118:balanced-cantilever 832:Building structures 789:Hammersmith Flyover 775:Pedestrian bridge, 125:high-rise buildings 121:reinforced concrete 109:reinforced concrete 85:high-tensile steels 4541:Building materials 4304:Self-consolidating 3996:Water–cement ratio 2266:www.freyssinet.com 1598:on 8 February 2017 1407:European Standard 1211:, Moscow, Russia; 1195:, Washington, US; 1165:liquid natural gas 959:Sydney Opera House 869:Sydney Opera House 767:UK Highways Agency 408: 383:post-tensioning). 357: 330: 322: 261: 230: 200: 133:foundation systems 97:compression forces 51: 4526: 4525: 4518:Category:Concrete 4299:Roller-compacting 4120:Climbing formwork 3969:Calcium aluminate 3941:Roman engineering 3411:978-3-642-12560-7 3369:978-1-4665-7277-5 3330:978-1-4665-7104-4 2897:on 25 August 2018 2829:978-0-7277-4113-4 2145:978-0-7277-2854-8 2106:978-0-415-60388-1 1588:978-2-88394-071-0 1451:Eugène Freyssinet 1363:South Hook, Wales 1331:Ad Damazin, Sudan 1203:, Brevik Norway; 1154:Nuclear and blast 911:, Abu Dhabi UAE. 732:precast-segmental 574:ultimate strength 275:hollow-core slabs 66:Eugène Freyssinet 4563: 4516: 4515: 4428:Concrete Society 4239:Fiber-reinforced 4054:Volumetric mixer 3946:Roman technology 3903: 3896: 3889: 3880: 3879: 3848: 3847: 3845: 3843: 3828: 3822: 3821: 3819: 3817: 3802: 3796: 3795: 3793: 3791: 3776: 3770: 3769: 3767: 3765: 3750: 3744: 3739: 3733: 3732: 3730: 3728: 3722: 3699: 3690: 3684: 3683: 3681: 3679: 3673: 3662: 3654: 3648: 3647: 3645: 3643: 3623: 3617: 3616: 3614: 3612: 3606: 3595: 3586: 3580: 3579: 3577: 3575: 3569: 3562: 3551: 3545: 3544: 3542: 3540: 3521: 3515: 3514: 3512: 3510: 3504: 3487: 3476: 3467: 3466: 3464: 3462: 3434: 3428: 3427: 3425: 3423: 3395: 3386: 3385: 3383: 3381: 3353: 3347: 3346: 3344: 3342: 3314: 3308: 3307: 3305: 3303: 3297: 3278: 3269: 3263: 3262: 3254: 3248: 3247: 3245: 3243: 3226:(6): 1151–1171. 3211: 3205: 3204: 3202: 3200: 3194: 3183: 3174: 3168: 3167: 3165: 3133: 3127: 3126: 3124: 3122: 3116: 3093: 3084: 3078: 3077: 3075: 3073: 3064:. Archived from 3041: 3035: 3034: 3032: 3030: 3024: 3017: 3006: 3000: 2999: 2997: 2995: 2989: 2978: 2969: 2963: 2962: 2960: 2958: 2944: 2938: 2937: 2935: 2933: 2917:Historic England 2913: 2907: 2906: 2904: 2902: 2883: 2877: 2876: 2874: 2872: 2852: 2846: 2845: 2843: 2841: 2813: 2807: 2806: 2804: 2802: 2796: 2785: 2773: 2767: 2766: 2764: 2762: 2756: 2745: 2736: 2730: 2729: 2727: 2725: 2719: 2704: 2695: 2689: 2688: 2686: 2684: 2678: 2663: 2654: 2648: 2647: 2645: 2643: 2620:Hormigon y Acero 2611: 2605: 2604: 2602: 2600: 2580: 2574: 2573: 2571: 2569: 2549: 2543: 2542: 2540: 2538: 2518: 2512: 2511: 2509: 2507: 2501: 2490: 2481: 2475: 2474: 2472: 2470: 2464: 2441: 2432: 2426: 2425: 2423: 2421: 2402: 2396: 2395: 2393: 2391: 2385: 2374: 2365: 2359: 2358: 2356: 2354: 2348: 2337: 2328: 2322: 2321: 2319: 2317: 2302: 2296: 2295: 2288: 2282: 2281: 2279: 2277: 2257: 2251: 2250: 2248: 2246: 2230: 2224: 2223: 2221: 2219: 2199: 2193: 2192: 2190: 2188: 2168: 2162: 2161: 2159: 2157: 2129: 2123: 2122: 2120: 2118: 2090: 2084: 2083: 2081: 2079: 2073: 2042: 2033: 2024: 2023: 2021: 2019: 2013: 2002: 1993: 1987: 1986: 1984: 1982: 1976: 1961: 1952: 1946: 1945: 1943: 1941: 1917: 1911: 1910: 1908: 1906: 1900: 1889: 1880: 1874: 1873: 1871: 1869: 1863: 1852: 1843: 1820: 1817: 1811: 1810: 1808: 1806: 1800: 1789: 1780: 1774: 1773: 1757: 1747: 1738: 1737: 1719: 1692: 1691: 1673: 1667: 1666: 1646: 1640: 1638: 1636: 1634: 1614: 1608: 1607: 1605: 1603: 1597: 1591:. Archived from 1580: 1569: 1550: 1549: 1547: 1545: 1517: 1481:Segmental bridge 1372: 1356: 1340: 1324: 1308: 1292: 1276: 1260: 1244: 1228: 1084:Civil structures 1068: 1049: 1030: 1011: 992: 977:Kai Tak Terminal 973: 955: 939: 920: 493: 482: 460:pressure-grouted 271:precast concrete 257:hollow-core slab 4571: 4570: 4566: 4565: 4564: 4562: 4561: 4560: 4531: 4530: 4527: 4522: 4504: 4488: 4457: 4411: 4348: 4220: 4174: 4093: 4069:Flow table test 4030: 3950: 3912: 3907: 3857: 3852: 3851: 3841: 3839: 3830: 3829: 3825: 3815: 3813: 3804: 3803: 3799: 3789: 3787: 3778: 3777: 3773: 3763: 3761: 3752: 3751: 3747: 3740: 3736: 3726: 3724: 3720: 3697: 3691: 3687: 3677: 3675: 3671: 3660: 3656: 3655: 3651: 3641: 3639: 3624: 3620: 3610: 3608: 3604: 3598:www.cmnzl.co.nz 3593: 3587: 3583: 3573: 3571: 3567: 3560: 3552: 3548: 3538: 3536: 3523: 3522: 3518: 3508: 3506: 3502: 3496: 3485: 3477: 3470: 3460: 3458: 3451: 3435: 3431: 3421: 3419: 3412: 3396: 3389: 3379: 3377: 3370: 3354: 3350: 3340: 3338: 3331: 3315: 3311: 3301: 3299: 3295: 3276: 3270: 3266: 3255: 3251: 3241: 3239: 3232:10.1139/l96-925 3212: 3208: 3198: 3196: 3192: 3181: 3175: 3171: 3134: 3130: 3120: 3118: 3114: 3091: 3085: 3081: 3071: 3069: 3042: 3038: 3028: 3026: 3022: 3015: 3007: 3003: 2993: 2991: 2987: 2976: 2970: 2966: 2956: 2954: 2946: 2945: 2941: 2931: 2929: 2914: 2910: 2900: 2898: 2885: 2884: 2880: 2870: 2868: 2853: 2849: 2839: 2837: 2830: 2814: 2810: 2800: 2798: 2794: 2783: 2777:Tang, Man-Chung 2774: 2770: 2760: 2758: 2754: 2743: 2737: 2733: 2723: 2721: 2717: 2702: 2696: 2692: 2682: 2680: 2676: 2661: 2655: 2651: 2641: 2639: 2612: 2608: 2598: 2596: 2581: 2577: 2567: 2565: 2550: 2546: 2536: 2534: 2519: 2515: 2505: 2503: 2499: 2488: 2482: 2478: 2468: 2466: 2462: 2439: 2433: 2429: 2419: 2417: 2404: 2403: 2399: 2389: 2387: 2383: 2372: 2366: 2362: 2352: 2350: 2346: 2335: 2329: 2325: 2315: 2313: 2304: 2303: 2299: 2290: 2289: 2285: 2275: 2273: 2258: 2254: 2244: 2242: 2231: 2227: 2217: 2215: 2200: 2196: 2186: 2184: 2177:www.ukcares.com 2169: 2165: 2155: 2153: 2146: 2130: 2126: 2116: 2114: 2107: 2091: 2087: 2077: 2075: 2071: 2040: 2034: 2027: 2017: 2015: 2011: 2000: 1994: 1990: 1980: 1978: 1974: 1959: 1953: 1949: 1939: 1937: 1918: 1914: 1904: 1902: 1898: 1887: 1881: 1877: 1867: 1865: 1861: 1850: 1844: 1823: 1818: 1814: 1804: 1802: 1798: 1787: 1781: 1777: 1770: 1748: 1741: 1734: 1720: 1695: 1688: 1674: 1670: 1663: 1647: 1643: 1632: 1630: 1615: 1611: 1601: 1599: 1595: 1589: 1578: 1570: 1553: 1543: 1541: 1534: 1518: 1495: 1490: 1485: 1435: 1387: 1380: 1378: 1373: 1364: 1362: 1357: 1348: 1346: 1341: 1332: 1330: 1325: 1316: 1314: 1309: 1300: 1299:Toronto, Canada 1298: 1293: 1284: 1282: 1280:Ostankino Tower 1277: 1268: 1266: 1261: 1252: 1250: 1245: 1236: 1235:Brisbane, Aust. 1234: 1229: 1209:Ostankino Tower 1187:, South Korea; 1173: 1156: 1147: 1145:Silos and tanks 1134: 1091: 1086: 1079: 1075: 1069: 1060: 1056: 1050: 1041: 1037: 1031: 1022: 1018: 1015:Ocean Heights 2 1012: 1003: 999: 993: 984: 979: 974: 965: 961: 956: 947: 943: 940: 931: 927: 921: 907:, Croatia; and 893:Ocean Heights 2 861: 855: 850: 845: 834: 825: 817: 802: 792: 780: 770: 746: 730:A single-span, 729: 719: 701: 695: 686: 671: 555: 504: 503: 502: 501: 496: 495: 494: 485: 484: 483: 472: 400: 314: 216:static friction 192: 168:post-tensioning 49: 17: 12: 11: 5: 4569: 4559: 4558: 4553: 4548: 4543: 4524: 4523: 4521: 4520: 4509: 4506: 4505: 4503: 4502: 4496: 4494: 4490: 4489: 4487: 4486: 4481: 4476: 4471: 4465: 4463: 4459: 4458: 4456: 4455: 4450: 4445: 4440: 4435: 4430: 4425: 4419: 4417: 4413: 4412: 4410: 4409: 4404: 4399: 4394: 4389: 4387:Concrete block 4384: 4383: 4382: 4377: 4375:voided biaxial 4372: 4367: 4356: 4354: 4350: 4349: 4347: 4346: 4345: 4344: 4339: 4331: 4326: 4321: 4316: 4311: 4306: 4301: 4296: 4291: 4286: 4281: 4276: 4271: 4266: 4261: 4256: 4251: 4246: 4241: 4236: 4230: 4228: 4222: 4221: 4219: 4218: 4213: 4208: 4203: 4198: 4193: 4188: 4182: 4180: 4176: 4175: 4173: 4172: 4167: 4162: 4157: 4152: 4147: 4142: 4137: 4132: 4127: 4122: 4117: 4112: 4107: 4101: 4099: 4095: 4094: 4092: 4091: 4086: 4081: 4079:Concrete cover 4076: 4071: 4066: 4061: 4056: 4051: 4049:Concrete mixer 4046: 4040: 4038: 4032: 4031: 4029: 4028: 4023: 4018: 4013: 4008: 4003: 3998: 3993: 3988: 3987: 3986: 3981: 3976: 3971: 3960: 3958: 3952: 3951: 3949: 3948: 3943: 3938: 3936:Roman concrete 3933: 3928: 3922: 3920: 3914: 3913: 3906: 3905: 3898: 3891: 3883: 3877: 3876: 3871: 3863: 3856: 3855:External links 3853: 3850: 3849: 3823: 3797: 3771: 3745: 3734: 3685: 3649: 3618: 3581: 3546: 3516: 3494: 3468: 3449: 3429: 3410: 3387: 3368: 3348: 3329: 3309: 3264: 3249: 3206: 3169: 3128: 3079: 3036: 3001: 2964: 2939: 2908: 2878: 2847: 2828: 2808: 2768: 2731: 2690: 2649: 2606: 2575: 2544: 2513: 2493:vslvietnam.com 2476: 2427: 2397: 2360: 2323: 2297: 2294:. 8 July 2014. 2283: 2268:. Freyssinet. 2252: 2225: 2194: 2163: 2144: 2124: 2105: 2085: 2025: 1988: 1947: 1912: 1875: 1821: 1812: 1775: 1768: 1739: 1732: 1693: 1686: 1668: 1661: 1641: 1609: 1587: 1551: 1532: 1492: 1491: 1489: 1486: 1484: 1483: 1478: 1473: 1468: 1463: 1458: 1453: 1448: 1442: 1436: 1434: 1431: 1430: 1429: 1423: 1416: 1398:building codes 1386: 1383: 1382: 1381: 1374: 1367: 1365: 1358: 1351: 1349: 1347:Washington, US 1342: 1335: 1333: 1326: 1319: 1317: 1315:Brevik, Norway 1310: 1303: 1301: 1294: 1287: 1285: 1283:Moscow, Russia 1278: 1271: 1269: 1262: 1255: 1253: 1248:Incheon Bridge 1246: 1239: 1237: 1232:Gateway Bridge 1230: 1223: 1185:Incheon Bridge 1181:Gateway Bridge 1172: 1169: 1155: 1152: 1146: 1143: 1133: 1130: 1090: 1087: 1085: 1082: 1081: 1080: 1070: 1063: 1061: 1051: 1044: 1042: 1032: 1025: 1023: 1013: 1006: 1004: 994: 987: 985: 975: 968: 966: 957: 950: 948: 941: 934: 932: 922: 915: 865: 864: 858: 857:"cycle-times". 852: 847: 833: 830: 824: 821: 820: 819: 810: 804: 799: 795:de-icing salts 786: 773: 764: 753:concrete cover 743: 722: 721: 716: 698: 692: 670: 667: 666: 665: 649: 645: 642:concrete cover 638: 631: 626:Improved site 624: 615:Ability to be 609: 608: 604: 593: 590:yield strength 570: 554: 551: 538: 537: 534: 498: 497: 488: 487: 486: 477: 476: 475: 474: 473: 471: 468: 399: 396: 313: 310: 234:prefabrication 212:tension forces 191: 188: 164:pre-tensioning 129:concrete slabs 127:, residential 105:serviceability 101:tension forces 48: 47: 44: 41: 38: 35: 32: 28: 15: 9: 6: 4: 3: 2: 4568: 4557: 4554: 4552: 4549: 4547: 4544: 4542: 4539: 4538: 4536: 4529: 4519: 4511: 4510: 4507: 4501: 4498: 4497: 4495: 4491: 4485: 4482: 4480: 4477: 4475: 4472: 4470: 4467: 4466: 4464: 4460: 4454: 4451: 4449: 4446: 4444: 4441: 4439: 4436: 4434: 4431: 4429: 4426: 4424: 4421: 4420: 4418: 4416:Organizations 4414: 4408: 4405: 4403: 4400: 4398: 4395: 4393: 4390: 4388: 4385: 4381: 4380:slab on grade 4378: 4376: 4373: 4371: 4368: 4366: 4363: 4362: 4361: 4358: 4357: 4355: 4351: 4343: 4340: 4338: 4335: 4334: 4332: 4330: 4327: 4325: 4322: 4320: 4317: 4315: 4312: 4310: 4309:Self-leveling 4307: 4305: 4302: 4300: 4297: 4295: 4292: 4290: 4287: 4285: 4282: 4280: 4277: 4275: 4272: 4270: 4267: 4265: 4262: 4260: 4257: 4255: 4252: 4250: 4247: 4245: 4242: 4240: 4237: 4235: 4232: 4231: 4229: 4227: 4223: 4217: 4214: 4212: 4209: 4207: 4204: 4202: 4199: 4197: 4194: 4192: 4189: 4187: 4184: 4183: 4181: 4177: 4171: 4168: 4166: 4163: 4161: 4158: 4156: 4153: 4151: 4148: 4146: 4143: 4141: 4138: 4136: 4133: 4131: 4128: 4126: 4123: 4121: 4118: 4116: 4113: 4111: 4110:Cast-in-place 4108: 4106: 4103: 4102: 4100: 4096: 4090: 4087: 4085: 4082: 4080: 4077: 4075: 4072: 4070: 4067: 4065: 4062: 4060: 4057: 4055: 4052: 4050: 4047: 4045: 4042: 4041: 4039: 4037: 4033: 4027: 4024: 4022: 4019: 4017: 4014: 4012: 4009: 4007: 4006:Reinforcement 4004: 4002: 3999: 3997: 3994: 3992: 3989: 3985: 3982: 3980: 3977: 3975: 3972: 3970: 3967: 3966: 3965: 3962: 3961: 3959: 3957: 3953: 3947: 3944: 3942: 3939: 3937: 3934: 3932: 3929: 3927: 3924: 3923: 3921: 3919: 3915: 3911: 3904: 3899: 3897: 3892: 3890: 3885: 3884: 3881: 3875: 3872: 3870: 3867: 3864: 3862: 3859: 3858: 3837: 3833: 3827: 3811: 3807: 3801: 3785: 3781: 3775: 3759: 3755: 3749: 3743: 3738: 3719: 3715: 3711: 3707: 3703: 3696: 3689: 3670: 3666: 3659: 3653: 3637: 3633: 3629: 3622: 3603: 3599: 3592: 3585: 3566: 3559: 3558: 3550: 3534: 3530: 3526: 3520: 3501: 3497: 3495:0-07-063444-0 3491: 3484: 3483: 3475: 3473: 3456: 3452: 3450:0-471-53915-5 3446: 3442: 3441: 3433: 3417: 3413: 3407: 3403: 3402: 3394: 3392: 3375: 3371: 3365: 3361: 3360: 3352: 3336: 3332: 3326: 3322: 3321: 3313: 3294: 3290: 3286: 3282: 3275: 3268: 3260: 3253: 3237: 3233: 3229: 3225: 3221: 3217: 3210: 3191: 3187: 3180: 3173: 3164: 3159: 3155: 3151: 3147: 3143: 3139: 3132: 3113: 3109: 3105: 3101: 3097: 3090: 3083: 3067: 3063: 3059: 3055: 3051: 3047: 3040: 3021: 3014: 3013: 3005: 2986: 2982: 2975: 2968: 2953: 2949: 2943: 2928: 2927: 2922: 2918: 2912: 2896: 2892: 2888: 2882: 2866: 2862: 2858: 2851: 2835: 2831: 2825: 2821: 2820: 2812: 2793: 2789: 2782: 2778: 2772: 2753: 2749: 2748:CTBUH Journal 2742: 2735: 2716: 2712: 2708: 2701: 2694: 2675: 2671: 2667: 2660: 2653: 2637: 2633: 2629: 2625: 2621: 2617: 2610: 2594: 2590: 2586: 2579: 2563: 2559: 2555: 2548: 2532: 2528: 2524: 2517: 2498: 2494: 2487: 2480: 2461: 2457: 2453: 2450:(3): 84–111. 2449: 2445: 2438: 2431: 2415: 2411: 2407: 2401: 2382: 2378: 2371: 2364: 2345: 2341: 2334: 2327: 2311: 2307: 2301: 2293: 2287: 2271: 2267: 2263: 2256: 2240: 2236: 2229: 2213: 2209: 2205: 2198: 2182: 2178: 2174: 2167: 2151: 2147: 2141: 2137: 2136: 2128: 2112: 2108: 2102: 2098: 2097: 2089: 2070: 2066: 2062: 2058: 2054: 2050: 2046: 2039: 2032: 2030: 2010: 2006: 1999: 1992: 1973: 1969: 1965: 1958: 1951: 1935: 1931: 1927: 1923: 1916: 1897: 1893: 1886: 1879: 1860: 1856: 1849: 1842: 1840: 1838: 1836: 1834: 1832: 1830: 1828: 1826: 1816: 1797: 1793: 1786: 1779: 1771: 1769:0-9778752-0-2 1765: 1761: 1756: 1755: 1746: 1744: 1735: 1733:0-582-71225-4 1729: 1725: 1718: 1716: 1714: 1712: 1710: 1708: 1706: 1704: 1702: 1700: 1698: 1689: 1687:0-582-80247-4 1683: 1679: 1672: 1664: 1662:0-691-02393-X 1658: 1654: 1653: 1645: 1628: 1624: 1620: 1613: 1594: 1590: 1584: 1577: 1576: 1568: 1566: 1564: 1562: 1560: 1558: 1556: 1539: 1535: 1533:0-471-01898-8 1529: 1525: 1524: 1516: 1514: 1512: 1510: 1508: 1506: 1504: 1502: 1500: 1498: 1493: 1482: 1479: 1477: 1474: 1472: 1469: 1467: 1464: 1462: 1459: 1457: 1454: 1452: 1449: 1446: 1443: 1441: 1438: 1437: 1427: 1424: 1421: 1417: 1414: 1410: 1406: 1405: 1404: 1401: 1399: 1394: 1392: 1377: 1371: 1366: 1361: 1355: 1350: 1345: 1339: 1334: 1329: 1323: 1318: 1313: 1307: 1302: 1297: 1291: 1286: 1281: 1275: 1270: 1265: 1259: 1254: 1249: 1243: 1238: 1233: 1227: 1222: 1221: 1220: 1218: 1214: 1210: 1206: 1202: 1198: 1194: 1190: 1186: 1182: 1177: 1168: 1166: 1160: 1151: 1142: 1138: 1129: 1127: 1123: 1119: 1116: 1112: 1107: 1105: 1101: 1097: 1078: 1077:18° lean 2010 1073: 1067: 1062: 1059: 1054: 1053:Torre Espacio 1048: 1043: 1040: 1035: 1029: 1024: 1021: 1016: 1010: 1005: 1002: 997: 991: 986: 983: 978: 972: 967: 964: 960: 954: 949: 946: 938: 933: 930: 925: 919: 914: 913: 912: 910: 906: 902: 901:Torre Espacio 899:, Melbourne; 898: 894: 891:, Hong Kong; 890: 886: 882: 878: 874: 870: 859: 853: 848: 843: 842: 841: 838: 829: 815: 811: 808: 805: 800: 796: 790: 787: 784: 778: 774: 768: 765: 762: 758: 754: 750: 744: 741: 737: 733: 727: 726: 725: 717: 714: 709: 705: 699: 693: 690: 684: 683: 682: 679: 675: 663: 659: 655: 650: 646: 643: 639: 636: 632: 629: 625: 622: 618: 617:prefabricated 614: 613: 612: 605: 602: 598: 594: 591: 587: 583: 579: 575: 571: 568: 564: 563: 562: 559: 550: 547: 542: 535: 532: 531: 530: 527: 525: 521: 517: 513: 509: 492: 481: 467: 465: 461: 457: 452: 450: 446: 442: 438: 433: 428: 426: 422: 418: 415: 414: 404: 395: 393: 389: 384: 382: 378: 374: 370: 366: 362: 353: 349: 347: 343: 337: 335: 326: 318: 309: 307: 304:and concrete 303: 299: 295: 291: 287: 283: 278: 276: 272: 267: 258: 253: 249: 247: 243: 238: 235: 228: 223: 219: 217: 213: 209: 205: 196: 187: 185: 181: 177: 173: 169: 165: 160: 158: 154: 150: 146: 142: 138: 134: 130: 126: 122: 118: 113: 110: 106: 102: 98: 94: 90: 86: 82: 79:, multi-wire 78: 74: 69: 67: 63: 59: 56:is a form of 55: 45: 42: 39: 36: 33: 30: 29: 26: 21: 4528: 4392:Step barrier 4353:Applications 4283: 4264:Nanoconcrete 4150:Power trowel 4135:Power screed 4125:Slip forming 4098:Construction 3842:12 September 3840:. Retrieved 3826: 3816:12 September 3814:. Retrieved 3800: 3790:12 September 3788:. Retrieved 3774: 3764:12 September 3762:. Retrieved 3748: 3737: 3725:. Retrieved 3708:(4): 18–43. 3705: 3701: 3688: 3676:. Retrieved 3664: 3652: 3640:. Retrieved 3631: 3621: 3609:. Retrieved 3597: 3584: 3572:. Retrieved 3556: 3549: 3537:. Retrieved 3528: 3519: 3507:. Retrieved 3481: 3459:. Retrieved 3439: 3432: 3420:. Retrieved 3400: 3378:. Retrieved 3358: 3351: 3339:. Retrieved 3319: 3312: 3300:. Retrieved 3280: 3267: 3258: 3252: 3240:. Retrieved 3223: 3219: 3209: 3197:. Retrieved 3185: 3172: 3145: 3141: 3131: 3119:. Retrieved 3099: 3095: 3082: 3070:. Retrieved 3066:the original 3056:(5): 52–80. 3053: 3049: 3039: 3027:. Retrieved 3011: 3004: 2992:. Retrieved 2980: 2967: 2955:. Retrieved 2951: 2942: 2930:. Retrieved 2924: 2911: 2899:. Retrieved 2895:the original 2881: 2869:. Retrieved 2860: 2850: 2838:. Retrieved 2818: 2811: 2799:. Retrieved 2787: 2771: 2759:. Retrieved 2747: 2734: 2722:. Retrieved 2710: 2706: 2693: 2681:. Retrieved 2669: 2665: 2652: 2640:. Retrieved 2623: 2619: 2609: 2597:. Retrieved 2588: 2578: 2566:. Retrieved 2558:www.cmecs.co 2557: 2547: 2535:. Retrieved 2527:www.arup.com 2526: 2516: 2504:. Retrieved 2492: 2479: 2467:. Retrieved 2447: 2443: 2430: 2418:. Retrieved 2409: 2400: 2388:. Retrieved 2376: 2363: 2351:. Retrieved 2340:ashet.org.au 2339: 2326: 2314:. Retrieved 2300: 2286: 2274:. Retrieved 2265: 2260:Freyssinet. 2255: 2243:. Retrieved 2228: 2216:. Retrieved 2212:the original 2208:www.nace.org 2207: 2197: 2185:. Retrieved 2176: 2166: 2154:. Retrieved 2134: 2127: 2115:. Retrieved 2095: 2088: 2076:. Retrieved 2051:(5): 34–55. 2048: 2044: 2016:. Retrieved 2004: 1991: 1979:. Retrieved 1967: 1963: 1950: 1938:. Retrieved 1929: 1925: 1915: 1903:. Retrieved 1891: 1878: 1866:. Retrieved 1854: 1815: 1803:. Retrieved 1791: 1778: 1753: 1723: 1677: 1671: 1651: 1644: 1631:. Retrieved 1622: 1612: 1600:. Retrieved 1593:the original 1574: 1542:. Retrieved 1522: 1447:AG (Dywidag) 1418:US Standard 1402: 1395: 1388: 1328:Roseires Dam 1312:Norcem silos 1264:Autobahn A73 1201:Cement silos 1189:Roseires Dam 1178: 1174: 1161: 1157: 1148: 1139: 1135: 1114: 1108: 1096:Adam Viaduct 1092: 1076: 1072:Capital Gate 1057: 1038: 1034:Eureka Tower 1019: 1000: 981: 962: 944: 928: 909:Capital Gate 897:Eureka Tower 866: 839: 835: 826: 823:Applications 755:in the side 739: 723: 713:polyethylene 680: 676: 672: 628:productivity 610: 560: 556: 543: 539: 528: 514:-inhibiting 508:longitudinal 505: 453: 437:polyethylene 431: 429: 411: 409: 385: 380: 372: 368: 358: 338: 333: 331: 279: 265: 262: 259:being placed 246:surface area 239: 231: 203: 201: 183: 179: 176:multi-strand 175: 171: 161: 143:structures, 114: 93:aramid fiber 89:carbon fiber 70: 53: 52: 4370:hollow-core 4329:Waste light 4324:Translucent 4284:Prestressed 4211:Segregation 4196:Degradation 4084:Cover meter 4021:Silica fume 3956:Composition 3727:6 September 3702:PCI Journal 3678:6 September 3642:2 September 3634:. DYWIDAG. 3611:2 September 3574:5 September 3539:5 September 3509:5 September 3461:5 September 3422:5 September 3380:5 September 3341:5 September 3302:5 September 3281:PCI Journal 3242:2 September 3199:2 September 3148:(1): 1–13. 3121:2 September 3096:PCI Journal 3072:7 September 3050:PCI Journal 3029:7 September 2994:2 September 2957:22 February 2861:Railway Age 2840:2 September 2801:5 September 2761:2 September 2724:2 September 2683:2 September 2642:1 September 2599:1 September 2568:1 September 2537:2 September 2506:1 September 2469:2 September 2444:PCI Journal 2420:1 September 2390:1 September 2353:1 September 2276:7 September 2218:7 September 2187:7 September 2156:7 September 2117:7 September 2078:7 September 2045:PCI Journal 2018:7 September 2005:PCI Journal 1964:PTI Journal 1344:Wanapum Dam 1251:South Korea 1193:Wanapum Dam 1104:box girders 1074:, Abu Dhabi 1036:, Melbourne 996:World Tower 926:, Hong Kong 883:, Toronto; 873:World Tower 708:stay-cables 662:deformation 648:in-service. 635:flexibility 342:split-wedge 302:water tanks 286:floor slabs 166:to include 4535:Categories 4469:Eurocode 2 4407:Structures 4294:Reinforced 4254:Lunarcrete 4234:AstroCrete 4191:Durability 4186:Properties 4064:Slump test 4036:Production 4026:Metakaolin 3188:. IEAust. 2410:cclint.com 2245:3 December 1488:References 1411:-2:2005 – 980:Hong Kong 879:, London; 875:, Sydney; 863:materials. 704:monitoring 572:Increased 524:tensioning 518:, usually 441:galvanised 361:galvanised 172:monostrand 73:tensioning 68:in 1928. 62:compressed 4500:Hempcrete 4462:Standards 4289:Ready-mix 4206:Recycling 4001:Aggregate 3984:Rosendale 3626:DYWIDAG. 3283:: 64–85. 3102:: 76–88. 2932:25 August 2901:25 August 2871:25 August 2713:: 37–41. 2632:0439-5689 2560:. CMECS. 2377:ctbuh.org 2342:. ASHET. 2179:. CARES. 2065:109223938 2007:: 62–73. 1981:25 August 1940:22 August 1905:25 August 1868:23 August 1805:19 August 1633:25 August 1602:26 August 1544:24 August 1466:PC strand 1360:LNG tanks 1197:LNG tanks 1191:, Sudan; 1058:230m 2008 1039:297m 2006 1020:335m 2016 1001:230m 2004 945:290m 2016 929:484m 2010 924:ICC tower 895:, Dubai; 816:, England 814:Liverpool 761:corrosion 757:abutments 736:Corrosion 654:ductility 621:lead time 546:extrusion 512:corrosion 500:recesses. 464:corrosion 421:corrosion 388:curvature 296:, driven 290:balconies 266:deviators 4493:See also 4484:EN 10080 4479:EN 206-1 4474:EN 197-1 4333:Aerated 4274:Polished 4269:Pervious 4244:Filigree 4140:Finisher 4115:Formwork 3979:Portland 3910:Concrete 3836:Archived 3810:Archived 3784:Archived 3758:Archived 3718:Archived 3669:Archived 3636:Archived 3602:Archived 3565:Archived 3533:Archived 3500:Archived 3455:Archived 3416:Archived 3374:Archived 3335:Archived 3293:Archived 3236:Archived 3190:Archived 3112:Archived 3020:Archived 2985:Archived 2865:Archived 2834:Archived 2792:Archived 2779:(2007). 2752:Archived 2715:Archived 2707:Connaect 2674:Archived 2666:Connaect 2636:Archived 2593:Archived 2562:Archived 2531:Archived 2529:. ARUP. 2497:Archived 2460:Archived 2414:Archived 2381:Archived 2344:Archived 2310:Archived 2270:Archived 2239:Archived 2181:Archived 2150:Archived 2111:Archived 2069:Archived 2009:Archived 1972:Archived 1934:Archived 1896:Archived 1894:(2–01). 1859:Archived 1796:Archived 1792:MaineDOT 1627:Archived 1538:Archived 1433:See also 1413:Eurocode 1296:CN Tower 1213:CN Tower 1055:, Madrid 998:, Sydney 881:CN Tower 783:chemical 772:in 1996. 658:catenary 640:Reduced 597:cracking 456:formwork 445:building 417:grouting 392:reaction 381:unbonded 365:grouting 346:threaded 242:adhesion 227:formwork 58:concrete 4443:Nanocem 4402:Columns 4279:Polymer 4179:Science 4145:Grinder 4105:Precast 4011:Fly ash 3918:History 3150:Bibcode 2822:. ICE. 2495:. VSL. 2412:. CCL. 2316:8 April 2171:CARES. 1581:. FIB. 1409:EN 1992 1115:in-situ 1111:girders 1089:Bridges 1017:, Dubai 740:in-situ 697:tendon. 586:tensile 582:strains 578:flexure 520:lithium 432:bundles 413:in situ 377:greased 294:lintels 184:outside 81:strands 4365:waffle 4314:Sulfur 4170:Tremie 4165:Sealer 4130:Screed 4074:Curing 3964:Cement 3492:  3447:  3408:  3366:  3327:  2826:  2750:(11). 2672:: 51. 2630:  2521:ARUP. 2202:NACE. 2142:  2103:  2063:  1932:(19). 1766:  1730:  1684:  1659:  1585:  1530:  1420:ACI318 769:, 1992 516:grease 369:bonded 180:within 137:bridge 4397:Roads 4319:Tabby 4226:Types 4160:Float 4089:Rebar 4044:Plant 3991:Water 3721:(PDF) 3698:(PDF) 3672:(PDF) 3661:(PDF) 3605:(PDF) 3594:(PDF) 3568:(PDF) 3561:(PDF) 3503:(PDF) 3486:(PDF) 3296:(PDF) 3277:(PDF) 3193:(PDF) 3182:(PDF) 3115:(PDF) 3092:(PDF) 3023:(PDF) 3016:(PDF) 2988:(PDF) 2977:(PDF) 2795:(PDF) 2790:: 7. 2784:(PDF) 2755:(PDF) 2744:(PDF) 2718:(PDF) 2703:(PDF) 2677:(PDF) 2662:(PDF) 2500:(PDF) 2489:(PDF) 2484:VSL. 2463:(PDF) 2440:(PDF) 2384:(PDF) 2373:(PDF) 2347:(PDF) 2336:(PDF) 2072:(PDF) 2061:S2CID 2041:(PDF) 2012:(PDF) 2001:(PDF) 1975:(PDF) 1960:(PDF) 1899:(PDF) 1888:(PDF) 1862:(PDF) 1851:(PDF) 1799:(PDF) 1788:(PDF) 1762:–54. 1596:(PDF) 1579:(PDF) 798:2015. 607:ones. 601:rebar 567:grout 439:) or 334:after 306:pipes 298:piles 282:beams 208:cures 204:prior 149:tanks 145:silos 117:spans 77:wires 4360:Slab 4342:RAAC 4259:Mass 4249:Foam 4155:Pump 3844:2016 3818:2016 3792:2016 3766:2016 3729:2016 3680:2016 3644:2016 3613:2016 3576:2016 3541:2016 3511:2016 3490:ISBN 3463:2016 3445:ISBN 3424:2016 3406:ISBN 3382:2016 3364:ISBN 3343:2016 3325:ISBN 3304:2016 3244:2016 3201:2016 3123:2016 3074:2016 3031:2016 2996:2016 2959:2024 2934:2018 2903:2018 2873:2018 2842:2016 2824:ISBN 2803:2016 2763:2016 2726:2016 2685:2016 2644:2016 2628:ISSN 2601:2016 2570:2016 2539:2016 2508:2016 2471:2016 2422:2016 2392:2016 2355:2016 2318:2021 2278:2016 2247:2012 2220:2016 2189:2016 2158:2016 2140:ISBN 2119:2016 2101:ISBN 2080:2016 2020:2016 1983:2016 1942:2016 1907:2016 1870:2016 1807:2016 1764:ISBN 1728:ISBN 1682:ISBN 1657:ISBN 1635:2016 1604:2016 1583:ISBN 1546:2016 1528:ISBN 1132:Dams 1120:and 982:2013 963:1973 887:and 871:and 155:and 147:and 139:and 25:beam 4337:AAC 3710:doi 3285:doi 3228:doi 3158:doi 3104:doi 3058:doi 2452:doi 2053:doi 576:in 449:dam 141:dam 91:or 4537:: 3834:. 3808:. 3782:. 3756:. 3716:. 3706:10 3704:. 3700:. 3663:. 3630:. 3600:. 3596:. 3527:. 3498:. 3471:^ 3453:. 3414:. 3390:^ 3372:. 3333:. 3291:. 3279:. 3234:. 3224:23 3222:. 3218:. 3184:. 3156:. 3144:. 3140:. 3110:. 3100:10 3098:. 3094:. 3054:32 3052:. 3048:. 2979:. 2950:. 2923:. 2919:. 2889:. 2859:. 2832:. 2786:. 2746:. 2711:10 2709:. 2705:. 2670:10 2668:. 2664:. 2634:. 2624:59 2622:. 2618:. 2587:. 2556:. 2525:. 2491:. 2458:. 2448:21 2446:. 2442:. 2408:. 2375:. 2338:. 2308:. 2264:. 2206:. 2175:. 2148:. 2109:. 2067:. 2059:. 2049:37 2047:. 2043:. 2028:^ 2003:. 1966:. 1962:. 1930:87 1928:. 1924:. 1890:. 1853:. 1824:^ 1794:. 1790:. 1742:^ 1696:^ 1621:. 1554:^ 1536:. 1496:^ 1128:. 1100:UK 466:. 373:de 308:. 300:, 292:, 284:, 218:. 159:. 151:, 135:, 131:, 87:, 3902:e 3895:t 3888:v 3846:. 3820:. 3794:. 3768:. 3731:. 3712:: 3682:. 3646:. 3615:. 3578:. 3543:. 3513:. 3465:. 3426:. 3384:. 3345:. 3306:. 3287:: 3246:. 3230:: 3203:. 3166:. 3160:: 3152:: 3146:7 3125:. 3106:: 3076:. 3060:: 3033:. 2998:. 2961:. 2936:. 2905:. 2875:. 2844:. 2805:. 2765:. 2728:. 2687:. 2646:. 2603:. 2572:. 2541:. 2510:. 2473:. 2454:: 2424:. 2394:. 2357:. 2320:. 2280:. 2249:. 2222:. 2191:. 2160:. 2121:. 2082:. 2055:: 2022:. 1985:. 1968:8 1944:. 1909:. 1872:. 1809:. 1772:. 1760:5 1736:. 1690:. 1665:. 1637:. 1606:. 1548:.

Index

six figures showing forces and resulting deflection of beam
beam
concrete
compressed
Eugène Freyssinet
tensioning
wires
strands
high-tensile steels
carbon fiber
aramid fiber
compression forces
tension forces
serviceability
reinforced concrete
spans
reinforced concrete
high-rise buildings
concrete slabs
foundation systems
bridge
dam
silos
tanks
industrial pavements
nuclear containment structures
pre-tensioning
post-tensioning
three figures; darker green slab is pre-tensioned in lighter green casting bed
cures

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.